*2 SLOVITER, Before GREENBERG COWEN, Judges. Circuit OF THE COURT OPINION GREENBERG, Judge. Circuit appeal on This matter is before the court by defendant Pacific Insurance Company denying from an order its motion 59(e) pursuant to alter or to Fed.R.Civ.P. summary judgment entered in fa amend a Knecht, plaintiff Inc. and from an vor attorney’s for fees in this action on payment bond. The dis labor and material for sum judge trict ruled on cross-motions mary judgment that Knecht was entitled to scope our recover on the bond and thus plenary. review on this issue See Good F.2d man v. Meade Johnson & (3d Cir.1976), 429 U.S. cert. denied L.Ed.2d 748 97 S.Ct. summary judgment affirm the but We will fees. will reverse the order leading ap- undisputed facts to this 19,1983 peal are as follows. On November bond, i.e., Sordoni, International, Inc., owner, entered with the Knoll Construction into a contract with Sordoni or with a subcontractor of the contractor, of a for the construction reasonably and material used facility adjacent to assembly/shipping new quired of the contract. Greenville, Montgom- plant Knoll’s East provided princi- The bond further *3 Pennsylvania. This was a sub- ery County, pal surety agreed severally and jointly and with maximum cost project stantial unpaid every “may sue on claimant and, $14,700,000 surprisingly, Knoll of claimant, the use prose- this bond for complex. documents were the contract cute the suit to final for such judgment protection of Knoll from They provided for sum or sums as be due claim- also forth that claims and set lien “[i]f ant, and have execution The own- thereon. [Knoll], Contractor requested Owner er, pay- shall not be for the liable [Knoll] shall, cost, provide at Owner’s [Sordoni] any expenses any ment of costs or such (a) bonds to assure the surety bond or suit.” in full performance of the Work timely September On 1984 Sordoni and W.J. Drawings compliance with the Final and Ambrose, Inc. entered into subcontract (b) Project and Specifications for the incorporating the Knoll-Sordoni contract labor, materials, equipment assure that all providing perform and for Ambrose to incorporated into the Work or supplies and ventilating heating, conditioning and air employed in therewith will be connection project. work on the Knoll The Sordoni- in full. Such or bonds bond Ambrose subcontract included Article 19.1 sureties, issued amounts and will be provided that: which acceptable in com- on terms to Owner and ASSIGNMENT AND SUBCON- pliance the laws of Penn- State TRACTING. sylvania.” Agreement any Neither nor monies 28, 1983, anticipation On October due or to become due hereunder shall be contract, the execution of Knoll assignable prior without con- written stipulation barring made a lien sent of Contractor nor shall against property by [Sordoni] claims Sordoni and any part or subcontractor, materialman, whole of the Work be any workman prior person subcontracted without like written any any or labor or mate- stipula- Any assignment consent. such or supplied project. rial This sub- Montgom- contracting in the without prior tion was filed office of the such written ery County Prothonotary on November shall be void effect consent and of no pursuant apparently to section 402 of right right shall vest or of action in Mechanics’ Lien Law of assignee or sub-subcontractor (Purdon Pa.Stat.Ann. tit. against Contractor. Contrac- 1965). any consent to assignment tor’s or sub- contracting shall not relieve Subcon- November and Unit- On 1983 Sordoni any agree- tractor of its [Ambrose] ed, respectively surety, ments, duties, responsibilities or obli- payment a labor executed and material gations under this Agreement and the binding jointly and sever- themselves other Contract Documents and Sub- $14,700,000. ally to Knoll for The condi- shall fully contractor be and remain as incorporated tion of defaults, responsible and liable for the contract, Knoll-Sordoni was that if Sordoni neglects, assign- acts and of its omissions promptly “shall make to all claim- per- defined, ees and sub-subcontractors and all hereinafter all ants as directly indirectly employed by sons or reasonably required used and material or defaults, Contract, is for them as it ne- for use its own void; glects, acts and then this other- omissions and those shall officers, employees. it shall remain in force and ef- wise full own servants and fect____” A in the claimant was defined The Subcontractor shall each of its bind person as a permitted with a direct contract to all sub-subcontractors terms, of this Knecht’s. The order also provisions and covenants recited “that judgment is entered in favor Agreement plain- and the other Contract Doc- tiff and respect permitted subcon- defendant.” uments with 59(e) then moved Fed.R.Civ.P. portions of the Work. The Con- al- tracted judgment ter