midpage
Projects
Sign in to see your projects.
139 F.4th 903
D.C. Cir.
2025
Read the full case

Background

  • Mountain Valley Pipeline, LLC (MVP) sought an extension of a construction deadline for its Southgate Project, an extension of the Mainline natural gas pipeline.
  • The Southgate Project's original completion deadline (June 18, 2023) could not be met due to delays in Mainline permitting and litigation, which were prerequisites for Southgate construction.
  • FERC (the Federal Energy Regulatory Commission) granted MVP a three-year extension for the Southgate Project, finding good cause due to circumstances beyond MVP’s control.
  • Environmental groups challenged FERC’s decision, arguing the extension was not justified and that market need and environmental impact assessments were now outdated and should be revisited.
  • The D.C. Circuit reviewed these petitions seeking to overturn FERC’s order, focusing only on the extension decision (not the merits of any proposed amendment to the project).

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether FERC properly found “good cause” for deadline extension MVP did not actively pursue permits for Southgate and is abandoning the original project Mainline permitting delays were beyond MVP's control, and extension is justified FERC reasonably found good cause in light of Mainline delays
Whether FERC should revisit market need and environmental findings Changed circumstances (e.g., market demand, new incentives) render past findings obsolete No significant new evidence; previous findings remain valid absent major changes FERC had discretion not to revisit prior findings; no major changes shown
Sufficiency of mitigation measures for erosion and sedimentation Mainline had past failures; Southgate likely to suffer similar environmental harms Southgate has improved measures and different circumstances; agency fully considered these issues FERC’s review and mitigation measures met legal requirements
Whether extension required supplemental NEPA analysis Extension plus project updates trigger NEPA analysis anew No significant changes yet; future amendments will be reviewed under NEPA FERC’s refusal to do supplemental NEPA review at extension stage was reasonable

Key Cases Cited

  • Sierra Club v. FERC, 97 F.4th 16 (D.C. Cir. 2024) (Commission may revisit need/environmental findings only if circumstances become significantly outdated)
  • Baltimore Gas & Elec. Co. v. Nat. Res. Def. Council, 462 U.S. 87 (1983) (Agency judgments on technical matters receive considerable deference)
  • Motor Vehicle Mfrs. Ass’n of U.S., Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (1983) (Agency must articulate rational connection between facts and decisions)
  • Robertson v. Methow Valley Citizens Council, 490 U.S. 332 (1989) (NEPA is procedural; agencies must consider environmental impacts but not reach particular outcomes)
  • Loper Bright Enters. v. Raimondo, 603 U.S. 369 (2024) (Review of agency authority and discretionary standards)
  • PennEast Pipeline Co. v. New Jersey, 594 U.S. 482 (2021) (Background on NGA regulation of natural gas infrastructure)
  • Citizens Against Burlington, Inc. v. Busey, 938 F.2d 190 (D.C. Cir. 1991) (Scope and limits of NEPA alternatives analysis)
Read the full case

Case Details

Case Name: Appalachian Voices v. FERC
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Jun 6, 2025
Citations: 139 F.4th 903; 24-1094
Docket Number: 24-1094
Court Abbreviation: D.C. Cir.
Log In
    Appalachian Voices v. FERC, 139 F.4th 903