GREAT PLAINS EQUIPMENT, INC., a foreign corporation; Michetti Pipe Stringing; Beard Oil Petroleum, Inc., a Foreign Corporation; Atlas Copco Rental, Inc., a foreign corporation; CRC-evans Pipeline International, Inc., a foreign corporation; Courtesy Ford Lincoln Mercury, Inc., an Idaho corporation; Cowboy Oil Co., an Idaho Corporation; Darby Enterprises, Inc., a foreign corporation; Hartford Insurance Company/Pickard Tate & Allen, a Connecticut Company; Rasmussen Equipment Company, a Utah corporation; Rocky Mountain Machinery Company, a foreign corporation; V-1 Oil Company, an Idaho corporation; Valley Office Systems, Inc., an Idaho corporation; Cate-Idaho Equipment Co., Inc., an Idaho corporation B.D. Holt & Company, Inc., d/b/a Holt Company of Texas, a foreign corporation, Plaintiffs-Respondents-Cross Appellants, v. NORTHWEST PIPELINE CORPORATION, a foreign corporation, Defendant-Appellant-Cross Respondent Kirkpatrick & O‘Donnell Construction Equipment Co., Plaintiff-Appellant, v. Northwest Pipeline Corporation, a foreign corporation, Defendant-Respondent.
Nos. 22762, 22973
Supreme Court of Idaho, Boise
March 29, 1999
Rehearing Denied May 20, 1999
979 P.2d 627
WALTERS, Justice
IV.
CONCLUSION
We hold that the warrants of attachment were improperly executed on Hall because they were not served on him in a “public place” as required by the face of the warrant. Therefore the evidence seized in Hall‘s motel room should have been suppressed. We therefore reverse the district court‘s decision denying Hall‘s motion to suppress and remand this case for proceedings consistent with this opinion.
Chief Justice TROUT, Justices SILAK, SCHROEDER, and WALTERS CONCUR.
Racine, Olson, Nye, Cooper & Budge, Pocatello, for respondents in case no. 22762, Hartford Insurance/Pickard, Tate & Allen
Craig W. Christensen, Ctd., Pocatello, argued for respondent B.D. Holt & Co., Inc.
Lowell N. Hawkes, Pocatello, argued for respondent Cate-Idaho Equipment Co. Inc.
WALTERS, Justice
NATURE OF THE CASE
This is an appeal from a judgment in favor of several claimants involved in the construction of a natural gas transmission pipeline. The construction contract was entered into by Northwest Pipeline Corporation (NWP) and Great Plains Pipeline Construction, Inc. (GPPC), and required GPPC to build a new pipeline, compressor pumping stations and related facilities between Pocatello and Burley, Idaho. Delays in the completion of the contract forced GPPC to quit the job, leaving numerous subcontractors, equipment lessors, insurance providers, and other vendors unpaid. GPPC eventually was forced into involuntary bankruptcy, and the subcontractors filed liens against NWP for the unpaid amounts. All but seventeen of these subcontractors settled with NWP before trial. Following trial in the district court, sixteen of the remaining seventeen subcontractors were awarded judgment against NWP on all or a substantial portion of their claims on alternative legal theories based on Idaho‘s mechanic‘s lien statute, Utah‘s bond statute and alleged unjust enrichment. The final judgment and decree against NWP in favor of the successful claimants collectively exceeded $3 million.
NWP timely appealed from the judgment, and the subcontractors cross-appealed for the purpose of challenging the trial court‘s decision not to allow recovery of any punitive damages. In addition, the remaining subcontractor-claimant, Kirkpatrick & O‘Donnell Construction Equipment Co. (K & O), separately appealed from the district court‘s order granting summary judgment to NWP against K & O. The appeals were consolidated for disposition. For the following reasons, we affirm in part, and vacate in part.
I.
FACTUAL BACKGROUND
NWP, a regulated utility company, distributes natural gas to customers from New Mexico to the pacific northwest and Canada. In 1992, after review of its customers’ needs, NWP applied to the Federal Energy Regulatory Commission (FERC), for a permit to expand its mainstream transmission line capacity. The entire expansion project consisted of 378 miles of new pipeline loops on NWP‘s existing mainline and lateral systems, together with ten new compressor stations, modifications at thirteen more compressor stations, and construction of or additions to thirty-five communication sites. The system expansion was divided into seven different “spreads.” Spread 2 covered a span of seventy-six miles beginning south of Pocatello in Bannock County and running west across Power County to Burley in Cassia County, Idaho. Due to environmental concerns, the FERC approval required construction on Spread 2 to occur during the off-irrigation season.
After NWP invited bids to construct Spread 2, GPPC of Lubbock, Texas, submitted the lowest bid. Although NWP initially was concerned because GPPC‘s bid was significantly lower than any of the other bids, NWP‘s concerns were resolved on further investigation when NWP concluded that GPPC had sufficient assets to complete the job as bid. The contract between NWP and GPPC was entered into in Utah and explicitly required the application of Utah law. Utah has a bond statute (
In January of 1993, GPPC notified NWP that Spread 2 could not be completed as originally bid due to delays in starting, extreme weather conditions, and underestimations in the cost of the project. NWP obtained bids to complete construction from several other contractors, but elected to have GPPC complete the job since GPPC‘s cost to complete the project was far less than the other contractors’ bids. Thereafter, NWP and GPPC renegotiated the contract, and construction continued through April of 1993. However, in May of 1993, GPPC halted construction, leaving subcontractors, equipment lessors, insurance providers, and other vendors unpaid in amounts exceeding $6 million. NWP refused to make further payments to GPPC, but did pay Precision Blasting and Smackover Pressure Testing from the retainage.
II.
PROCEDURAL BACKGROUND
Thereafter, GPPC filed a claim of lien against NWP and the pipeline and informed the subcontractors to do the same, because GPPC was unable to pay them. Approximately fifty subcontractors, equipment lessors, insurance providers, and other vendors filed claims of lien against NWP. In addition, on May 8, 1993, NWP filed suit against GPPC in Utah state court for breaching the prime contract. In July of 1993, the subcontractors, equipment lessors, insurance providers and vendors, including GPPC, filed complaints against NWP in the district court in Idaho in Bannock County in the Sixth Judicial District. Those actions included foreclosure of mechanics’ liens, claims under Utah‘s bond statute, and allegations of unjust enrichment.
