History
  • No items yet
midpage
328 Barry Avenue, LLC v. Nolan Properties Group, LLC
871 N.W.2d 745
Minn.
2015
Read the full case

Background

  • 328 Barry Avenue, LLC (328 LLC) hired Nolan Properties Group, LLC (NPG) as general contractor for a commercial building; both companies are owned by John Nolan. NPG subcontracted most work and had no written contract with 328 LLC.
  • During construction in Oct–Nov 2009, a subcontractor observed water intrusion around an east-side window; subcontractor applied some sealant and performed a hose test; no repairs beyond that are clearly documented.
  • Certificate of occupancy issued Jan 2010; parties agree construction was substantially complete by May 2010 and occupied thereafter.
  • In August 2010 328 LLC again observed water on the floor; later inspections (2011–2012) revealed leaks and widespread water damage around multiple windows and defective installations.
  • 328 LLC sued NPG for negligence on June 14, 2012. District court granted summary judgment holding the suit time-barred under Minn. Stat. § 541.051, subd. 1(a) (2‑year discovery rule); the court of appeals affirmed. The supreme court affirmed the statutory interpretation but reversed in part and remanded on the factual discovery issue.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether § 541.051(1)(a) requires substantial completion before accrual Limitations cannot run before substantial completion; pre-completion defects may be remediable and not an actionable injury Plain text triggers accrual on "discovery of the injury," not on substantial completion Court: statute unambiguous — accrual depends on discovery, not substantial completion; will not read "substantial completion" into the limitations clause
When did the 2-year limitations period begin (discovery date)? Discovery occurred in Aug 2010 when widespread water intrusion was observed; the Oct–Nov 2009 leak was an isolated, remediable construction issue Discovery occurred in Oct–Nov 2009 when leak was first observed and tested; that notice started the limitations clock Court: factual dispute exists whether 2009 leak was remedied or constituted discoverable injury; summary judgment improper; remand for fact resolution
Whether owner must know the injury’s cause or extent to start limitations Argues that mere knowledge of a leak during construction is not necessarily knowledge of an actionable injury Defendants cite precedents holding notice of some injury or need to repair starts limitations Court: owner need not know full cause/extent, but here reasonable minds could differ whether 2009 events constituted discovery of actionable injury
Effect of applying accrual during construction on statute of repose Plaintiff: would render 10-year repose meaningless if limitations always runs during construction Defendant: repose and discovery limitations serve different roles; repose still bars long-latency discoveries Court: Repose remains meaningful for injuries discovered long after completion; no redundancy shown

Key Cases Cited

  • Great River Energy v. Swedzinski, 860 N.W.2d 362 (Minn. 2015) (standard of statutory interpretation; review de novo)
  • Vlahos v. R & I Constr. of Bloomington, Inc., 676 N.W.2d 672 (Minn. 2004) (limitations on warranty claims — distinguished because this case is negligence)
  • Day Masonry v. Indep. Sch. Dist. 347, 781 N.W.2d 321 (Minn. 2010) (discovery of leakage and need for repair can start limitations period)
  • Seagate Tech., LLC v. Western Digital Corp., 854 N.W.2d 750 (Minn. 2014) (interpretive principle that differing language in same statute is intentional)
  • Pamida, Inc. v. Christenson Bldg. Corp., 285 F.3d 701 (8th Cir. 2002) (example where owners reasonably discovered construction defects years after substantial completion)
Read the full case

Case Details

Case Name: 328 Barry Avenue, LLC v. Nolan Properties Group, LLC
Court Name: Supreme Court of Minnesota
Date Published: Nov 25, 2015
Citation: 871 N.W.2d 745
Docket Number: No. A14-0724
Court Abbreviation: Minn.