This action arises from alleged defects in the construction of Willmar High School, which opened in 1994. In 2006, respondent Independent School District 347 (School District) commenced an arbitration proceeding against appellants, Lov-ering-Johnson Construction (Lovering-Johnson), Commercial Roofing, Inc. (Commercial Roofing), and GenFlex Roofing Systems, LLP (GenFlex), which were contractors or suppliers on the project. The School District asserted claims based on express written warranties and other non-warranty claims. Lovering-Johnson joined appellant Day Masonry to the arbitration proceeding because Day Masonry was the subcontractor that performed masonry work on behalf of Lovering-John-son. 1
The Contractors sought to have the arbitration proceeding dismissed, arguing that it was untimely. The district court agreed with the Contractors and dismissed the claims based on the statute of limitations. On appeal, the court of appeals affirmed as to the non-warranty claims, but reversed as to the warranty claims. Because we conclude that the statute of limitations bars the non-warranty claims but not the warranty claims, we affirm in part. But because we conclude that the Contractors were not required to file a notice of review in order to preserve their statute-of-repose defense for appeal, we remand the warranty claims to the court of appeals for consideration of the statute-of-repose defense.
In January 1993, the School District entered into construction contracts with Lov-ering-Johnson and Commercial Roofing for the construction of a new high school. Lovering-Johnson was the general contractor for masonry work, and Lovering-Johnson subcontracted the masonry work to Day Masonry. Commercial Roofing installed the roofing systems, including the waterproof membrane, and GenFlex manufactured the membrane for the roof. Gen-Flex provided two warranties to the School District, a Full Roofing System Warranty and a Limited Membrane Only Warranty. The Full Roofing System Warranty provides that during the period May 1, 1994, through May 1, 2004, GenFlex “will repair any leak” in the roofing system. -The Limited Membrane Only Warranty provides that during the period May 1, 2004 through May 1, 2014, the roofing membrane “will not deteriorate to the point of causing leaks through the membrane.” The School District’s contracts with both Lovering-Johnson and Commercial Roofing also contained express warranties that provide “that all Work will be of good quality, free from faults and defects and in conformance with the Contract Documents.”
The new Willmar High School was substantially complete by September 1, 1994. But almost as soon as the high school opened, the building began experiencing numerous leaks. Several custodians testified in their depositions as to the extent and ongoing nature of the leakage problems. According to deposition testimony, there were at least six specific areas in the building that experienced frequent leaks.
The record also shows the School District’s efforts to address the water problem at the high school. For example, in November 1996, the then head custodian at the high school wrote a letter to GenFlex informing the company of leaks in the roof. And, as detailed in two invoices from May
In 2004, the School District hired Waters Edge Architectural Group, Inc., to perform an assessment of the condition of the buildings in the district. In September 2004, on Waters Edge Architectural’s recommendation, the School District hired Inspec, an independent forensic engineering and testing firm, to do a thorough investigation of the causes of the roof leaks at the high school. Inspec issued two reports detailing the nature and cause of the roof leaks and recommending extensive repairs to the exterior walls and the perimeter of the roof. The recommended repairs totaled about two million dollars.
Following receipt of the first Inspec report, the School District sent letters, dated December 13, 2004, to both Lovering-Johnson and Commercial, enclosing a copy of the Inspec report and informing them of the potential warranty claims. On August 12, 2005, the School District sent notice to GenFlex of issues with the roof membrane and its intention to make a claim under the GenFlex warranties.
On March 13, 2006, the School District submitted a demand for arbitration pursuant to its contracts with Lovering-Johnson and Commercial Roofing and the warranties therein, and the GenFlex warranties. The contracts with Lovering-Johnson and Commercial Roofing incorporate the American Institute of Architects’ General Conditions of the Contract for Construction and contain an arbitration provision that provides that “[a]ll claims, disputes and other matters in question between the Contractor and the Owner arising out of or relating to the Contract Documents or the breach thereof ... shall be decided by arbitration.” The arbitration clause goes on to stipulate that “[t]he demand for arbitration ... in no event shall ... be made after the date when institution of legal or equitable proceedings based on such claim, dispute or other matter in question would be barred by the applicable statute of limitations.”