On August 5, 1993, GPPC was dismissed from the Idaho suit; however, the other various claims remained in Idaho and were consolidated into the present litigation regardless of the county in which the work on Spread 2 may have been accomplished. The case was eventually removed to federal court where GPPC was forced by NWP into involuntary bankruptcy. Some of the pending claims were settled in the bankruptcy action. In January of 1994, the Idaho and Utah state court actions were removed to federal district court, but in August of 1994, the federal court remanded the subcontractors’ claims to the Idaho state court.
On September 16, 1994, following remand to the state court, the district court in Bannock County issued a memorandum decision determining several of the initial, controlling issues. The district court held that NWP‘s waiver of the Utah bond requirement allowed the subcontractors and vendors to invoke the Utah private payment bond statute as a remedy. The district court also held that Idaho‘s mechanic‘s lien statutes applied to those claimants who had supplied tools and equipment, and who had supplied rental equipment and machinery but did not apply to those claimants who had supplied repair parts. In a later memorandum decision, the district court also held that suppliers of insurance have a lien claim under
Consistent with its memorandum decisions, the district court granted NWP summary judgment on March 13, 1995, as to K & O‘s lien claim for repair parts. Thereafter, the district court dismissed K & O‘s Utah bond statute claim, and eventually dismissed K & O‘s unjust enrichment claim as a matter of law.
After most of the claims against NWP were settled and K & O‘s action dismissed, sixteen claimants remained. Of those sixteen, fourteen were represented by Louis Racine, Jr. (Racine Subcontractors).1 Subse-
quently, the district court bifurcated the claims, holding that the Idaho lien claims and the unjust enrichment claims were equitable in nature and thus were not proper for determination by a jury. The district court concluded that the bond claims would be tried to a jury, but because the bond and lien claims were identical both would be tried together with the jury‘s verdict being advisory to the court as to the lien claims.
The trial on the remaining bond and lien claims lasted from April 27, 1995, to June 23, 1995. On June 26, 1995, the jury returned a special verdict on the sixteen claims under the Utah payment bond statute theory and found in favor of thirteen claimants. Cowboy Oil, V-1 Oil, and GPE did not recover from the jury on the bond statute theory. The district court reserved decision on the lien claims.
Following a trial on the unjust enrichment claims, on January 8, 1996, the district court entered a memorandum decision and findings of fact regarding the lien claims and the unjust enrichment claims. The district court held in favor of the sixteen remaining claimants. On March 15, 1996, the district court entered an errata memorandum decision to correct the amounts awarded to the claimants under the unjust enrichment theory.
All parties moved for attorney fees, costs and prejudgment interest, and on July 19, 1996, the district court awarded fees and costs to the prevailing claimants totaling more than $800,000 against NWP. NWP was awarded just over $5,000 in costs and fees against K & O. Consistent with the jury verdict and various decisions, the final judgment and decree of foreclosure was entered against NWP. The collective amount of the final judgment and decree of foreclosure against NWP exceeded $3 million.
III.
ISSUES ON APPEAL
A. NWP presents the following issues on appeal:
- Whether the district court erred in determining that suppliers of leased equipment, insurance and fuel are covered under Idaho‘s lien statutes.
- Whether the district court erred in determining that the claims of lien adequately describe the property.
- Whether the district court erred in allowing claims based on Utah‘s private bond statute.
- Whether the district court erred in allowing the claimants’ unjust enrichment claims, and in determining that NWP had received unjust enrichment.
- Whether the district court erred in reversing the jury verdict on Michetti‘s claims.
- Whether the district court erred in calculating Hartford‘s lien claim.
- Whether the district court improperly found in favor of GPE on its lien and unjust enrichment claims.
- Whether the district court erred in refusing to give preclusive effect to the jury‘s verdict.
- Whether the district court erred in refusing to allow and consider NWP‘s equitable defenses.
- Whether the district court erred in awarding attorney fees, costs and prejudgment interest against NWP.
B. The subcontractors raise the following issues on cross-appeal:
- Whether the district court erred in refusing to allow the claims for punitive damages.
- Whether the district court erred in denying CRC-Evans and Courtesy Ford‘s claims for repair parts.
- Whether the district court erred in determining that the “open account” defense barred the claims of lien by Valley Office Systems and Hartford Insurance.
- Whether B.D. Holt‘s claim of lien was untimely recorded.
- Whether the district court erred in granting summary judgment to NWP, thus, dismissing K & O‘s mechanic‘s lien, Utah bond statute, and unjust enrichment claims.
- Whether the district court erred in awarding attorney fees and costs to NWP.
IV.
DISCUSSION
Before we address the issues raised, we note that this Court must defer to findings of fact based upon substantial evidence but will review freely the conclusions of law reached by stating legal rules or principles and applying them to the facts found. Sun Valley Shamrock Resources, Inc. v. Travelers Leasing Corp., 118 Idaho 116, 118, 794 P.2d 1389, 1391 (1990). Accordingly, we exercise free review over the district court‘s conclusions of law. Kawai Farms, Inc. v. Longstreet, 121 Idaho 610, 613, 826 P.2d 1322, 1325 (1992).
A
NWP‘S ISSUES
1. WHETHER THE DISTRICT COURT ERRED IN DETERMINING THAT SUPPLIERS OF LEASED EQUIPMENT, INSURANCE AND FUEL ARE COVERED UNDER IDAHO‘S LIEN STATUTES.
a. Suppliers of leased equipment.
We first consider whether the district court erred in allowing lien claims for equipment lessors. The claims sought recovery of unpaid rental charges on leased equipment. NWP contends that Atlas, CRC-Evans, Darby, GPE, Rocky Mountain, Rasmussen and Cate-Idaho should not have been allowed to pursue liens pursuant to
The right to acquire and enforce a mechanic‘s or materialman‘s lien was unknown at common law and originally was also not allowed in equity. R.Y. Liang, Annotation, Charge for Use of Machinery, Tools, or Appliances Used in Construction as Basis for Mechanic‘s Lien, 3 A.L.R.3d 573 (1965). Because such a right exists solely as a result of statutory enactment, it depends entirely upon application of the statute involved. Id. at 577.
