History
  • No items yet
midpage
Alliance to Protect Nantucket Sound, Inc. v. Department of Public Utilities
461 Mass. 166
Mass.
2011
Read the full case

Background

  • National Grid entered into two long-term PPAs (PPA-1 and PPA-2) with Cape Wind under the Green Communities Act § 83 to procure renewable energy.
  • Interveners Alliance, AIM, NEPGA, and TransCanada challenged the Department of Public Utilities’ approval, arguing commerce clause violations and process issues.
  • § 83 requires distribution companies to solicit renewable proposals twice in five years and to seek approvals balancing costs and benefits; it also restricts capacity to 3% absent a best-interest finding.
  • The department suspended the geographic limitation in § 83 during the relevant proceedings, allowing in-state and adjacent federal waters sources; National Grid proceeded with individual negotiations for PPA-1.
  • PPA-1 covers 234 MW for 15 years; PPA-2 mirrors PPA-1 but contemplates assignment to another purchaser; department approved PPA-1 and denied PPA-2.
  • The court remands to the county court with instruction to affirm the department’s decision.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Does the geographic limitation violate the dormant Commerce Clause? Alliance and TransCanada contend it discriminates against out-of-state generators. Department found no Commerce Clause violation; National Grid acted independent of the limitation under suspension. Commerce clause challenge rejected; no constitutional violation.
Was the cost-effectiveness finding supported by substantial evidence? Alliance and TransCanada argue department erred by not considering lost opportunity costs and treating cost-effectiveness as lowest cost. Department adopted a broader cost-benefit view, including nonquantified benefits and environmental considerations. Department's cost-effectiveness finding upheld.
Was the public interest finding supported by substantial evidence? Alliance argues PPA-1’s above-market costs are not outweighed by benefits. Cape Wind’s location, size, and reliability benefits justify the higher cost. Public interest finding sustained.
Was individual negotiations permissible under § 83 as opposed to competitive bidding? NEPGA argues multiple bids were required; otherwise competitive bidding should apply. Statute allows individual negotiations; plural form of 'proposals' does not mandate multiple proposals. Reasonable interpretation that individual negotiations may be used; approved.
Did the department exceed its authority by cost-recovering above-market costs across all customers? AIM/NEPGA argue recovery method imprudent or ultra vires. Statutory framework and broad rate-filing authority authorize cross-customer cost recovery for environmental benefits. Cost recovery method approved; benefits allocated to all customers.

Key Cases Cited

  • Cambridge v. Department of Telecomm. & Energy, 449 Mass. 868 (Mass. 2007) (deference to agency statutory interpretation; complex regulatory framework)
  • DSCI Corp. v. Department of Telecomm. & Energy, 449 Mass. 597 (Mass. 2007) (deference to agency expertise; statutory review standards)
  • Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Bd., 448 Mass. 45 (Mass. 2006) (agency interpretation given substantial deference; statutory construction)
  • City Council of Agawam v. Energy Facilities Siting Bd., 437 Mass. 821 (Mass. 2002) (harmonious reading of related statutes; agency discretion)
  • Commonwealth v. Russ R., 433 Mass. 515 (Mass. 2001) (implied repeal and specific vs general statute interpretation)
Read the full case

Case Details

Case Name: Alliance to Protect Nantucket Sound, Inc. v. Department of Public Utilities
Court Name: Massachusetts Supreme Judicial Court
Date Published: Dec 28, 2011
Citation: 461 Mass. 166
Court Abbreviation: Mass.