Baldi Bros, Inc. v. United States
15-1300
| Fed. Cl. | Sep 13, 2017Background
- Baldi Bros., Inc. sued the United States in the Court of Federal Claims under the Contract Disputes Act seeking $961,132.39 plus interest after a government contracting officer issued a final decision adverse to Baldi.
- The dispute arose from a sealed-bid procurement and the government's invocation of FAR 14.407-4 (bid mistake rules) to deny relief to Baldi.
- The contracting officer concluded Baldi’s bid did not qualify for correction/reformation/rescission because its corrected price would exceed the next lowest acceptable bid.
- The parties agreed on the numeric bid figures; the dispute centered on application of FAR 14.407-4 and which price metric (total contract price or base item price) should be compared to the next lowest bid.
- Government moved for (partial) summary judgment; the court treated it as a full summary judgment motion and addressed de novo the legal issues presented.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Jurisdiction: whether a final contracting officer decision exists | Baldi framed the case as an appeal under the CDA and relied on the COFD | Government maintained the CO issued a final decision and the court has CDA jurisdiction | Court had jurisdiction to review de novo after CO final decision and proceeded |
| Application of FAR 14.407-4(b)(2)(ii): which price metric controls | Baldi argued its bid could be corrected such that the corrected contract price would not exceed the next lowest acceptable bid | Government argued that, under either metric (total price or base item price) Baldi’s corrected price still exceeded the next lowest acceptable bid | Court held Baldi failed to show its corrected bid was less than the next lowest acceptable bid under either metric, so FAR relief was not warranted |
| Summary judgment: whether disputed facts precluded decision | Baldi implied factual disputes mattered to its claim | Government noted parties agreed on bid figures; legal application of those figures resolves the case | Court found no genuine material factual dispute; resolved the case as a matter of law for the government |
Key Cases Cited
- M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323 (Fed. Cir. 2010) (CDA requires a valid claim and a contracting officer’s final decision for jurisdiction)
- Wilner v. United States, 24 F.3d 1397 (Fed. Cir. 1994) (court reviews contracting officer decisions de novo and gives no deference to findings of fact in CO decisions)
- Celotex Corp. v. Catrett, 477 U.S. 317 (U.S. 1986) (summary judgment burden-shifting framework)
- Anderson v. Liberty Lobby, Inc., 477 U.S. 242 (U.S. 1986) (definition of materiality and genuineness for summary judgment)
- Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574 (U.S. 1986) (viewing inferences in light most favorable to nonmoving party)
- Mingus Constructors, Inc. v. United States, 812 F.2d 1387 (Fed. Cir. 1987) (standard for viewing evidence at summary judgment in government contract cases)
- Ford Motor Co. v. United States, 157 F.3d 849 (Fed. Cir. 1998) (courts do not make factual findings on summary judgment)
