932 F.3d 940
D.C. Cir.2019Background
- Transcontinental Gas Pipe Line Co. (Transco) sought and FERC granted a certificate under the Natural Gas Act to build the Atlantic Sunrise pipeline (applied 2015; certificate issued Feb. 2017).
- FERC issued a Final Environmental Impact Statement in Dec. 2016 and authorized construction in Sept. 2017; construction began the same day.
- Homeowners whose land was to be taken and Environmental Associations filed rehearing petitions and stay motions; FERC issued tolling orders (granting rehearing for "further consideration") and ultimately denied rehearing months later.
- Homeowners lost in a district court eminent-domain action, which treated FERC’s certificate as conclusively establishing public use; appeals to this court followed.
- The D.C. Circuit consolidated challenges and affirmed FERC: plaintiffs argued NEPA violations (downstream GHGs, segmentation, alternatives), inadequate market-need finding, and that authorizing construction during tolling denied due process.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| NEPA — downstream GHG emissions | FERC failed to consider downstream (end-use) greenhouse-gas emissions as an indirect effect. | FERC did consider and quantify downstream CO2 and explained offsets and net effects in EIS and orders. | Court: FERC satisfied NEPA; plaintiffs identify no additional required analysis. |
| NEPA — segmentation with Southeast Market Pipeline | FERC improperly segmented environmental review and should have analyzed pipelines together. | The two projects have substantial independent utility; separate analyses were proper. | Court: No improper segmentation; record supports independent utility. |
| NEPA — alternative (Conestoga Route) analysis | FERC insufficiently considered the Conestoga Route as a reasonable alternative. | FERC compared routes, weighed tradeoffs, and reasonably explained its choice. | Court: FERC’s alternatives analysis was adequate. |
| Market need under NGA | Project lacks demonstrated market need; contracts etc. insufficient. | Transco had preconstruction contracts covering 100% capacity and supporting evidence of demand. | Court: Market-need requirement satisfied by contracts and supporting evidence. |
| Due process — construction during tolling/rehearing | Tolling orders and allowing construction before final agency action deprived homeowners of meaningful process and review (property taken before court access). | Tolling orders are permissible; rehearing is a statutory precondition and petitioners must await FERC action; eminent-domain courts treat certificates as controlling. | Court: Precedent forecloses plaintiffs’ due-process claim; petitions denied. Concurring judge: cautioned that tolling practice creates unfairness though bound by precedent. |
Key Cases Cited
- Myersville Citizens for a Rural Community, Inc. v. FERC, 783 F.3d 1301 (D.C. Cir. 2015) (NEPA/alternatives precedent)
- Sierra Club v. FERC, 867 F.3d 1357 (D.C. Cir. 2017) (downstream emissions and market-need discussion)
- Delaware Riverkeeper Network v. FERC, 857 F.3d 388 (D.C. Cir. 2017) (NEPA obligations of FERC)
- Delaware Riverkeeper Network v. FERC, 895 F.3d 102 (D.C. Cir. 2018) (tolling-order precedent discussed)
- City of Boston Delegation v. FERC, 897 F.3d 241 (D.C. Cir. 2018) (segmentation/substantial independent utility)
- Minisink Residents for Envtl. Pres. & Safety v. FERC, 762 F.3d 97 (D.C. Cir. 2014) (alternatives analysis standard)
- Clifton Power Corp. v. FERC, 294 F.3d 108 (D.C. Cir. 2002) (rehearing prerequisite to review)
- Midcoast Interstate Transmission, Inc. v. FERC, 198 F.3d 960 (D.C. Cir. 2000) (public-use determination and takings)
- FERC v. Electric Power Supply Ass'n, 136 S. Ct. 760 (2016) (agency decision review standard)
- Mathews v. Eldridge, 424 U.S. 319 (1976) (due-process balancing test)
- Loretto v. Teleprompter Manhattan CATV Corp., 458 U.S. 419 (1982) (physical occupation and property interests)
- Knick v. Township of Scott, 139 S. Ct. 2162 (2019) (prompt access to federal review for takings claims)
