History
  • No items yet
midpage
Brooke Drywall of Columbia, Inc. v. Building Construction Enterprises, Inc.
361 S.W.3d 22
Mo. Ct. App.
2011
Read the full case

Background

  • Contractor obtained a Missouri University project and obtained a surety bond from Hartford Fire Insurance Company.
  • Subcontractor Brooke Drywall performed part of the work but was not fully paid due to delays caused by steel shortages.
  • The University withheld payment to Contractor, who in turn withheld from Subcontractor; Subcontractor demanded final payment in spring 2005.
  • The subcontract contained an interest provision: unpaid payments bear interest from due date; and a prevailing-party attorney fees provision for disputes.
  • After litigation, the principal was settled for the full amount; interest and attorneys' fees were reserved for court decision.
  • The circuit court ruled Subcontractor entitled to interest and to attorneys' fees, and Hartford Insurance was liable for those fees; appeal followed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Interest on principal amount Subcontractor entitled to interest from due date per contract Interest only under prejudgment statutes; not applicable here Subcontractor entitled to interest under contract terms
Prevailing party for attorneys' fees Litigation on interest sufficed to prevail; thus prevailing party Settlement for principal amount precludes prevailing-party status Subcontractor prevailed on interest issue and is prevailing party
Surety liability for attorneys' fees Bond broad enough to cover attorneys' fees as 'such payment due' Bond only covers payments for materials, labor, etc. Bond language broad enough to cover attorneys' fees; Surety liable

Key Cases Cited

  • Buckhannon Bd. & Care Home, Inc. v. W. Va. Dep't of Health & Human Res., 532 U.S. 598 (U.S. Supreme Court 2001) (prevailing party requires some relief; no mere settlement)
  • Marcomb v. Hartford Fire Ins. Co., 934 S.W.2d 17 (Mo. App. W.D. 1996) (attorneys' fees may be included where contract permits)
  • Knecht, Inc. v. United Pac. Ins. Co., 860 F.2d 74 (3d Cir. 1988) (bond scope limits on payments for labor/materials)
  • City of Kansas City ex rel. Jennings v. Integon Indem. Corp., 857 S.W.2d 233 (Mo. App. W.D. 1993) (surety liability generally coextensive with principal)
  • City of Independence ex rel. Briggs v. Kerr Constr. Paving Co., 957 S.W.2d 315 (Mo. App. W.D. 1997) (surety obligation limited to contract terms)
Read the full case

Case Details

Case Name: Brooke Drywall of Columbia, Inc. v. Building Construction Enterprises, Inc.
Court Name: Missouri Court of Appeals
Date Published: Dec 20, 2011
Citation: 361 S.W.3d 22
Docket Number: WD 73355
Court Abbreviation: Mo. Ct. App.