Lead Opinion
Opinion for the Court filed by Senior Circuit Judge SENTELLE.
Concurring statement filed by Senior Circuit Judge SILBERMAN.
Petitioner Kern River Gas Transmission Company owns and operates an interstate pipeline that transports natural gas from its production area in Wyoming to markets in Utah, Nevada, and California. Petitioners Aera Energy LLC and several other natural gas and transportation companies (collectively “Shippers”) ship natural gas using Kern River’s pipeline. In their consolidated petitions, Kern River and the Shippers seek review of different aspects of seven orders issued by the Federal Energy Regulatory Commission during rate proceedings. We conclude that the Commission complied with the Natural Gas Act and our precedents. The Commission responded meaningfully to petitioners’ objections and articulated a rational explanation for its decisions under the particularly deferential standard of review we apply to ratemaking decisions. We therefore deny the petitions for review.
I.
A. Factual Background
To construct a pipeline, a natural gas company must first obtain a certificate from the Commission. See 15 U.S.C. § 717f(c). When Kern River applied for its certificate, then-existing regulations allowed it to obtain an optional certificate and assume the economic risks of the project. FERC approved Kern River’s optional certificate and permitted Kern River to charge separate rates during three periods: (1) Period One, the 15-year term of the original contracts; (2) Period Two, the period from the expiration of those con
Unlike a traditional rate structure, in which a pipeline charges higher rates during the early years of its life, Kern River’s levelized rate plan provided lower rates during the early years of operation. Lower initial rates help new .pipelines market their capacity and compete with other established pipelines. There is, however, a trade-off. By charging lower rates during the first half of the levelization period, Kern River defers the recovery of costs that it would otherwise recover during the early years of operation if it had used a traditional rate structure. Kern River therefore entered into long-term contracts with the Shippers, which extend beyond the initial period of lower rates, to ensure that it will adequately recover its costs.
With respect to calculating Kern River’s return on capital investment, FERC recognized that Kern River would not maintain its original ratio of 70 percent debt and 30 percent equity over the course of the pipeline’s life. Kern River Gas Transmission Co.,
In 1992, FERC issued the certificate order, and Kern River started operating its pipeline. Eight years later, Kern River proposed to lower its shipping rates by refinancing its debt. All existing customers, referred to as “original shippers,” extended the terms of their contracts in exchange for lower rates. Some original shippers agreed to new 10-year contracts (2001 to 2011), while others agreed to new 15-year contracts (2001 to 2016). FERC approved the proposal, allowing levelized rates to continue and permitting Kern River, consistent with its original certificate order, to recover its debt “by the end of the new debt repayment period.” Kern River Gas Transmission. Co.,
A few years later, Kern River sought to increase the capacity of its pipeline. Because of the unique nature of its existing levelized rate plan, Kern River could not use typical roll-in methodology to recover its expansion costs. Kern River therefore proposed to roll the costs of the proposed expansion into the cost of the original system by adjusting the rates for all “rolled-in” shippers (i.e., existing customers and new expansion customers). Kern River Gas Transmission Co.,
*188 • Original shippers with 10-year contracts (2001 to 2011)
• 2002 expansion shippers with 10-year . contracts (2002 to 2012)
• 2003 expansion shippers with 10-year contracts (2003 to 2013)
• Original shippers with 15-year contracts (2001 to 2016)
• 2002 expansion shippers with 15-year contracts (2002 to 2017)
• 2003 expansion shippers with 15-year contracts (2003 to 2018).
B. Procedural Background
In 2004, Kern River filed a general rate case pursuant to Section 4 of the Natural Gas Act, 15 U.S.C. § 717c, seeking to adjust Period One rates (at that time, all customers were paying Period One rates). Kern River Gas Transmission Co., Initial Decision,
In a series of orders, the Commission affirmed the administrative law judge’s finding that Kern River’s adjusted Period One rates should continue to be based on its levehzed methodology and addressed Kern River’s subsequent compliance filings with revised cost-of-service and cost-allocation elements. Kern River Gas Transmission Co., Opinion No. 486, Order on Initial Decision,
To ensure that the Shippers would benefit from lower Period Two rates, the Commission expanded the scope of the rate proceedings to include Period Two rates. See Opinion No. 486,
In Opinion No. 486-D, FERC stated that it would consider “circumstances unique to the transition from Period One to Period Two rates that justify an adjustment to the cost of service underlying the Period One rates.”
