delivered the opinion of the court.
This case was decided at the last term of this court, and is reported in
A petition for rehearing ivas filed near the close of the last term, calling our attention to the fact that the Supreme Court óf Nebraska had then recently decided that a grist-mill operated by water power was a work of internal improvement within the meaning of the before-mentioned statute. The judgment was suspended in .order that appellee might have an opportunity of presenting the full text of the opinion of the State court. That has been done at the present term. The case to which reference is made is Traver v. Merrick County, the opinion in which was not filed in the State court until after the close of our last term.
It is quite true, as claimed by counsel for appellee, that the • State court does, in that case, rule, that a water grist-mill is a work of internal improvement within the meaning of the statute in question. But the court takes care to say :
“ In onr view there is a clear distinction betweén aiding the development of the' water power of the State — a power that is continuing in its nature and may be used without cost'or expense, and must be used at certain points on a stream where a dam can be erected and power obtained — and a mill propelled by steam, that must be attended with' a continuous cost for fuel, and may at any time be moved to another locality.”
So far from the decision of the State court furnishing any ground for a rehearing, it is' an authority in support of that construction of the act of 1867 which excludes steam grist-mills from the class of internal improvements in aid of which counties, cities, and precincts of organized counties- are, by that statute, authorized to issue their bonds.
The rehearing is denied.