Right to lien. Every person performing labor upon, or furnishing materials to be used in the construction, alteration or repair of any mining claim, building, wharf, bridge, ditch, dike, flume, tunnel, fence, machinery, railroad, wagon road, aqueduct to create hydraulic power, or any other structure, or who grades, fills in, levels, surfaces or otherwise improves land ... and every professional engineer or licensed surveyor under contract who prepares or furnishes designs, plans, plats, maps, specifications, drawings, surveys, estimates of cost, on site observation or supervision, or who renders any other professional service whatsoever for which he is legally authorized to perform in connection with any land or building development or improvement, or to establish boundaries, has a lien upon the same for the work or labor done or professional services or materials furnished.
NWP asserts that
When applying this statute, this Court has held the provisions are to be liberally construed in the favor of the persons who perform labor upon or furnish materials to be used in the construction, alteration, or repair of a building or structure. Pierson v. Sewell, 97 Idaho 38, 539 P.2d 590 (1975); Dybvig v. Willis, 59 Idaho 160, 82 P.2d 95 (1938). The rule of liberal construction of statutory liens, however, does not permit the court to create a lien where none exists or was intended by the legislature. Boone v. P & B Logging Co., Inc., 88 Idaho 111, 397 P.2d 31 (1964).
In determining who may assert a lien against a landowner‘s property pursuant to
Under this statute the legislature evidently intended to grant the right to claim a lien to any person who contributes labor or materials for the construction, alteration, or repair of a building or structure upon real property. . . . [I]t was clearly the intent of the legislature to grant an absolute lien direct upon the property, to the person who performs labor upon, or furnishes materials to be used in a building, structure or other improvement without reference to whether such person performing such labor, or furnishing material, is an original contractor or subcontractor, or a laborer or a materialman, and without reference to whether there is anything due the original contractor from the person or corporation constructing such building or other improvement.
Hill v. Twin Falls Water Co., 22 Idaho 274, 279, 125 P. 204, 206 (1912). Referring to
grant[s] the right to claim a lien for “the value of the labor or material furnished and used in or about the construction, alteration or repair of the building, structure or other works.” That right of lien is based on the theory that the claimant has, either by his labor or by the materials furnished and used, contributed to the construction or improvement of the property against which the lien is asserted. Hence, where the labor is not used or the materials are not incorporated into the building, structure or improvement, no lien on land or building results.
Chief Industries, Inc. v. Schwendiman, 99 Idaho 682, 687, 587 P.2d 823, 828 (1978) (quoting Chamberlain v. City of Lewiston, 23 Idaho 154, 163, 129 P. 1069, 1071 (1912)) (citations omitted, emphasis deleted). In the Chamberlain case, a lien was claimed for the construction of an extension into the Clearwater River of the intake pipe servicing the pumping plant of the water system of the City of Lewiston. A portion of the claim of lien was for labor and material furnished to build a coffer-dam in the river preparatory to construction of the pipe extension. The coffer-dam subsequently washed out and was swept away by a flood. On appeal, the city argued that the coffer-dam was not part of the contract in the case, and its loss therefore was beyond the liability of the city. In response, the Court held that construction of the pipe extension necessitated the building of the coffer-dam or some similar method in order to do the work. As to the loss of the labor and materials that went into the dam, the Court said:
When a man contracts to have a building erected, he knows that the contractors and builders will be obliged to have scaffolding and other material that does not actually go into the building, but which may practically be used and consumed and destroyed in the course of the work. Such material and the labor incident thereto is as much a part of the contract as if it were specified and set forth in the contract itself.
23 Idaho at 165, 129 P. at 1072. Accordingly, the Court allowed recovery for the labor and materials that went into the coffer-dam before it was destroyed.
The use of equipment in carrying out labor or providing materials is analogous to the use of tools discussed in two prior Idaho cases. In Naylor v. Lewiston & S.E. Elec. Ry. Co., 14 Idaho 789, 96 P. 573 (1908), this Court addressed whether a supplier of tools would be entitled to a claim of lien. The Court held that the charge for the use of tools consumed in construction work is a lienable item. Id. at 802, 96 P. at 576. The Court stated that,
if a person furnishes tools which are used and consumed in the construction of work, such person would be entitled to a lien for the same reason that gives a lien for the use and consumption of material. The use and consumption of tools ought to give the same right as the use and consumption of materials.
Id. Likewise, while addressing the opposite situation, the Court in Ninneman v. City of Lewiston, 23 Idaho 169, 129 P. 1073 (1912), disallowed a lien for tools that were not used or consumed in the pipe extension repair
It will be necessary, however, for the judgment to be modified in this case so as to eliminate therefrom the value of tools and appliances which did not go into or become a part of the work or improvement, and were not used or consumed in or about the work. A lien cannot be allowed for tools and appliances which are the property of the contractors and may be used from time to time in other works or which do not go as a part of the building or improvement and necessarily enter therein.
23 Idaho at 171, 129 P. at 1073 (emphasis supplied).
Similarly here, the leased equipment was not incorporated into, or consumed and destroyed by, the construction project. The district court below, however, adopted the reasoning of the Wyoming Supreme Court in United Pacific Ins. Co. v. Martin & Luther General Contractors, Inc., 455 P.2d 664 (1969), and concluded that rented equipment is “consumed” to the extent that its measurable useful life is diminished while the equipment is put to use on a project. In essence this reasoning allows for the assertion of a lien based upon a theory of partial consumption of the asset.
We are not persuaded to follow the lead of the Wyoming court, and we reject the suggestion that there may be a partial consumption of equipment as a basis for permitting a claim of lien under
There is little doubt that Logan contributed to the value of the construction project by leasing equipment to the Lawrence Group. The contribution of value, however, is not what the statute requires. Rather, the furnishing of labor or materials forms the basis for a mechanic‘s lien.
...
“It is generally held under applicable lien laws that machinery not (a) totally depreciated by use on the property or (b) incorporated into the improvement, or (c) in connection with which labor was also supplied could not be the basis of a valid lien.” Air Service Co. v. Cosmo Investments, Inc., 115 Ga.App. 596, 597, 155 S.E.2d 413, 414 (1967). The excavation equipment in question was not totally depreciated by its use, nor was it incorporated into the improvement. Therefore, it does not satisfy the definition of materials.
...
