Appeal of Lake Sunapee Protective Ass'n
165 N.H. 119
| N.H. | 2013Background
- The State (F&G) sought DES permits to build a two-ramp public boat launch with parking on the 3.3-acre Wild Goose parcel of a 135-acre State-owned site on Lake Sunapee; the State acquired the land to provide public boat access.
- F&G submitted an alternatives analysis and acknowledged the project would violate two minimum shoreland-protection standards (waterfront buffer tree-point requirement and natural woodland buffer unaltered-vegetation percentage).
- DES issued a shoreland impact permit (January 7, 2009) and an amended permit (May 22, 2009) allowing the boat launch and limiting impervious cover; plans did not show the local 75-foot setback.
- Petitioners (Lake Sunapee Protective Association and Town of Newbury) appealed to the Wetlands Council arguing DES violated RSA 483-B:9, IV-b (must permit public water access only "as necessary and consistent with" Act and other state law) and RSA 483-B:3, II (must apply more stringent local setback).
- The Wetlands Council upheld DES (except on a separate, non‑raised ground), finding no way to build a ramp that complied with all minimum standards and that DES properly reviewed the project against the Act’s purposes; petitioners appealed to the NH Supreme Court.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether DES violated RSA 483-B:9, IV-b by issuing a permit without showing the project was "necessary" and consistent with the Act's purposes and other state law | Petitioners: DES failed to evaluate whether the boat launch (or its size) was necessary, considered only two of the Act's 16 purposes, failed to analyze conflicts with RSA 233-A and RSA 162-C, and did not make specific statutory findings | DES: "As necessary" means a permit is required for the project to proceed; DES need not second-guess need/design reserved to other agencies and did review the project against the Act's purposes and standards | Court: Affirmed DES — "as necessary" means necessary for completion of the project; DES properly considered the Act's purposes and had adequate record support; DES need not enforce or police other agencies' statutes (RSA 233-A, 162-C) in this permitting context |
| Whether DES was required to enforce a more stringent local 75-foot shoreland setback under RSA 483-B:3, II | Petitioners: The local 75-foot setback is more stringent than the Act's 50-foot rule and DES must apply the more stringent local standard | DES/Wetlands Council: RSA 483-B:3, II does not apply to this RSA 483-B:9, IV-b approval; additionally, State projects are generally exempt from local zoning restrictions absent clear legislative intent | Court: Affirmed Wetlands Council — petitioners challenged only the exemption rationale, but the Council’s primary ground (RSA 483-B:3, II does not apply to IV-b approvals) stands and is sufficient to uphold the decision |
Key Cases Cited
- Appeal of Garrison Place Real Estate Inv. Trust, 159 N.H. 539 (N.H. 2009) (standard of review for Wetlands Council factual findings)
- In re Christopher K., 155 N.H. 219 (N.H. 2007) ("shall" as mandatory command)
- Appeal of Geekie, 157 N.H. 195 (N.H. 2008) (avoid literal statutory reading producing absurd result)
- Ocasio v. Fed. Express Corp., 162 N.H. 436 (N.H. 2011) (consistent meaning of statutory terms across provisions)
- Appeal of City of Nashua, 138 N.H. 261 (N.H. 1994) (distinguishing adjudicative findings requirements)
- Appeal of Town of Bethlehem, 154 N.H. 314 (N.H. 2006) (agency actions versus adjudicative proceedings)
- Region 10 Client Mgt., Inc. v. Town of Hampstead, 120 N.H. 885 (N.H. 1980) (state generally exempt from local zoning rules absent clear legislative intent)
- Vogel v. Vogel, 137 N.H. 321 (N.H. 1993) (appellate discretion to decline extended consideration of non‑dispositive arguments)