The Commission affirmed the administrative law judge’s initial decision on all matters, except one issue not relevant here, and denied rehearing. Opinion No. 486-E,
Kern River filed a timely petition for review of Opinion Nos. 486 through 486-F. It raises two issues: (1) whether FERC erred in setting the effective date for Period One rates; and (2) whether FERC erred by refusing to consider its proposed cost-of-service adjustment for Period One rates after Opinion No. 486-D. The Shippers filed a timely petition for review of Opinion Nos. 486-E and 486-F. They argue that FERC erred when it did not reduce Kern River’s return on equity in Period Two. We consolidated the petitions.
II.
Under the Administrative Procedure Act, we will set aside FERC’s orders if they are arbitrary, capricious, an abuse of discretion, or otherwise not in accor
A. Kern River’s Petition
Kern River advances several arguments as to why it thinks FERC’s orders are arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with the law. None have merit.
1. Setting the Effective Date of Period One Rates
Kern River contends that FERC’s decision to fix the prospective Period One rates as of December 17, 2009, the date it issued Opinion No. 486-C, is contrary to the plain language of the Natural Gas Act and controlling precedent. Kern River asks us to set the effective date of the Period One rates as November 18, 2010, the date FERC accepted Kern River’s supplemental compliance filing in Opinion No. 486-D. We reject Kern River’s arguments and deny its petition for review.
Before it can fix a new rate, FERC must find the prospective rates “just and reasonable.” 15 U.S.C. § 717d(a). Because FERC found an aspect of the prospective Period One rates unjust and unreasonable and ordered Kern River to submit “a substantively new compliance filing,” Kern River argues that FERC could not have fixed the rates under Section 5 of the Natural Gas Act as of the date of Order No. 486-C. Kern River Br. 20. In support of its argument, Kern River relies on Electrical District No. 1 v. FERC, where we explained “that the statute means what it says” — when fixing a rate, it is not enough for FERC “to prescribe the legal and accounting principles which, properly applied, will yield one particular rate” because the statute “requires the rate itself to be specified.”
In Electrical District, we considered the effective “date of an order setting forth no more than the basic principles pursuant to which the new rates are to be calculated.”
*191 The Commission need not confine rates to specific, absolute numbers but may approve a tariff containing a rate “formula” or a rate “rule” (as Public Service Co. of New Hampshire assumed); it may not, however, simply announce some formula and later reveal that the formula was to govern from the date of announcement (as it had done in Electrical District).
The circumstances here, FERC correctly determined, are unlike those in Electrical District. See Opinion No. 486-D,
Kern River suggests, however, that Transwestem is inapplicable because its tariff contains neither a formula nor a rule; instead, it contains “rate models.” See, e.g., Kern River Br. 21, 26-27, 29. Since its rate models are so complex, Kern River points out that “no party (not Kern River, FERC, nor any shipper) knew the effective prospective Period One rates until all levelized rate models had been rerun with the changed components.” Kern River Br. 27; see also Opinion No. 486-D,
FERC’s conditional acceptance of Period One rates in Opinion No. 486-C simply required Kern River to substitute one number for another when allocating costs to the rolled-in shippers. See
The Shippers, moreover, could have calculated the rates on their own. See Kern River Gas Transmission Co.,
2. Adjusting the Period One Rate Credit
Kern River argues that FERC failed to respond meaningfully to its objections, and the Commission’s nonresponse rendered its decisions arbitrary and capricious. See, e.g., PSEG Energy Res. & Trade LLC v. FERC,
At the outset, FERC suggests that we need not consider Kern River’s argument because it “twice waived” any contention that Opinion No. 486-D was not final— Kern River never raised the argument on rehearing before the Commission or in its opening brief here. Xcel Energy Servs. Inc. v. FERC,
We uphold FERC’s decisions because “the agency’s path may reasonably be discerned” from the record. Motor Vehicle Mfrs. Ass’n of U.S., Inc. v. State Farm Mut. Auto. Ins. Co.,
FERC acknowledges that it did not reiterate the administrative law judge’s analysis related to Kern River’s proposed cost-of-service adjustment for Period One rates in Opinion Nos. 486-E and 486-F. However, “[t]he Commission is not required to recapitulate the reasoning of the [administrative law judge] if it is satisfied that the initial decision and the reasoning underlying it are sound.” Boroughs of Ellwood City v. FERC,
Kern River misreads Opinion No. 486-D as an invitation to reopen the Period One evidentary record to adjudicate its proposed cost-of-service adjustment for Period One rates. As we have previously explained: “Reopening an evidentiary hearing is a matter of agency discretion, and is reserved for extraordinary circumstances.” Cities of Campbell v. FERC,
The Commission’s basis for refusing to consider Kern River’s rolled-in rate credit argument can be reasonably discerned from the record. See Motor Vehicle Mfrs. Ass’n,
In sum, FERC correctly set the effective date of Period One rates as December 17, 2009, and FERC did not abuse its discretion by refusing to reopen the Period One evidentiary record after it issued Opinion No. 486-D. Kern River advances additional arguments, but none warrant relief or compel further discussion.