Logan‘s appeal now turns on a contention that he did work. “It is well settled that the rental or the value of the use of machinery cannot be the basis for the claim of a mechanic‘s lien.” Wilkinson v. Pacific Mid-West Oil Co., 152 Kan. 712, 714, 107 P.2d 726, 727 (1940). Fifty years later, this statement still represents the majority view. Some jurisdictions have amended their statutes to include expressly the rental of equipment as the basis for a lien. But when the statute speaks only in terms of work done or materials furnished, as does our own law, jurisdictions generally deny recovery.
Logan Equipment v. Profile Constr. Co., 585 A.2d 73, 74-75 (R.I.1991).
Like the Rhode Island court, the New Mexico Supreme Court held that rent for equipment used in excavation and comparable construction work was not a lienable item. The court said:
While we may feel that in view of our changed methods and construction work generally, and the increased and ever-increasing use of machinery to replace manual labor, the rental of such machinery might well be the basis of a claim of lien, we do not find such to be the law as it exists in New Mexico today; nor do we believe we should enlarge the scope of our present lien law by judicial construction, but that the wisdom and necessity of so doing should be determined by and left to the legislature.
Lembke Constr. Co., Inc. v. J.D. Coggins Co., 72 N.M. 259, 382 P.2d 983, 989 (1963).
Similar to the conclusions reached by the Rhode Island and New Mexico courts with regard to their lien statutes, we hold that under
The district court‘s decision, allowing recovery by way of mechanic‘s liens under
b. Suppliers of Insurance.
We next consider whether Idaho‘s mechanic‘s lien statute applies to the recovery of unpaid insurance premiums by a supplier of insurance. Only one insurance provider, Pickard Tate & Allen (PTA), was permitted by the district court to foreclose its claim for a lien under
NWP contends that PTA cannot recover under the lien statutes because the insurance provided continues beyond the completion of the project. Thus, the insurance is not labor and is not consumed within the project.2 We agree.
As previously stated, the underlying purpose of Idaho‘s lien statutes is to protect those who perform labor or furnish material to the extent of the value that the owner‘s property is improved. The providing of liability insurance coverage is neither labor nor material that is consumed in the process of structurally improving real property. As with the claim for recovery of rental payments due for the lease of equipment, the liability insurance premium claim fails because it is not within the mechanic‘s lien statute. Compare
We therefore hold that PTA‘s claim for unpaid premiums relating to general liability and equipment insurance relating to the Spread 2 project is not protected by Idaho‘s lien statutes. The district court‘s decision to the contrary is set aside, and the judgment allowing foreclosure of PTA‘s claim of lien is vacated.
c. Suppliers of Fuel.
NWP contends that the district court erred in holding that suppliers of fuel and lubrication products used for construction equipment and passenger vehicles, such as was provided to GPPC by Beard Oil, can recover under Idaho‘s mechanic‘s lien statute. Moreover, NWP asserts that Beard Oil essentially acted as a lender to GPPC by arranging to extend a general line of credit to GPPC for fuel and that lenders have no lien rights. NWP‘s lender theory traces the following path: Beard Oil, of Michigan, would contract with local suppliers for delivery of fuel to tanks and GPPC‘s construction
For the same reasons stated above with regard to the rental of equipment and providing of liability insurance, we conclude that Beard Oil was not entitled to claim a lien for its fuel and oil account. We reach this conclusion with some guidance from the decisions of this Court in State ex rel. Modern Motor Co., Inc. v. H & K Construction Co., 75 Idaho 492, 274 P.2d 1002 (1954), and People ex rel. White v. Storm, 49 Idaho 246, 287 P. 689 (1930). In each of those cases, the Court decided that costs for gasoline and oil supplied in highway construction are recoverable under Idaho‘s public contractor‘s bond statute as indirectly contributing to the work, while recognizing that similar claims for recovery for fuel are not permissible under the mechanic‘s lien statute because such is not “labor and materials that are lienable under the mechanic‘s lien law in its relation to private structures.” Modern Motor, 75 Idaho at 495, 274 P.2d at 1003; White, 49 Idaho at 246, 287 P. at 692. Accordingly, we set aside the district court‘s decision that permitted Beard Oil to pursue a claim of lien for supplying fuel products, and we vacate that portion of the judgment allowing foreclosure of Beard Oil‘s claim of lien.
2. WHETHER THE DISTRICT COURT ERRED IN DETERMINING THAT THE CLAIMS OF LIEN ADEQUATELY DESCRIBE THE PROPERTY.
In addition to directly challenging the underlying bases asserted by the various plaintiffs claiming lien rights, NWP contends that the lien claims failed to sufficiently describe the property pursuant to
The sufficiency of the description in the liens was determined by the district court, as the trier of fact concerning the claims of liens, upon motions by the parties for summary judgment. Riverside Development Co. v. Ritchie, 103 Idaho 515, 650 P.2d 657 (1982). The district court concluded with respect to this issue:
[The] Plaintiffs have demonstrated by affidavit that, through the use of the prop-
erty descriptions contained in the liens, two different people familiar with the locality have been able to identify the property with reasonable certainty. Due to the unique nature of the project at issue, it is apparent that any person familiar with the surrounding area, accompanied by the maps and diagrams provided and referenced in plaintiffs’ lien, would be able to locate the liened property.
This Court concludes as a matter of law that the property descriptions contained in the liens filed by all of the plaintiffs are sufficient for purposes of identification.
We agree and hold that the property descriptions contained in the claims of lien substantially complied with
3. WHETHER THE DISTRICT COURT ERRED IN ALLOWING CLAIMS BASED ON UTAH‘S PRIVATE BOND STATUTE.
We turn next to whether the district court erred in allowing recovery to several of the plaintiffs who asserted claims based on Utah‘s private bond statutes,
The contract between NWP and GPPC contained a provision stating: “This Contract and the rights and obligations of the parties shall be governed by and interpreted in accordance with the laws of the State of Utah.”3 The district court held that this provision permitted the plaintiffs to invoke the Utah private bond statutes as third party beneficiaries to the arrangement between NWP and GPPC. In particular,
In reaching its decision, the district court stated that Seubert Excavators, Inc. v. Eucon Corp., 125 Idaho 744, 753, 874 P.2d 555, 564 (Ct.App.1993), review granted, modified on other grounds, 125 Idaho 409, 871 P.2d 826 (1994), “demonstrate that the plaintiffs are properly regarded as third party beneficiaries of the contract under
The Seubert case involved a claim by a subcontractor against the surety on a public works contract bond required by the state of Washington. The surety argued that an unpaid subcontractor cannot maintain a third party beneficiary cause of action against the surety. On appeal, the Idaho Court of Appeals determined that the subcontractor could proceed under
Seubert does not stand for the proposition that a subcontractor is the third party beneficiary of any other type of contract or that failure to require or to obtain a private contractor‘s bond places the subcontractor, who would otherwise have been protected with the bond, in the status of a third party beneficiary of a contract between the general contractor and the property owner.