amend the or but this any subcontracting motion tractor’s consent order of was denied November shall not be deemed to create con- provided which also that United was to party beneficiary third rela- tractual or $134,784 with interest and that a tionship the Contractor between hearing would be later held to assess attor- Work, to whom the sub-subcontractor ney’s fees.2 On December 1987 the thereof, subcontracted, any portion judge testimony took on the issue of attor- any right and shall not vest ney’s judge fees. On March 1988 the action in such sub-subcontractor *4 $48,432.84 entered an order for for attor- the or the Owner Contractor [Knoll]. fees, ney’s the reciting that it was 18, entered On October Ambrose predicated of the bond per- Knecht to into a sub-subcontract with allowing recovery for all “sums ... on the Knoll form sheet metal work justly Thus, judge’s due.” in the view un- in- contract project. The Ambrose-Knecht less Knecht’s fees were allowed Knecht corporated the Sordoni-Ambrose “would not be made whole” and would not “principal referred to as which was all appeal recover sums due. This provided that Knecht was contract” and followed. by provisions bound Leaving aside award of contract.1 fees, might it be wondered on the basis of agree parties that work went for- our recitation issue by what could raised project payments and ward on the were is, all, appeal. on this United after clear by Knoll which in turn made to Sordoni agreed that and in the Ambrose, however, de- Ambrose. bring Knoll that a claimant with could obligations in its to Knecht fail- faulted against jointly them severally action or $134,784 pay due Knecht even to supplied the bond for labor and materials though requested and Ambrose received project. There is no doubt that Ultimately, for Knecht’s work. performed sup- Knecht the services and Knecht and three other creditors of Amb- plied the materials for which it seeks recov- involuntary petition in rose filed an bank- ery claimant and is a as defined ruptcy against Ambrose. bond, as it had a sub-subcontract with 1,May brought On 1986 Knecht this which was a subcontractor of Sor- Ambrose diversity action under law doni. United does not contend otherwise against United on the bond. The challenge computation nor does it Knecht’s summary judgment filed cross-motions for suggest pro- Knecht of its claim is judge, cedurally bringing and on October 1987 the district from this barred case. apparently opinion, without entered an or- it is true that Knecht as a While sub-sub- denying granting precluded by motion and contractor the contract der United’s was dispute print- undoubtedly 1. The Ambrose-Knecht contract was on a While there is a of fact on provided ed Ambrose form and that Ambrose point, purposes appeal accept this of this we materials, entering equipment its was order for United’s contention which seems to be accurate performed pursuant services to be and/or interpretation Knecht’s the Ambrose- as under prepared by contract documents the architect Thus, incorporated Knecht contract itself. engineer part of the as “contract between result, dispute of our of fact is not view AMBROSE, Knecht, (herein- WJ. INC. and Inc. material. CONTRACT) referred to as PRINCIPAL hereby part become a of the Contract as if judge hearing also ordered that a 2. The length set at attached hereto.” United forth damages punitive on Knecht’s claim for be held notwithstanding contends that this reference to but this claim was later dismissed on United’s contract, the Ambrose-Knecht it was the Sordo- cross-appealed motion. Knecht has not from incorporated. ni-Ambrose contract which was denying damages. punitive the order this, disputes contending that the Amb- says. contract means what it rose-Knecht Here, however, asserting against a lien claimants. documents and, along possible though incorporating property Knoll-Sordoni claimants, contract, filing a matter of law did condition against pro- surety liens in the either the to stipulation satisfaction office, obligations thonotary's nothing the bond under the Knoll-Sordoni con- tract, right way right to nor was the of a conditioned claimant’s claimant right to way ability under it on its to assert lien.3 related its claim Rather, Finally, agree- undertaking lien. while the Sordoni-Ambrose assert a right ment limited the a sub-subcontrac- Sordoni, for labor to make a claim claimants and material. also
tor See Security, made reference bond Restatement prejudiced express terms never under established law bring an United should be of a sub-subcontractor liable on bond. action United. plainly United seeks to avoid its
Accordingly,
point
obligation by advancing
the facts seem
stated
what
reached
in its
princi
same result
Penn
characterizes
brief as
basic
law,
ple of
Casualty
sylvania Supply Co. National
where
joint
Pa.Super.