After Lovering-Johnson joined Day Masonry in the arbitration proceeding, Day Masonry filed an action in district court seeking to stay the arbitration. Day Masonry, joined by the other contractors, argued that Minn.Stat. § 541.051 (2006) barred all the School District’s claims— both the express warranty claims and the non-warranty claims — and moved for summary judgment on the grounds that these claims were time-barred. 2 The district court made extensive findings of fact and found the School District’s claims untimely under section 541.051, concluding that the statute of limitations had run on the School District’s claims. 3
The School District appealed, and the court of appeals affirmed in part and reversed in part.
Day Masonry v. Indep. Sch. Dist. 347,
The court of appeals did not consider the Contractors’ alternative argument that, if the warranty claims accrued in December 2004, the claims would still be time-barred under the statute of repose in section 541.051. Because the Contractors did not file a notice of review relating to the statute-of-repose defense, the court held that the Contractors waived their argument that the warranty claims were barred by the statute-of-repose.
Day Masonry,
The Contractors filed a petition for review on the accrual of warranty claims, and the School District filed a request for conditional cross-review on the accrual of non-warranty claims. We granted review on both issues.
I.
This case comes to us after the district court granted the Contractors’ motion for summary judgment. We apply a de novo standard of review to a grant of summary judgment.
Zip Sort, Inc. v. Comm’r of Revenue,
This case raises questions as to whether the statute of limitations or the statute of repose in Minn.Stat. § 541.051 bars the School District’s claims. The construction and application of a statute of limitations or repose, including the law governing the accrual of a cause of action, are questions of law that we also review de novo.
See State Farm Fire Cas. v. Aquila Inc.,
For non-warranty claims, section 541.051, subdivision 1(a), provides both a statute of limitations and a statute of repose. Actions must be commenced no later “than two years after discovery of the injury,” but such causes of action shall not “accrue more than ten years after substantial completion of the construction.” Section 541.051, subdivision 1(b), goes on to provide that “a cause of action accrues upon discovery of the injury.” 5 The parties agree that the two-year statute of limitations and the ten-year statute of repose in section 541.051 apply to the School District’s non-warranty claims.
For warranty claims, the applicable limitations period is contained in subdivision 4 of section 541.051, which provides that claims must be commenced “within two years of the discovery of the breach.” In 2004, the Minnesota Legislature amended subdivision 4 so that the ten-year statute of repose found in subdivision 1 of Minn. Stat. § 541.051 would also apply to breach-of-warranty claims. Act of May 15, 2004, ch. 196, § 1, 2004 Minn. Laws 356, 356-57. Until the 2004 amendments became effective on August 1, 2004, there was no statute of repose for breach-of-warranty claims. Minn.Stat. 541.051, subd. 4 (2002). 6
With this statutory framework in mind, we proceed to address the timeliness of the School District’s claims beginning with the warranty claims.
II.
The Contractors argue that the School District’s breach-of-warranty claims are untimely under both the two-year statute of limitations and the ten-year statute of repose in Minn.Stat. § 541.051 (2006). In order to decide whether the School District’s warranty claims are timely, we must first consider when those claims accrued. The parties agree, and we will assume for
A.
We held in
Vlahos v. R & I Construction of Bloomington, Inc.,
that the statute of limitations for a breach-of-warranty claim “begins to run when the homeowner discovers, or should have discovered, the builder’s refusal or inability to ensure the home is free from major constructions defects.”
The district court cited the standard from Vlahos and concluded that under that standard, the School District’s warranty claims accrued more than two years before the March 2006 arbitration demand. The court explained that, based on its finding that the School District had notice of defects in the building prior to September 1, 2002, “the School District had every opportunity to contact Gen-Flex, Commercial Roofing and Lovering-Johnson about the problem prior to September 1, 2004 (the ten year anniversary date of substantial completion of the school) and thus would have known whether they were intending on performing or breaching their respective warranties.” Because the School District did not take action to inform the Contractors of the leaks or make a demand that the Contractors fix the problems until after September 1, 2004, the district court found that the statute of limitations had already run on the School District’s warranty claims by the time it brought the arbitration action under the “should have known” prong of the Vlahos test.
The court of appeals concluded that the district court misapplied the
Vlahos
standard.