Here, it appears that the Utah code provisions were adopted by the Utah legislature as measures intended to apply to construction contracts in the state of Utah. There is no indication in the Utah statutes that they should have any extraterritorial effect. The Utah statutes were not “contracts” made for the benefit of third persons. The statutes contemplated the existence of a payment bond which could be resorted to by subcontractors in Utah for payment of sums due them. Failure to obtain the payment bond would render the owner liable to a subcontractor in Utah—not because the subcontractor was the third party beneficiary of a contract—but by virtue of the terms of the statute.
As noted,
We hold that the generalized statement in the NWP-GPPC contract, that the contract and the rights and obligations of the parties shall be governed by and interpreted in accordance with the laws of the State of Utah, does not suffice to invoke the terms of
4. WHETHER THE DISTRICT COURT ERRED IN ALLOWING THE UNJUST ENRICHMENT CLAIMS.
We next address the viability of the unjust enrichment claims. NWP contends that the subcontractors, not in privity with NWP, cannot recover under an implied contract claim. The district court acknowledged that a subcontractor cannot sue an owner for quantum meruit based on an implied promise to pay, but held that an unjust enrichment claim is not based on an implied promise to pay. In this regard, the district court misapplied Dale‘s Service Co., Inc. v. Jones, 96 Idaho 662, 534 P.2d 1102 (1975), and incorrectly created a distinction between an action for quantum meruit and unjust enrichment because both quantum meruit and unjust enrichment do involve claims based on an implicit promise to pay.7 In Continental Forest Products, Inc. v. Chandler Supply Co., 95 Idaho 739, 518 P.2d 1201 (1974), this Court recognized three types of contractual arrangements:
First is the express contract wherein the parties expressly agree regarding a transaction. Secondly, there is the implied in fact contract wherein there is no express agreement but the conduct of the parties implies an agreement from which an obligation in contract exists. The third category is called an implied in law contract, or quasi contract. However, a contract implied in law is not a contract at all, but an obligation imposed by law for the purpose of bringing about justice and equity without reference to the intent or the agreement of the parties and, in some cases, in spite of an agreement between the parties. It is a non-contractual obligation that is to
be treated procedurally as if it were a contract, and is often referred to as quasi contract, unjust enrichment, implied in law contract or restitution.
Id. at 743, 518 P.2d at 1205 (citations omitted; emphasis in original). In Smith v. Smith, 95 Idaho 477, 511 P.2d 294 (1973), the Court noted that:
“Restitution” and “unjust enrichment” are the modern designations for the older doctrine of “quasi contracts.” The substance of an action for unjust enrichment lies in a promise, implied by law, that a party will render to the person entitled thereto that which in equity and good conscience belongs to the latter. (Citations omitted; emphasis supplied.)
The two theories, quantum meruit and unjust enrichment, are simply different measures of recovery as equitable remedies. The doctrine of quantum meruit permits recovery, on the basis of an implied promise to pay, of the reasonable value of the services rendered or the materials provided. Peavey v. Pellandini, 97 Idaho 655, 551 P.2d 610 (1976). Unjust enrichment, as a fictional promise or obligation implied by law, allows recovery where the defendant has received a benefit from the plaintiff that would be inequitable for the defendant to retain without compensating the plaintiff for the value of the benefit. Continental Forest Products, Inc., 95 Idaho at 743, 518 P.2d at 1205.
Neither of these two theories allows recovery by a subcontractor who lacks a contractual relationship directly with a property owner. While couched in terms of discussing a claim for recovery on the basis of quantum meruit, this Court‘s decision in Dale‘s Service is equally dispositive as to a subcontractor‘s claim for recovery on a theory of unjust enrichment arising from an implied obligation. There the Court held:
We do not believe that T & J [the subcontractors] have a basis for recovery against O.K. [the landowner] under a quantum meruit theory. The general rule in this area is that a subcontractor who furnishes material or labor pursuant to an agreement with, or upon the order and credit of a general contractor cannot recover against the property owner upon the basis of an implied promise to pay arising from the owner‘s receipt and acceptance of the benefit of the material and labor furnished. Thus it is said that a landowner will not be held liable for work or material furnished by a subcontractor to a contractor, pursuant to a contractual arrangement between the contractor and subcontractor, where the landowner is not a party to this contractual arrangement.
...
It is true that there is an exception to this general rule under the mechanic‘s lien laws, where if a subcontractor is not paid, he may enforce his claim for compensation directly against the landowner. However, T & J did not avail themselves of this remedy, and therefore this exception is inapplicable to the case at hand.
Dale‘s Service, 96 Idaho at 666-67, 534 P.2d at 1106-07. In the present case, the plaintiff subcontractors, who did not have express contracts directly with NWP, were limited to recovery upon their claims under the mechanic‘s lien statute. Absent that right of recovery, they have no cause of action directly against NWP for alleged unjust enrichment.
The decision of the district court allowing recovery to the subcontractors as plaintiffs on the grounds of unjust enrichment are set aside, and the judgments entered on those theories are vacated.
5. WHETHER THE DISTRICT COURT ERRED IN REVERSING THE JURY VERDICT ON MICHETTI‘S CLAIMS.
Michetti contracted with GPPC to load, haul and string eighty-foot sections of pipe along NWP‘s Spread 2 pipeline expansion project. On Michetti‘s Utah bond claims, the jury returned a verdict for Michetti on its
On appeal, NWP argues that the district court incorrectly rejected the jury‘s verdict and determined that Michetti‘s contract with GPPC was modified. NWP asserts that the jury‘s verdict should be upheld and that the contract was not modified because there was no new consideration, the new contract price was not included in any modification, and there was no impossibility preventing performance. Furthermore, NWP asserts that the district court erred in granting Michetti a new trial as to the Utah bond claims.
