History
  • No items yet
midpage
893 F.3d 786
D.C. Cir.
2018
Read the full case

Background

  • FERC issued Order No. 1000 (2011) to promote interregional transmission projects and required neighboring RTOs/ISOs to adopt interregional cost-allocation methods that allocate costs "roughly commensurate with benefits."
  • MISO proposed a "cost-avoidance" allocation: MISO’s share equals costs of regional projects the interregional project would avoid, but MISO excluded from that calculation any regional projects already approved by MISO’s board.
  • FERC accepted MISO’s methodology in part but rejected the exclusion of approved projects, concluding that omission would undervalue interregional benefits and thus misallocate costs and discourage efficient interregional projects.
  • MISO and its transmission-provider members sought rehearing; FERC denied rehearing. Petitioners (MISO members) filed for review in this court; MISO intervened in support of petitioners.
  • The petition raised standing, ripeness, exhaustion, and merits challenges: chiefly that FERC’s requirement to count approved projects would (1) displace approved projects harming stakeholders and (2) violate FERC’s obligations under section 206 of the Federal Power Act.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Standing Petitioners: FERC orders injure transmission providers; MISO also affected FERC: injuries speculative; no causal link Court: MISO (intervenor) has standing; thus reviewable
Ripeness Petitioners: present dispute ripe because FERC justified rule based on displacement risk FERC: unripe—displacement speculative; can seek rehearing if/when occurs Court: claims ripe; factual development not needed to assess adequacy of FERC's explanation
Exhaustion (section 206 claim) Petitioners: FERC failed to make affirmative section 206 finding; claim inherent in any rate challenge FERC: petitioners did not raise this argument on rehearing Held: petitioners failed to exhaust this specific section 206 argument; waived for review
Merits (adequacy of FERC’s response re displacement) Petitioners: FERC ignored harms from displacing approved projects (investor harm, financing uncertainty, unfairness) FERC: excluding approved projects would undervalue interregional benefits, misallocate costs, and reduce incentives to pursue efficient interregional projects; other regions follow FERC’s approach Held: FERC adequately considered and rationally rejected petitioners’ concerns; denial not arbitrary or capricious; petition denied

Key Cases Cited

  • Lujan v. Defenders of Wildlife, 504 U.S. 555 (standing requires concrete injury, causation, redressability)
  • Rumsfeld v. Forum for Academic & Institutional Rights, Inc., 547 U.S. 47 (one party with standing suffices for Article III)
  • Diamond v. Charles, 476 U.S. 54 (intervenor may maintain appeal if it has standing)
  • PPL Wallingford Energy LLC v. FERC, 419 F.3d 1194 (agency must respond meaningfully to objections)
  • Aera Energy LLC v. FERC, 789 F.3d 184 (court defers when agency articulates rational connection between facts and choice)
  • Transcontinental Gas Pipe Line Corp. v. FERC, 518 F.3d 916 (standard for judicial review of FERC determinations)
Read the full case

Case Details

Case Name: Ameren Servs. Co. v. Fed. Energy Regulatory Comm'n
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Jun 22, 2018
Citations: 893 F.3d 786; 16-1150
Docket Number: 16-1150
Court Abbreviation: D.C. Cir.
Log In
    Ameren Servs. Co. v. Fed. Energy Regulatory Comm'n, 893 F.3d 786