and several with the
*5
greater
Superior
There the
Court of
will be no
than
principal.
that
that of
observes that
bring
held
a materialman could
general rule,
against
surety
surety
a
action
a
a
“[a]s
a bond which
extinguishment
ends
of the
building
obli
a
contractor was the
gation
Therefore,
principal.”
of his
obligee,
United
inasmuch
the owner was
as the
“a
contends that
determination as to
building
incorporated
contract and
damages
whether United
liable
required
contract
contractor-
requires
an examination as to
used
pay for
materials
right
any
whether Knecht has
of action
“[wjhat
project. The court observed that
against
points
Sordoni.” It then
that
out
may
prompted
obligee
require
have
quoted
under the above
Article
of the
19.1
protection
parties, also is unimpor
for third
contract,
Sordoni-Ambrose
a sub-subcon
stipulation
protected by
tant. She
was
party
tractor is not
a contractual or third
against
her
liens and
motives
have
beneficiary relationship with Sordoni and
sentimental,
altruistic
even
been
without
against
can have no
of action
either
affecting
obligation
surety.”
Accordingly,
Sordoni or Knoll.4
as Knecht
at
Pa.Super.
152
at
31 A.2d
against Sordoni,
can
no
assert
claim
Unit
Here,
owner, Knoll,
too, the
for reasons
ed,
surety,
cannot
Sordoni’s
be liable to
protec
not our concern obtained
support
contention,
In
Knecht.
Similarly,
tion for sub-subcontractors.
primarily
United relies
on Dravo-Doyle
Supreme
Pennsylvania in
Court of
Dravo-
Royal Indemnity
Co. v.
92
Pa.
Doyle
Royal Indemnity
Co. v.
372 Pa.
above,
A.2d
discussed
and McShain v.
(1952),
judge’s
filing
Ambrose’s sub-subcontractors
Pennsylvania found
Supreme
project.
lien claims on the
We
mechanic’s
receipt of
error in
evi-
there was an
emphasize
the Sordoni-Ambrose
pointed
out
against the
dence
agreement
incorporated into the
which was
axiomatic that “the
event it was
provid
Ambrose-Knecht
greater than that
liability of a
is not
ed that sub-subcontractors would
judgment in favor
and that a
of a
party beneficiary
or third
re
a contractual
*6
upon the merits of the case
lationship
and would have no
with Sordoni
by
sure-
as a defense
can be asserted
against
right of action
it.
118,
«1
plaintiff
written to
was entitled to
of how a bond could be
recover such
conceive
anything
“justly
sum
claimant
to sue for
as was
due.”
U.S.C.
authorize
270b(a).
justly due. We also ob-
The court noted
contrary
than a sum
that a
less
express provi-
result
in the
everyday
that in some contracts
context of
commer-
serve
litigation
fees
recovery
attorney’s
for
cial
would have
sion is made
obviated the
litigant
for a
Yet American rule that
in the event of an action
breach.
each
must bear
was made to
the cost of
legal representation.
in
no reference
its own
United’s bond
circumstances,
130-31,
we
In the
U.S. at
attorney’s fees.
S.Ct. at 2165-66.
While Rich is
recov-
attorney’s
binding
fees are not
conclude that
not
on us as we
law,
decide this case
Pennsylvania
in this action.
erable
it
extremely
nevertheless is
instructive. Cer-
Supreme
While we are directed to
tainly the reasoning in
Rich directly
con-
controlling our
Court of
case
trary to that of the
judge.
district
We also
result,
supports our conclusion.
precedent
point out that
previously predicted
we have
Industries v.
Ins.