We agree that the district court erred in granting a new trial on the alternative cause of action based upon the Utah bond statute, for the reasons stated in part IV(A)(3), above. The issue remains, however, whether the contract between Michetti and GPPC was modified, thus allowing Michetti to recover additional amounts over those found by the advisory jury on the lien claim.
Michetti‘s original bid to string the pipe was for $1.27 per foot of pipe installed. However, Michetti eventually lowered its bid to $1.10 per foot based on the projection that Michetti could string 13,000 feet per day and complete the project in thirty-five days. The bid included a projected profit of $50,000.
GPPC then awarded Michetti the contract and notified Michetti that the stringing was to begin during the week of December 2, 1992. On December 1, 1992, Michetti sent its foreman to the job site to mobilize equipment and personnel. However, the combination of the mountainous terrain and extreme weather conditions caused Michetti‘s personnel to conclude that the project was possible but not for the prices quoted in Michetti‘s bid. Michetti asserted that its vice-presi-
NWP argued that no modification took place. NWP conceded that Michetti was entitled to recover on its lien claim for the amount due under the original contract of $1.10 per foot, but contended that Michetti was not to recover extra compensation beyond the original contract price because of the alleged late start and weather conditions. Following a jury trial on the Utah bond claims, the jury returned a verdict for Michetti for $1.10 per foot, but did not award additional costs because the jury found that the contract was not modified. Thus, the jury found the unpaid amount on the original contract between Michetti and GPPC to be $284,288.85. The district court held that the evidence was clearly insufficient to support the jury‘s verdict and ordered a new trial as to the Utah bond claims.
In Ore-Ida Potato Products, Inc. v. Larsen, 83 Idaho 290, 296, 362 P.2d 384, 387 (1961), this Court stated that the general rule in Idaho is that “parties to an unperformed contract may, by mutual consent, modify [the contract] by altering, excising or adding provisions, and such modification may be by parol agreement though the contract is in writing.” The Court further observed that “the party asserting the parol modification of the written contact has the burden of proving the modification by clear and convincing evidence.” Id. at 293-94, 362 P.2d at 385. One party to a written contract cannot alter the terms of the contract,
without the assent of the other [party] and that the minds of the parties must meet as to any proposed modification. The fact of agreement may be implied from a course of conduct in accordance with its existence and assent may be implied from the acts of one party in accordance with the terms of a change proposed by the other.
Furthermore, general principles of contract law require that a contract modification, like the formation of any contract, must be supported by valid consideration. Brand S Corp. v. King, 102 Idaho 731, 733, 639 P.2d 429, 431 (1981). It is well estab-
Relying on the above stated principles, the district court held that clear and convincing evidence established that the original contract between Michetti and GPPC had been modified. The evidence included testimony that GPPC understood that the pipe stringing could not be accomplished as originally bid. The district court found that GPPC was aware of the treacherous weather conditions and knew the job would cost more than originally bid. Moreover, once Michetti informed GPPC that the job could not be done as bid for the original price, GPPC did not commence or threaten to commence any action legal or otherwise. The district court found that, instead, GPPC‘s president stated that the job could not be put off because NWP wanted the job done by April 1, and GPPC was not willing let NWP down. GPPC‘s president assured Michetti that GPPC would take care of the extra costs beyond the original $1.10 per foot bid. In fact, when Michetti prepared a job cost summary disclosing that Michetti lost a total of $187,524.04, GPPC tendered a check to Michetti for that amount. The check was later voided. Lastly, on projects completed by Michetti in the past, GPPC always modified the original agreements and paid any excess expenses incurred by Michetti. Based on this evidence, the district court held that the parties had modified the contract to include amounts in excess of the original $1.10 per foot bid.
Additionally, the district court concluded that the amount GPPC would eventually pay was sufficiently definite for the court to determine the acts to be performed by Michetti and GPPC under the modified contract. In consideration of Michetti staying on the job
We conclude that the district court‘s order determining that the original contract between Michetti and GPPC was modified is supported by substantial competent evidence. Moreover, the amount of Michetti‘s charges were reasonable, and we affirm the district court‘s award of additional costs, plus Michetti‘s original bid and profit.8
6. WHETHER THE DISTRICT COURT ERRED IN CALCULATING HARTFORD‘S LIEN CLAIM.
Hartford supplied worker‘s compensation insurance to GPPC for the Spread 2 project. The district court determined that the value of the insurance provided by Hartford on the Spread 2 project amounted to $987,118. The district court credited $643,932.43 in premiums paid by GPPC, leaving an unpaid amount of $343,185.57. Thus, the district court held that it would be unjust for NWP to retain the benefit of the insurance provided by Hartford and awarded Hartford $332,478.18. Additionally, the jury credited the premiums paid by GPPC on the bond statute claims and awarded Hartford $378,220. However, the district court did not credit the premiums paid by GPPC on Hartford‘s lien claims and held that for purposes of Hartford‘s lien claim, the unpaid amount of its contract with GPPC on the Spread 2 project amounted to $987,118. However, the district court determined that the open account defense barred Hartford‘s lien claim and awarded nothing to Hartford on its lien claim.
On appeal, NWP submits that if this Court reinstates Hartford‘s lien claim, then the district court erred in calculating the amount of Hartford‘s claim for worker‘s compensation premiums. NWP contends that Hartford did
7. WHETHER THE DISTRICT COURT IMPROPERLY FOUND IN FAVOR OF GPE ON ITS LIEN AND UNJUST ENRICHMENT CLAIMS.
NWP asserts as a separate issue that the district court erred in finding for GPE on its mechanic‘s lien and unjust enrichment claims, contending that the open account defense bars GPE‘s lien claims, that GPE was paid by GPPC for the use of its rental equipment on the Spread 2 project, and that the district court erred in not allowing an offset to NWP for the amount that GPE owed to GPPC. Because we have held that GPE was entitled neither to a lien for the rental of its equipment nor to any recovery on the theory of unjust enrichment, we need not address the questions separately raised by NWP as possible defenses in regard to these claims.