B. Shippers’ Petition
Because of the reduced financial risk associated with being debt free in Period Two, the Shippers urged FERC to lower Kern River’s return on equity for Period Two rates. FERC refused. The Shippers argue that FERC failed to engage in reasoned decision making after it: (1) failed to address the reduced financial risk associated with 100 percent equity in Period Two; (2) relied on an irrational composite capital structure; (3) assumed increased business risk would offset decreased financial risk; and (4) failed to follow its precedent, which requires a reduction in the return on equity. The Shippers ask us to reverse Opinion Nos. 486-E and 486-F and remand with instructions for FERC to reduce Kern River’s return on equity in Period Two. We deny the Shippers’ petition under the deferential
1. Financial Risk
In general, “the higher the proportion of equity capital, the lower the financial risk ... and thus, in this respect, the lower the necessary rate of return” on equity. Missouri Pub. Serv. Comm’n v. FERC,
FERC reasonably explained why the Shippers’ argument lacks merit. When it set Kern River’s return on equity for Period Two, FERC considered how investors in 2004 would have viewed the transition from a 30 percent equity structure in Period One to the 100 percent equity structure in Period Two. See Opinion No. 486-E,
2. Composite Equity
The Shippers contend that FERC unjustifiably abandoned the notion of separate capital structures in Period One and Period Two when it referred to a “composite equity” standard. Shippers Br. 21 (quoting Opinion No. 486-E,
We reject the Shippers’ arguments because they ignore the context of the Commission’s reference to “composite equity” in Opinion No. 486-E. Considering the reference in context, we conclude that FERC did not abandon the separate capital structures for each period when it referred to
3. Business Risk
The Shippers advance several arguments suggesting that FERC’s analysis of Kern River’s business risk is inconsistent and not supported by the record. None are persuasive.
The Shippers urged FERC to set Kern River’s return on equity at the lowest reasonable level because, in their view, Kern River’s business risk is substantially reduced during Period Two by the 100 percent equity structure. FERC explained that a low return on equity would only be appropriate if “Kern River’s business risk would necessarily be so low that investors could be assured that changes in Kern River’s capital structure would offset all of the potential competition from new pipeline capacity or gas supply.” Opinion No. 486-E,
First, FERC determined the record was insufficient to conclude that the change in capital structure over time would completely offset “incentive[s] for entry by competing firms,” which “would be hard to quantify in 2004.” Opinion No. 486-E,
Second, FERC concluded that the record did “not provide compelling evidence that” the gradual transition in capital structure would completely offset Kern River’s re-contracting risk as Period One contracts expired. Opinion No. 486-E,
The Shippers suggest that FERC cited lower Period Two rates as a factor that would reduce re-contracting risk. Again, context matters. While addressing the return on equity for Period One rates, FERC noted: “Kern River’s competitive position should be enhanced” as the reduced Period Two rates become effective. Opinion No. 486-B,
The Shippers further contend that re-contracting risk during the transition period “ ‘would unlikely have been visible even to the most discerning [2004] investor.’ ” Shippers’ Reply Br. 6 (quoting Opinion No. 486-E,
Because FERC rejected re-contracting risk as a basis for decreasing rate design volumes, the Shippers argue it is inconsistent for FERC to refuse to lower Kern River’s return on equity based on re-contracting risk. Their argument misses the mark because the rate design analysis for volume takes post-2004 test period data into account, whereas the return on equity analysis does not. Simply put, FERC has
4. Precedent
The Shippers contend that FERC departed from its precedent without providing a reasoned explanation. We disagree.
FERC acknowledged that Kern River’s 100 percent equity capital structure is “unique” and “anomalous.” See e.g., Opinion No. 486-F,
The Shippers raise additional arguments, but none warrant relief or compel further discussion.
Under the particularly deferential standard of review we apply to the Commission’s ratemaking decisions, we deny the petitions for review.
So ordered.'
Concurrence Opinion
concurring:
I wish FERC’s briefing was as clear as Judge Sentelle’s opinion.