Can-Tex
Safeco
in another context
Supreme
Court
(W.D.Pa.1978),
an action
Pennsylvania in announcing Pennsylva-
law,
the court
decided under
nia
Supreme
law would follow the
Court of
on a
bond on a
held that a
the United States. Aloe Coal
v.Co. Clark
construction contract conditioned on the
Equipment
(3d
117-19
money due
payment by the
of all
—
denied,
Cir.),
cert.
U.S. -,
108 S.Ct.
any claimant for labor or materials
«3
case,
Despite
only
apparently increasing
one
the
majority has cited
liberal
policy
respect,
though
and even
v. National
a
Pennsylvania Supply Co.
corporate surety in
profit
business for
31 A.2d
Pa.Super.
Casualty
law,’
a ‘favorite
position that
support
of its
Supply
Casualty
Co. v. National
liability
independent
is an
basis
there
supra,
bring myself
I cannot
to the con
However, this interme
the bond.
clusion that the
to the contract
court case has
distin
appellate
diate
been
and bond
suit intended to make Van[
repeatedly and cannot withstand
guished
third-party beneficiary
entitled
Cor
]
See,
strong language
e.g.,
of Dravo.
delay damages
recover for
such as here
Cor,
Casualty
Inc. v. American
Van
involved.
(1965) (per
cu
417 Pa.
417 Pa.
riam).
Cor,
(quoting
at. at
thority. The bond suretyship ciaries are under the bond which cooperate things, the subcontractor (as gave to Knoll Dravo and Van do), contractors. When sub Cor indicate we must it is clear that Cor, bankrupt, contractor became Van Sordoni did not intend Knecht to be a bene- contractor, ficiary, equally sued the general clear that Knecht did resulting beneficiary damages delay not consider itself a until Amb- caused subsequently example, In hold rose defaulted. For default. from the subcontractor’s Knecht, Knecht, Harry president C. tes- not an intended bene that Van Cor was rely tified that he did not bond, bond. Pennsylvania Su ficiary of the original While Knecht’s sub-subcontract underlying preme Court first examined signed with Ambrose was October documents.2 The court stated 1985), (and February, later amended in that, considering possible are now “We he had Knecht stated that never seen aris liability of one contractor another April, App. 1985.3 at 343. It bond before provisions, ing out of such contract be only after one of Knecht’s material- may safely cause I think it be said that requested copy men principal] were not liable at suit [the App. it. at 344.4 Knecht even looked at Cor], futile to assert liabil it would be [Van ity against surety.” 417 Pa. at A. opinion (quoting at 269 court A.2d lower Waters). finally fundamentally, majority Judge Charles The court More explain this case falls has failed to how concluded that: Cor, surety”, notwithstanding disap- Pa. at ty, issued Van in Dravo though apparent- the bond proving labor and ma- 208 A.2d at even of a distinction between bonds, incorporate ly explicitly contract as did not terial bonds and attempts distinguish it did in Dravo. it is clear that the court Van Cor on such Additionally, documents grounds. Maj.Op. in Van Cor believed that the contract n. 6. determining who the majority position must be considered adheres to the that Dravo is was intended to benefit. with their result. Id. Because not inconsistent bond, majority's misplaced focus on the June, they willing only began working project to look to the bond 3. Knecht App. to consider con- determine and refuse at 351-52. provisions tractual limit un- provisions part Ambrose, those have become less at the time of 4. The record shows Ambrose, bond. Since Dravo makes clear that the con- negotiations with Knecht’s contract $40,000.00 examined to determine whether tract must be approximately owed majority’s Knecht, light exists under previous project. construction result is inconsistent with Dravo. pay, prior could have of Ambrose’s failure protected Amb- itself another default rose. Now Knecht seeks to make Sordoni 2.In fact the court noted that "the terms of the *10 appropri- specifications when Knecht could have taken contract and between the authori- twice part protect ty principal] ate measures to itself. and became of the bond [the 84 indirectly what it could ting Knecht to do suretyship