8. WHETHER THE DISTRICT COURT ERRED IN REFUSING TO GIVE PRECLUSIVE EFFECT TO THE JURY‘S VERDICT.
NWP asserts that the district court erred in making findings inconsistent with the jury‘s verdict as to the following claimants: Michetti, GPE, PTA, V-1 Oil, Atlas, Beard Oil, Hartford and Rocky Mountain. NWP contends that the bond statute claims and lien claims involved the same issues; therefore, the district court should have given preclusive effect to the jury‘s findings. Additionally, NWP asserts that the district court erred in awarding to GPE, Michetti and PTA more than the reasonable value of the unjust enrichment claims because the jury‘s factual findings placed a cap on damages for the unjust enrichment claims.
9. WHETHER THE DISTRICT COURT ERRED IN REFUSING TO ALLOW AND CONSIDER NWP‘S EQUITABLE DEFENSES.
NWP asserts that the district court erred in refusing to allow NWP to present equitable defenses by way of evidence that several of the claimants did not follow reasonable business practices that could have mitigated their damages. It appears from NWP‘s argument that these defenses relate to the lien claims, Utah bond claims and claims for unjust enrichment which we have held are not proper bases for relief. Accordingly, we need not reach the merits of this issue.
10. WHETHER THE DISTRICT COURT ERRED IN AWARDING ATTORNEY FEES, COSTS AND PREJUDGMENT INTEREST AGAINST NWP.
In Idaho, we adhere to the “American rule” which requires the parties to bear their own attorney fees absent statutory authorization or a contractual right. Idaho Dep‘t of Law Enforcement v. Kluss, 125 Idaho 682, 684, 873 P.2d 1336, 1338 (1994); see also
With the exception of Michetti‘s lien claim, we agree with NWP. The awards of fees, costs and prejudgment interest to each of the
Accordingly, with the exception of Michetti, all awards of attorney fees, costs and prejudgment interest to the plaintiffs are vacated.
B
SUBCONTRACTORS’ CROSS-APPEAL ISSUES
1. WHETHER THE DISTRICT COURT ERRED IN REFUSING TO ALLOW THE CLAIMS FOR PUNITIVE DAMAGES.
During various stages of the litigation in this case, the plaintiffs moved to add a claim for punitive damages. The district court denied the motions on the basis that the motions were untimely. On appeal, Racine Subcontractors, B.D. Holt, and K & O argue that the district court abused its discretion in not allowing the punitive damage claims. Because we hold that the subcontractors—except for Michetti—did not have viable underlying claims of lien, claims for recovery on the Utah bond statute or upon the theory of unjust enrichment, the district court‘s conclusion with respect to the timeliness of the motions to add punitive damage claims need not be addressed. As to Michettis’ claim, we uphold the district court‘s conclusion.
CRC-Evans and Courtesy Ford argue that the district court erred in denying their individual claims for repair parts. As with the other plaintiff-subcontractors, these claims were asserted as claims of liens, as claims under the Utah bond statute or as allegations under the theory of unjust enrichment.
For the reasons stated in Part IV(C)(1), we uphold the district court‘s decision that suppliers of repair parts are not entitled to claim liens under
3. WHETHER THE DISTRICT COURT ERRED IN DETERMINING THAT THE “OPEN ACCOUNT” DEFENSE BARRED VALLEY OFFICE SYSTEMS AND HARTFORD‘S LIEN THEORY CLAIMS.
Valley Office Systems and Hartford Insurance assert that the district court erred in denying their claims because of NWP‘s open account defense. The district court held that the open account defense raised by NWP barred the claims of Valley Office and Hartford both for foreclosure of their claims of lien and for recovery under the Utah bond statute. Because we have held the Utah bond statute inapplicable to this case, we will discuss this issue only with respect to the claims of lien.
Valley Office rented equipment to GPPC. The district court held that Valley Office never relied, to any extent, on NWP or its land for the rental payment but relied exclusively on GPPC for payments. On appeal, Valley Office contends that the district court disregarded uncontroverted testimony that Valley Office first relied on GPPC for pay-
Hartford submits that it is entitled to the full value of its lien claim because the open account defense does not apply to worker‘s compensation claims. We disagree.
In Layrite Products Co. v. Lux, 91 Idaho 110, 416 P.2d 501 (1966), this Court recognized the “open account” defense to be applicable: in situations when a person furnishing material relies exclusively on the general credit of the purchaser, and does not look to the land, structure or building as additional security for the materials sold on credit, then the supplier is not entitled to a lien. Id. at 115, 416 P.2d at 506. Idaho‘s lien statutes, specifically
it is essential that the materials shall have been sold or furnished for the specific purpose of being used in the particular building on which the lien is claimed. Additionally, the materials must have been furnished on the credit of the building, and not merely on the general and personal credit of the owner, contractor or some other person. Where materials are furnished for use in a particular building, the fact that the materialman looks first or primarily to the contractor for payment and only subsequently to the building for security, would not itself defeat the lien.
Id. at 113-14, 416 P.2d at 504-05.
As to Hartford‘s claims, we conclude that sufficient evidence supports the district court‘s decision. We also affirm the district
[n]o substantial evidence was presented that Hartford, in providing worker‘s compensation insurance to the [Spread 2 project], relied to any extent on [NWP] or its land for payment. The evidence presented at trial overwhelmingly demonstrated that Hartford did not know that GPPC was performing work in Idaho until well after the commencement of that work. GPPC‘s policy with Hartford was not endorsed to include Idaho as a covered state on that policy. Hartford attributed none of GPPC‘s premium payments, made during the course of [NWP‘s] job, to GPPC‘s work in Idaho.
Furthermore, Hartford‘s argument that the open account defense does not apply to claims under
4. WHETHER B.D. HOLT‘S CLAIM OF A MECHANIC‘S LIEN WAS UNTIMELY RECORDED.
B.D. Holt asserts that the district court erred in dismissing its mechanic‘s lien claim. B.D. Holt bought a Caterpillar D8N tractor in 1991 and began leasing it to GPPC in July of 1992 to use on the Spread 2 project. However, due to GPPC‘s failure to make lease payments, the parties agreed in March
We conclude that we need not decide whether the district court erred in rejecting B.D. Holt‘s claim of lien for untimeliness. The claim clearly arose either from a rental arrangement, or as a purchase agreement relating to equipment supplied to GPPC by B.D. Holt. B.D. Holt‘s status as a creditor of GPPC under either arrangement does not entitle it to the benefit of the mechanic‘s and materialman‘s lien laws for equipment that was not incorporated into, consumed or destroyed by the project. See Part IV(A)(1) supra.
