Opinion by
On January 25,1979, tbe Pennsylvania Public Utility Commission (PUC) issued an Order (Order No. 1) directing that tbe Community Central Energy Corporation (CCEC) refund to its customers $129,750.56 of excessive automatic fuel adjustment revenues. CCEC appealed Order No. 1 to tbis Court, alleging that tbe
Absent good reason being shown to the contrary, the commission shall, within 60 days following such hearing (on an automatic adjustment report), by order direct each such public utility to, over an appropriate 12-month period, refund to its patrons an amount equal to that by which its revenues received pursuant to such automatic adjustment clause exceeded the amount of such expense or class of expenses....
The issue in that appeal, described by this Court as “very limited, but important,”
The PUC responded to the remand by reviewing the record made at the previous hearings, and, without further hearings, argument, or briefing, issued an Order (Order No. 2) on September 8, 1980, which reinstated the provisions of Order No. 1. CCEC has appealed Order No. 2 to this Court, alleging that the context of its issuance constitutes reversible error, in that the actions of the PUC did not comport with the mandate of this Court regarding further proceedings. The
When passing on the validity of an order of the PUC, this Court must examine whether the appellant’s constitutional rights have been violated, whether the PUC committed an error of law, and/or whether the findings and conclusions contained in the order are supported by substantial evidence. United States Steel Corporation v. Pennsylvania Public Utility Commission, 37 Pa. Commonwealth Ct. 195, 390 A.2d 849 (1978). CCEC here contends that the PUC committed an error of law in determining that a mere review of the record constituted compliance with the order of this Court. Further, CCEC raises a due process claim, in alleging that it was denied its “day in court” by the failure of the PUC to hold a hearing at which evidence on the question of justification could be thoroughly presented. This Court finds merit in those arguments, and hereby orders the case remanded to the PUC for the express purpose of conducting a hearing on the issue of good reason for the overcollection of automatic fuel adjustment revenues.
The PUC contends before this Court that the due process rights of the utility, CCEC, were satisfied by its participation in the hearings prior to the issuance of PUC Order No. 1. We find no merit in that proposition, because the PUC was maintaining at that time that the scope of its discretionary power did not encompass an examination of good cause for an over-collection.
Okdek
And Now, this 20th day of November, 1981, the Order of the Pennsylvania Public Utility Commission, dated August 28, 1980, pertaining to Community Central Energy Corporation, M-FACS0005, is hereby vacated, and the matter is remanded to the Commission. The Commission is hereby ordered to conduct a hearing concerning the question of what, if any, justification the Community Central Energy Corporation had for the apparent overcollection of automatic fuel adjustment revenues during the twelve month period ending June 30,1978.
Section 307(e) of the Public Utility Law, Act of May 28, 1937, P.L. 1053, formerly 66 P.S. §1147 was repealed by the Act of July 1, 1978, P.L. 598. That section is now found at §1307 (e) of the Public Utility Code, 66 Pa. C. S. §1307.
Community Central Energy Corporation v. PUC, 51 Pa. Commonwealth Ct. 142, 413 A.2d 1197 (1980).