Day Masonry,
The difference between the district court and court of appeals’ application of the
Vlahos
standard relates to whether a claim for breach of warranty of future performance can accrue in the absence of notice to the warrantor that the warranty was at issue. In addressing the question of when a warrantee discovers or should have discovered the warrantor’s breach of express warranty, we have focused on the date the warrantor gives some affirmative indication that it will not or cannot- fulfill its obligations under the warranty.
See, e.g.', WatPro,
We need not decide in this case whether someone in the position of the School District must always give written notice to the warrantor that a warranty is at issue before a claim for breach of warranty of future performance could accrue. This is so because the Contractors point to no evidence showing that the School District had reason to know, before notifying the Contractors that the warranties were at issue in December 2004, that the Contractors were not going to perform under their warranties of future performance. 9
Based on the record before us in this case, the earliest the breach-of-warranty claims could have accrued under the Vla-hos standard would have been after the School District sent letters to Lovering-Johnson and Commercial Roofing on December 13, 2004, informing them of the School District’s potential warranty claims and forwarding the Inspec report. 10 We therefore hold that the earliest the warranty claims could have accrued was December 2004.
B.
We turn next to consider whether, as the district court held, the statute of limitations bars the School District’s warranty claims. Minnesota Statutes § 541.051, subd. 4, provides that claims must be brought within two years of discovery of the breach of warranty. But the School District’s breach-of-warranty claims accrued no earlier than December 2004, which is less than two years before the School District submitted its demand for arbitration in March 2006. We therefore hold that the statute of limitations does not bar the School District’s warranty claims.
C.
We turn next to the question of the statute of repose. The Contractors rely
The district court did not explicitly decide whether, as the Contractors argue, the statute of repose bars the School District’s express warranty claims because the court concluded that the claims accrued before the statute of repose in Minn.Stat. § 541.051 became effective. In other words, the district court concluded that the 2002 version of section 541.051 applied. Because there was no statute of repose in the 2002 version of the statute, the district court did not decide whether the statute of repose bars the warranty claims, but instead concluded that the claims were barred by the statute of limitations.
The court of appeals disagreed with the district court’s accrual analysis and held that the claims accrued in December 2004.
Day Masonry,
At the time of the appeal, Rule 106 stated that “[a] respondent may obtain review of a judgment or order entered in the same action which may adversely affect respondent by filing a notice of review with the clerk of the appellate courts.” By its terms, Rule 106 would apply if there were an adverse judgment or order on the statute-of-repose question. In this case, there is no such adverse order. In fact, the district court never reached the issue of the statute of repose, deciding the case instead on the alternative grounds of the statute of limitations.
At the district court, the Contractors presented the statute of repose and the statute of limitations as two independent, alternative bases for the district court to hold the School District’s breach-of-warranty claims time-barred. A review of the district court judgment and memorandum confirms that the district court never made any ruling on the statute-of-repose argument one way or another. The district court carefully analyzed the facts of the case and applied the analysis from the court of appeals’ decision in
Sletto v. Wes
Moreover, the district court’s determination that all the School District’s claims accrued prior to March 2004, rendering them completely barred by the statute of limitations, was not adverse to the Contractors in any meaningful way. Because the district court concluded that the claims accrued prior to March 2004, the claims were barred by the statute of limitations and thus the court had no need to reach the statute-of-repose issue.
We have not “imposed the requirement of a notice of review where the trial court has failed to rule on a question litigated and practical reasons continue to render such a notice unnecessary.”
Hoyt Inv. Co. v. Bloomington Commerce & Trade Ctr. Assocs.,
We note that
Penn Anthracite
was decided before we promulgated the Rules of Civil Appellate Procedure. But we have continued to rely on the principle articulated in
Penn Anthracite
even after Rule 106 became effective in 1968.
See Hunt by Hunt v. Sherman,
The School District seemingly contends that the result reached in
Penn Anthracite
is inconsistent with
Arndt v. American Family Insurance Co.,
In
Arndt,
the plaintiff, Jeffrey Arndt, was injured while helping a friend, Ronald Kieffer, with farm work.
Arndt
is not inconsistent with
Penn Anthracite,
and
Arndt
does not apply to the Contractors’ alternate statute-of-repose argument in this case. Under
Arndt,
even where the final judgment is entirely in respondents’ favor, respondents must still file a notice of review to challenge an order that the district court entered that was adverse to the respondents.