C
K & O‘S SUMMARY JUDGMENT ISSUES
1. WHETHER THE DISTRICT COURT ERRED IN GRANTING SUMMARY JUDGMENT AS TO K & O‘S CLAIMS.
K & O appeals from the district court‘s summary judgment dismissing K & O‘s claims. NWP moved for summary judgment to dismiss K & O‘s claims because Idaho‘s mechanic‘s lien statutes do not apply to suppliers of “repair parts.” The district court agreed, granted summary judgment as to K & O‘s lien claims, and then subsequently dismissed, as a matter of law, K & O‘s unjust enrichment and Utah bond statute claims. Thus, most of the issues raised are the same as discussed above, however, the standard of review for all of K & O‘s claims are based on summary judgment.
Summary judgment must be granted when “the pleadings, depositions, and admissions on file, together with the affidavits, if any,
a. Repair Parts are Not Covered Under Idaho‘s Mechanic‘s Lien Statute.
K & O asserts that the district court‘s holding that “the parts and repairs supplied by K & O contributed, primarily, to the repair of the equipment and not to the construction of Northwest‘s pipeline” was erroneous. K & O contends that the repair parts which allowed two link-belt machines to keep working on the Spread 2 project benefited NWP, and whether the repair parts were used and consumed on the NWP job is debatable.
As previously stated,
Here, K & O supplied repair parts to maintain equipment, rented by GPPC, and used to construct NWP‘s Spread 2 project. The specific parts supplied by K & O included: hex screws and nuts, rod end, pawl rod and screw, back up rings, O-rings, washers, clutch shoes, lining kits, rivets, ball bearings, oil seals, bushing, dowel, piston ring, gaskets, shims, snap ring, roller chain, lock nut, spacers, a service manual, sprockets, bevel gear and a shaft. However, K & O‘s parts never became a part of the pipeline and were not used, consumed or destroyed in the course of the work.
Like leased equipment used on the Spread 2 project which would not be totally consumed, parts supplied to repair leased equipment would only enhance and add to the useful life of the leased equipment. Accord Johnson v. Starret, 127 Minn. 138, 149 N.W. 6, 8 (1914) (holding that parts and repairs for excavating machinery were not lienable because they were not consumed within the improvement, but merely became part of the contractor‘s personal property). The parts and repairs were not actually used and consumed in the construction of the Spread 2 project. Instead, the equipment‘s need for parts and repairs was based, at least in part, on the equipment‘s use prior to its service on the Spread 2 project. Additionally, the parts and repairs would certainly add to the equipment‘s future use. Thus, to allow K & O a lien for parts and repairs to rental equipment used on the Spread 2 project would essentially force NWP to pay for repairs and parts that would benefit the owner of the equipment well beyond the equipment‘s use on the Spread 2 project. Accordingly, we affirm the district court‘s decision to grant NWP‘s motion for summary judgment as to K & O‘s lien claims.
b. Repair parts are not covered under Utah‘s private bond statute.
K & O asserts that the district court erred in concluding that repair parts are not covered by the Utah bond statute. Because we have concluded that the Utah bond statute provides no relief in this case, we affirm
c. Repair parts are not covered under unjust enrichment law.
K & O contends that genuine issues of material fact exist as to its unjust enrichment claim, which would preclude the district court from denying the claim by summary judgment. Because we conclude that the subcontractors cannot recover on the theory of unjust enrichment, we affirm the district court‘s decision granting summary judgment to NWP on this issue, albeit on other grounds. Anderson & Nafziger v. G.T. Newcomb, Inc., 100 Idaho 175, 179, 595 P.2d 709, 713 (1979).
2. WHETHER THE DISTRICT COURT ERRED IN AWARDING ATTORNEY FEES AND COSTS TO NWP.
K & O asserts that NWP failed to make a timely request for attorney fees and failed to make the petition in the proper form pursuant to
V.
CONCLUSION
For the above stated reasons, we set aside the judgment and decree regarding foreclosure of the mechanic‘s liens, the Utah bond claims and unjust enrichment claims, with the exception of the judgment permitting foreclosure of Michetti‘s claim of lien. We also vacate the awards of prejudgment interest, attorney fees and costs entered in favor of the plaintiffs, except for the awards of those items to Michetti on its claim of lien foreclosure. We affirm the summary judgment entered on K & O‘s causes of action and the award of attorney fees and costs to NWP against K & O.
No attorney fees or costs are awarded on appeal.
Chief Justice TROUT, and Justices Pro Tem JOHNSON, and MORFITT, CONCUR.
Justice SCHROEDER, CONCURS in part and DISSENTS in part.
I respectfully dissent from that portion of the opinion which determines that the district court erred in allowing claims based upon Utah‘s private bond statute. GPPC and NWP entered into the contract in Utah and specified that Utah law would apply. Each acted pursuant to the agreement. GPPC and NWP waived the bond requirement. Under these circumstances Utah‘s private bond statute should be applied, as determined by the district court.
Notes
(1) For purposes of this chapter:
(a) “Contractor” means any person who is or may be awarded a contract for the construction, alteration, or repair of any building, structure, or improvement upon land.
(b) “Owner” means any person contracting for construction, alteration, or repair of any building, structure, or improvement upon land.
(2) (a) Except as provided in Subsection (2)(b), before any contract exceeding $2,000 in amount for the construction, alteration, or repair of any building, structure, or improvement upon land is awarded to any contractor, the owner shall obtain from the contractor a payment bond complying with Subsection (3).
The bond shall become binding upon the award of the contract to the contractor.
(3) The payment bond shall be with a surety or sureties satisfactory to the owner for the protection of all persons supplying labor, services, equipment, or material in the prosecution of the work provided for in the contract in a sum equal to the contract price.
(1) Unless exempted under Section 14-2-1, an owner who fails to obtain a payment bond is liable to each person who performed labor or services or supplied equipment or materials under the contract for the reasonable value of the labor or service performed or the equipment or materials furnished up to but not exceeding the contract price.
(3) In an action for failure to obtain a bond, the court may award reasonable attorneys’ fees to the prevailing party. These shall be taxed as costs in the action.
Enforcement by beneficiary— A contract, made expressly for the benefit of a third person, may be enforced by him at any time before the parties thereto rescind it.
