History
  • No items yet
midpage
BP Energy Co. v. Federal Energy Regulatory Commission
2016 U.S. App. LEXIS 12980
| D.C. Cir. | 2016
Read the full case

Background

  • Cove Point LNG was converted from an import-only facility (NGA § 7 customers receiving open-access, cost-based service) to a mixed-use import/export facility authorized under NGA § 3, allowing market-rate, non-open-access contracts for expansion customers.
  • BP Energy is an existing § 7 customer with a contract through 2023 for terminal and pipeline services; Statoil was the § 3 expansion customer whose contract included terminal services at market rates and pipeline service at § 7 rates.
  • In 2012 Dominion solicited turn-back (release) of pipeline capacity; after no § 7 customers accepted, Dominion negotiated a deal allowing Statoil to turn back both its § 7 pipeline and § 3 terminal services.
  • BP protested, claiming the turn-back agreement was unduly discriminatory under NGA § 3(e)(4) because BP was not offered a comparable turn-back opportunity and would remain liable for terminal capacity it could not use without pipeline capacity.
  • FERC rejected BP’s claim, holding (1) § 3(e)(4)’s protection against undue discrimination is limited to operational tariff "terms and conditions" (e.g., nominations, scheduling), not contract termination/turn-backs; and (2) BP and Statoil are not similarly situated because BP is a § 7 open-access customer with regulatory protections not afforded to a § 3 expansion customer. The D.C. Circuit remanded for further explanation.

Issues

Issue BP's Argument FERC's Argument Held
Whether § 3(e)(4) "terms or conditions of service at the facility" includes turn-back/contract-termination rights § 3(e)(4) protects against undue discrimination in turn-back opportunities; contract termination is a term/condition of service The phrase is limited to operational tariff areas (nominations, scheduling, operating conditions), not contract termination Court: FERC's interpretation may be permissible but agency failed to provide adequate explanation; remand for fuller reasoning
Whether BP and Statoil are "similarly situated" for undue-discrimination analysis They are similarly situated with respect to market risks and the practical effect of turn-backs; § 3/§ 7 labels shouldn't eviscerate § 3(e)(4) protection They are not similarly situated because BP (a § 7 customer) has regulatory rights (release/retention) that Statoil (a § 3 customer) lacks Court: FERC relied on this ground but did not explain why contractual protections (or lack thereof) for Statoil are irrelevant; remand for explanation
Standing: Can BP sue over FERC's refusal to order a turn-back offer? BP: FERC’s failure to enforce § 3(e)(4) causes economic injury (loss of ability to turn back valuable capacity) FERC: Injury is contractual and not traceable to the orders; no competitive harm shown Court: BP has Article III standing — injury-in-fact traceable to FERC decision and redressable on remand
Whether the Commission may rely on post-hoc explanations or outside precedent to justify its interpretation BP: FERC must explain its statutory interpretation in the orders FERC: Its interpretation is entitled to Chevron deference and prior orders support it Court: FERC can receive deference, but must articulate reasoning in its orders; cannot rely on new, unexplained rationales — remand required

Key Cases Cited

  • Chevron U.S.A., Inc. v. NRDC, 467 U.S. 837 (1984) (agency statutory interpretation reviewed under two-step deference framework)
  • City of Arlington v. FCC, 133 S. Ct. 1863 (2013) (deference to agency’s interpretation of its statutory jurisdictional grant)
  • Motor Vehicle Mfrs. Ass’n v. State Farm, 463 U.S. 29 (1983) (arbitrary-and-capricious standard requires reasoned explanation)
  • SEC v. Chenery Corp., 332 U.S. 194 (1947) (courts may judge agency action only on the grounds the agency invoked)
  • Corley v. United States, 556 U.S. 303 (2009) (statutory interpretation must give effect to all provisions)
  • Complex Consol. Edison Co. v. FERC, 165 F.3d 992 (D.C. Cir. 1999) (disparate treatment permissible where rational basis and explained)
  • TransCanada Pipelines Ltd. v. FERC, 878 F.2d 401 (D.C. Cir. 1989) (differential treatment allowed if based on relevant, significant, explained facts)
Read the full case

Case Details

Case Name: BP Energy Co. v. Federal Energy Regulatory Commission
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Jul 15, 2016
Citation: 2016 U.S. App. LEXIS 12980
Docket Number: 15-1205
Court Abbreviation: D.C. Cir.