In sum, Rule 106 does not require a notice of review where a respondent advances on appeal an argument that was presented to, but was not ruled on by, the district court and is an alternative ground that supports affirmance of a judgment or order that was entered in respondents’ favor.
See Penn Anthracite,
205 Minn, at 520,
III.
In its request for conditional cross-review, the School District argues that the court of appeals erred in affirming summary judgment in favor of the Contractors on the grounds that the School District’s non-warranty claims are barred by the
But the question on appeal from entry of summary judgment is not whether the district court’s findings are clearly erroneous. The question is whether, when the evidence is construed in the light most-favorable to the School District, there is a genuine dispute that the School District had knowledge of its injury prior to March 2004.
See Kratzer v. Welsh Co., LLC,
The School District argues that it did not know of an actionable injury prior to March 2004 because it was not aware of the extent of the leakage problem at the high school until after that time. The School District’s argument is akin to the accrual argument we rejected in
Hyland Hill North Condominium Ass’n v. Hyland Hill Co.,
In
Hyland Hill,
the district court concluded that a condominium association was aware of its injury by October 6, 1987, based on the minutes of an association meeting in which the members discussed leaks in the party room and the garage.
The evidence, even when construed in the light most favorable to. the School District, establishes that this standard is met here. The two invoices from 2002, both of which refer to “leak(s),” demonstrate that the School District was not only aware of a leakage problem in 2002, but was also aware of the need to take action to repair the problem. The deposition testimony from the custodians, describing their experience with the water problem at the high school, further confirms that the School District had knowledge of the leakage problem more than two years before the March 2006 arbitration demand. See Minn.Stat. § 541.051, subd. 1.
The School District offers two arguments why this evidence is not sufficient to demonstrate its knowledge. The School District first argues that the 2002 invoices cannot be used to establish knowledge of its injury because the cost of the repairs reflected in these invoices was only $120. But under the standard we applied in
Hy-land Hill,
a party need not be aware of the extent of its injury for the statute of limitations to begin to run so long as the party is aware of the injury and the need for repairs.
The School District next argues that these invoices and the custodians’ testimony do not establish that the School District had knowledge of the water problem. Specifically, the School District contends that it was not on notice of its injury because the superintendent of the School District was not fully apprised of the leakage problem until she received Inspec’s report in 2004. But the custodians were the agents of the School District to the extent they were entrusted with the upkeep of- the school. Their knowledge of the leaks and the efforts they took to have the leaks repaired therefore is imputed to the School District.
See Sussel Co. v. First Fed. Sav. & Loan Ass’n of St. Paul,
In short, the evidence, when construed in the light most favorable to the School District, establishes that the School District was aware of its injury before March 2004. We therefore hold that the statute of limitations bars the School District’s non-warranty claims, which were not brought until March 2006.
Affirmed in part, reversed in part, and remanded.
Notes
. For ease of reference, we refer to Lovering-Johnson, Commercial Roofing, GenFlex and Day Masonry collectively as the “Contractors.”
. Minnesota Statutes § 541.051, subd. 1, provides that an action to recover damages for injury to property, other than an action for breach of warranty, must be commenced within two years of its accrual and that such a cause of action cannot "accrue more than ten years after substantial completion of the construction.” Minnesota Statutes § 541.051, subd. 4, provides the limitations period for breach-of-warranty claims.
. While the district court found that the School District's claims under the Full Roofing System Warranty were time-barred, it found the School District could proceed to arbitration on the Limited Membrane Only Warranty. The district court's conclusion with respect to the Limited Membrane Only Warranty was not challenged on appeal.
. We promulgated amendments to Rule 106 that became effective on January 1, 2010. Because these amendments do not apply to this case, we do not discuss them further and refer to the 2009 version of the rule throughout. The version of Minnesota Rule of Civil Appellate Procedure 106 applicable to this case provides:
A respondent may obtain review of a judgment or order entered in the same action which may adversely affect respondent by filing a notice of review with the clerk of the appellate courts. The notice of review shall specify the judgment or order to be reviewed, shall be served and filed within 15 days after service of the notice of appeal, and shall contain proof of service. A filing fee of $100 shall accompany the notice of review.
. In the 2004 and 2006 versions of the statute, this provision was in subdivision 1(b) of Minn.Stat § 541.051. But in the most recent version of Minn.Stat. § 541.051, this provision is found in subdivision 1(c). Id., subd. 1(c) (2008).