outside the realm of black-letter directly namely, recover from Sor- surety- of general principles do law. Under — surety can demonstrate law, of the be of this case ship liability The facts doni. liability princip its greater of defies nor- majority’s no than the conclusion that the Co., Sur. keeping v. Seaboard United States with practice. mal commercial al.5 956, (2d Cir.1987), cert. de 817 F.2d 962 let- practice, obtained a commercial United — 161, nied, U.S. -, 98 L.Ed. 108 S.Ct. indemnification from Sordoni which ter of (1987); Lining Alger 115 v. 2d Co. following provisions: contained Pacific 237, 241 812 F.2d non-Blair Constr. indemnify, keep and in- To SECOND: denied, (5th Cir.1987), 506 So. certification demnified, and hold and save harmless (La.1987), opinion 2d 505 certifica demands, claims, Surety against all Cir.1987); (5th denied, 602 tion costs, loss, damages, and attor- expenses v. No. 171 Williams Painters Local Union whatever, any all neys’ fees and (10th Inc., F.2d 539 Kelley, & 605 therefor, or sustained incurred Sinclair, 424 Cir.1979); Smith by executing Surety by reason of or (D.C.Okla.1976); 1115 Diversified any procuring the execution of said Bond Sales, v. Monte Fusco Exca Utilities Inc. Bonds, Bonds, or or which vating 71 F.R.D. 664 Contracting already or hereafter executed on be- Drive-In, (E.D.Pa.1976); Exton Contractor, or half of the or renewal 489-90, Pa. 261 Home Indem. thereof; or sustained or in- continuation denied, (1969), A.2d cert. U.S. by making investiga- of an curred reason L.Ed.2d 46 91 S.Ct. thereof, prosecuting tion on account or long has been rule defending brought in any action connec- surety liability of with the ends therewith, obtaining release tion there- princi extinguishment of the from, recovering attempting or recov- pal. Metropolitan Nat’l Bank Mer any salvage er or connection therewith Bank, 155 Pa. chants & Mfrs.’Nat’l enforcing by litigation or otherwise (1893); Brock, Pa. A. 764 re agreements herein contained. clearly provides A. 778 The bond Surety Payment of amounts due hereun- jointly together legal der interest shall be severally for the benefit of the claim liable upon payable demand. successfully ants. Because Sordoni extin To money THIRD: furnish to the Con- i.e., guished liability, Ambrose Surety or to tractor as needed for the full, part there can be no labor, materials, prompt payment of Moreover, Knecht’s counsel con United.6 expenses or in connection any other costs during argument ceded oral cause with the of contracts when could lie Sordoni. Such action requested Surety. to do and as so astonishing highlights concession major of Knecht’s case. Yet the App. weakness at 625.
ity ignore this critical conces chooses indemnity This between sion. merely and Sordoni United affirms
Instead, permitting majority, by common law of indemnification in fa- United, permit- Knecht to recover from is vor of United and Sordoni.7 The majority does not contest the REIMBURSEMENT BY PRINCIPAL: IN post- Sordoni is whom GENERAL. ed the bond. (1) Where the makes performs princi- otherwise default See, e.g., § Restatement Contracts surety’s pal, property is or where the used to provides: duty, satisfy principal’s duty it is the DISCHARGEBY EXACTPERFORMANCEOF to reimburse to the extent DUTY. outlay his reasonable duty discharged A the exact contractual (a) surety’s has been in- performance thereof. curred, subjected property or his been has See, e.g., Security, Restatement charge, with the consent (1941): *11 indemnification, however, Security, including of statement of surety’s section 110 upon surety’s the assertion which states: is conditioned principal. available to the of those defenses SURETY’S RIGHT OF REIMBURSE- 108(5) provides: of the Restatement Section MENT AFTER DISCHARGE OF PRIN- principal has a defense which Where the CIPAL OBLIGATION. surety available to a who
is known to and
principal’s obligation
Where the
has
of
surety
with the consent
has become
discharged by payment
been
or
re-
surety does not
principal,
the
and the
lease
reserving
from the creditor not
it,
in an action with-
assert
or asserts it
rights against
surety,
prin-
his
principal notice of the
giving
out
cipal
duty
has no
to reimburse the
it,
opportunity to defend
action and an
surety.
