History
  • No items yet
midpage
Axenics, Inc. v. Turner Construction Co.
164 N.H. 659
| N.H. | 2013
Read the full case

Background

  • Axenics subcontracted Turner to install process pipe for the West Lebanon biotech facility; original contract price was $1,992,506.
  • Delays and changes occurred; mechanical completion target was December 2004, with Axenics' last day on site June 2, 2005.
  • Subcontract allowed Turner-directed changes, change orders, and a specific process for billing extra work with written proposals and five-day deadlines.
  • Axenics sought eight change orders approved by Turner and Stryker; a ninth change order for $435,929 was not paid.
  • Axenics alleged Turner breached the subcontract and that Stryker aided or caused unjust enrichment; CPA claims were also alleged.
  • Trial court awarded Axenics restitution of $1,080,000 for unjust enrichment against both Turner and Stryker, and found no CPA violation.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Abandonment vs. breach Axenics argues abandonment occurred through conduct; breach separate still present. Defendants contend no abandonment and no breach; contract remained in effect. Abandonment not proven; breach to be determined on remand.
Unjust enrichment against Turner Turner's coordination failures caused extra work and costs outside the contract. Change orders and contract controls precluded unjust enrichment; subject matter within contract. Turner not liable for unjust enrichment; within-contract change-order framework governs.
Unjust enrichment against Stryker Stryker benefited from extra work and should restitution be paid when privity exists via owner-contractor chain. Stryker paid to Turner; no direct obligation to Axenics; no unconscionable transfer. No unjust enrichment against Stryker; benefit not unconscionably retained.
Damages for unjust enrichment and Rule 408 Damages should reflect value of extra work; internal compromise memo should be admissible. Damages tainted by inadmissible compromise communications under Rule 408. Rule 408 error; internal compromise memo excluded; damages reconsidered on remand.
CPA claim viability Defendants’ conduct constitutes unfair or deceptive acts; rascality threshold met. Conduct did not reach rascality; businesslike disputes and cooperation occurred. No CPA violation; rascality not shown.

Key Cases Cited

  • J.A. Jones Constr. v. Lehrer McGovern Bovis, 89 P.3d 1009 (Nev. 2004) (abandonment requires mutual consent; mixed law/fact question)
  • Fru-Con/Fluor Daniel v. Corrigan Brothers, 154 S.W.3d 330 (Mo. Ct. App. 2004) (many changes do not prove abandonment when contract contemplates changes)
  • Clarendon America v. General Sec. Indem., 124 Cal. Rptr. 3d 1 (Cal. Ct. App. 2011) (abandonment shown by inconsistent conduct; contract rights preserved)
  • EMF General Contracting Corp. v. Bisbee, 774 N.Y.S.2d 39 (N.Y. App. Div. 2004) (abandonment analysis in construction context)
  • R.J. Berke & Co. v. J.P. Griffin, Inc., 116 N.H.760 (N.H. 1976) (quantum meruit as restitutionary remedy after material breach)
  • Puritan Mills, Inc. v. Pickering Construction Co., 262 S.E.2d 586 (Ga. Ct. App. 1979) (contract clearly sets scope; rock removal not within contract)
  • Great Plains Equipment v. N.W. Pipeline, 979 P.2d 627 (Idaho 1999) (owner generally not liable to subcontractor unless owner consents to pay)
Read the full case

Case Details

Case Name: Axenics, Inc. v. Turner Construction Co.
Court Name: Supreme Court of New Hampshire
Date Published: Mar 13, 2013
Citation: 164 N.H. 659
Docket Number: No. 2011-219
Court Abbreviation: N.H.