. The version of section 541.051, subdivision 4, in effect prior to the 2004 amendments provided that section 541.051 "shall not apply to actions based on breach of ... an express written warranty, provided such actions shall be brought within two years of the discovery of the breach.” Minn.Stat. § 541.051, subd. 4 (2002). In 2004, the Minnesota Legislature amended section 541.051, subdivision 4, to read in part: "For the purposes of actions based on breach of ... an express written warranty, such actions shall be brought within two years of the discovery of the breach.” Act of May 15, 2004, ch. 196, § 1, 2004 Minn. Laws 356, 356-57. By removing the "shall not apply” language of the earlier version of section 541.051, subdivision 4, that exempted warranty claims from application of the other provisions in the section, including the statute of repose in subdivision 1, the legislature effectively added the ten-year statute of repose to breach-of-warranty claims.
. In examining when a cause of action for breach of an express warranty accrues, courts have often looked to whether the claim is one for breach of warranty of future performance or one for breach of warranty to repair and replace.
See Donatelle Plastics Inc.
v.
Stonhard, Inc.,
No. 01-1429,
. Courts in other jurisdictions that apply a Vlahos-like test also tend to date the accrual of a breach-of-warranty claim to an affirmative communication in which the warrantor gives some indication of its inability or unwillingness to perform.
See, e.g., Hersh Cos. v. Highline Vill. Assocs.,
. The one exception is GenFlex’s reliance on a letter sent by the high school’s head custodian, on November 18, 1996, to GenFlex. Gen-Flex contends that this letter provides a basis to conclude that the School District had reason to know that GenFlex was going to breach its warranties many years before December 2004. Specifically, GenFlex argues that because the record does not reflect how it responded to the November 18 letter, it must have ignored the letter and from its failure to respond, the School District should have known, presumably in very late 1996, that GenFlex was going to breach its warranties. The School District argues that we should not consider GenFlex’s argument because the district court did not decide it. Because the district court did not make findings of fact sufficient for us to determine whether the 1996 letter gave the School District reason to know that GenFlex would breach its warranty of future performance, we decline to consider this argument.
See Rehberger v. Project Plumbing Co., 295
Minn. 577, 578,
For the same reason, we decline to consider GenFlex’s alternative argument that the warranty claims fail because the warranty expired before the School District demanded arbitration. GenFlex argues that it is entitled to dismissal of the School District's breach-of-warranty claims because the warranty was effective from May 1, 1994, through May 1, 2004, and thus expired before the School District brought its breach-of-warranty claims in March 2006. The School District counters
. We refrained from deciding the accrual question as a matter of law in
Vlahos,
concluding that factual disputes made summary judgment inappropriate.
. The School District argues that even if the Contractors preserved the statute-of-repose defense, the statute of repose does not apply because the statute of repose effectively rewrites the parties’ contracts. Specifically, the School District argues that the only time limitation relevant to its arbitration demand is the statute of limitations and that a statute of repose is not a statute of limitations. The School District also argues that the time limitation applicable to its arbitration demand must be the limitations period in effect when the contract was signed in 1993, not the limitations period in effect in 2006 when it filed its arbitration demand.
. In
Sletto,
the court of appeals held that the statute of repose of section 541.051 did not apply to bar the homeowners’ statutory warranty claim, which they brought more than ten years after the completion of construction, because their warranty claim accrued before August 1, 2004.
. The School District also relies on the court of appeals' decision in
City of Duluth v. Duluth Police Local,
. The findings that the School District challenged at the court of appeals were numbered 18, 22(a), 22(e), 32, 35, 37, 50, and 53. The School District generally argues that in these findings the district court mischaracterized documents or testimony in the record. Even assuming that the School District is correct as to all of these findings, there is still no genuine issue of fact as to the School District's knowledge of its injury. Findings 18 and 22(a) relate to GenFlex’s separate accrual arguments, and because we are not reaching these arguments, the dispute as to the facts set forth in these findings is not material to the question of the School District's knowledge of its injury. The' other findings relate to evidence of the water problem in the building. We do not, rely on the district court's characterization of the evidence referenced in these findings on review of summary judgment. We' examine the evidence in the record in the light most favorable to the School District to determine whether summary judgment was properly entered. As set forth below, we conclude that it was.