surety
principal
well as the
where the
Security
By
Restatement of
§
defense,
principal
duty
has no
has a
holding
liable,
Sordoni will bear the
surety unless
to reimburse the
business
burden under its
of indemnifica-
requires performance by
compulsion
precisely
tion with United. This is
the re-
surety.
sult
provisions
which the above-cited
prevent.9
Restatement seek to
(5):
Commentary on Subsection
B.
surety
principal
j. Where both
have
contrary
eq-
Finally,
defenses it would be
I
majority’s
take issue with the
of
uitable basis of the rule
reimburse- holding
proper interpretation
of
surety by paying
the creditor
ment
“Principal
Contract”
not
a material
compel
principal to
could
reimburse
dispute.
argument
United’s
it—that
him____
gen-
It should be observed that
Sordoni,
is not
liable because
erally
surety
is under no business
is not liable—rests on its assertion that
compulsion
perform
princi-
where the
provisions in
certain
the Ambrose-Sordoni
defense.
pal has a substantial
disclaiming liability
possible
subcontract
third-party
incorpo-
beneficiaries have been
108(5) (1941).
Security
Restatement
§
rated into the Knecht-Ambrose sub-sub-
Therefore, United must assert the defense
Specifically,
argued
contract.
United has
that Knecht has no cause of action
any liability
pos-
disclaimed
that Sordoni
Ignoring
Sordoni.
the bald concession that
party
sible third
beneficiaries
virtue of
defeats
Knecht cannot hold Sordoni liable
Article 19.1 in the Sordoni-Ambrose sub-
purpose of these Restatement
the essential
contract,
Paragraph 2
majority’s holding also
and that
provisions.8 The
Re- Terms and Conditions of the Knecht-Amb-
undercuts several other sections
(b)
surety
princi-
principal
obligation
placing
has assumed an
once a
obligation
primary
pal
which was once the
released:
has been
surety.
surety
principal
are bound
Where the
jointly,
addition,
of one is the release of
the release
numerous courts have acknowl
rights
obligee
edged
suretyship
law that a
both unless the
the basic rule of
other____
See,
principal.
surety
principal
can assert a defense of its
served
If the
e.g.,
Hosp.
v. Ohio
Rhode Island
Trust Nat'l Bank
longer
duty
as a result of the credi-
has
Cir.1986) (stat
(1st
Co. Ins.
act,
surety
tor’s
should not be held to
ing
basic rule on the
"[t]he
duty.
of that
to answer for a default
surety
sureties is that ‘the
is not liable to the
Furthermore,
compelled
could be
if the
liable’[;]
unless his
thus he
creditor
release,
principal’s
he would
after the
may plead
which are available to
the defenses
if he had be-
be entitled to reimbursement
U.S.A.,
principal____”);
his
Siata Int'l
request
principal’s
at the
come
Am.,
Insurance Co.
No.
Such an outcome would be
with his consent.
(E.D.Pa.1973) (noting is true that
"[i]t
a release because
unfair
it
[payment by
principal]
is a valid de
attack-
would
the creditor a means
afford
obligee,
fense for a
in a suit
surety.
indirectly through
tanto."),
discharge
surety pro
rev’d on
(1941) (emphasis
Security
Restatement
(3d Cir.1974).
grounds,
subcontractors payment by
of final Subcontractor shall discharge complete a full and of W.J.
be
Ambrose, payment, including Inc. No payment,
final shall be construed to be work im- acceptance of defective
proper materials.
App. at 250. makes no sense construe this
provision payments to mean Paragraph provides: of the PRINCIPAL CONTRACTto which the performed by bound, Work Subcontractor shall be in CONTRACTOR and to the same ex- strict accordance with CONTRACT DOC- tent. applicable UMENTS per- work App. to be at 250. materials, formed and articles equip- and/or ment to be Harry furnished hereunder. Subcontrac- Knecht testified that he understood tor provisions shall bound all the “Principal of these Contract” to refer to the contract by applicable documents and provisions also between Knoll App. and Sordoni. at 320.
