How the question now presented to us arose under the pleadings is not very clear. The agreement of the parties required that a surveyor agreeable to both parties should test the amount of yards excavated, and the amount of work done should be determined by his estimate. The certificate of the surveyor under that agreement would Ire conclusive upon the parties unless attacked for fraud. (Wyckoff v. Meyers, 44 N. Y. 143.) Plaintiff is bound to produce to defendant the certificate of estimate by the survejror agreed on, or satisfactory to defendant, before he would be entitled to recover (Barton v. Herman, 11 Abb. N. S. 378, and cases cited), and defendant is equally bound to pay upon that certificate. The parties having established the authority or tribunal to determine the amount of work done, and con
As the evidence of Mr. Smith, the surveyor, was admitted by the court to show the amount of work done, it is to be presumed that the testimony was material in some aspect of
The statute (L. 1851, c. 134, § 33) provided as follows: “ No surveyor shall give evidence in any cause depending in any of the courts of the State, or before arbitrators, respecting the survey or measurement of lands which he may have made, unless such surveyor shall make oath, if required, that the chain-or measure used by him was conformable to the standards which were the standards of the State at the time such survey was made.”
This provision is part of the act respecting weights and measures. The learned judge who presided at the trial correctly held that gis no “ survey ” was the subject of the proposed proof, and the question before the court had no reference to metes and bounds, the evidence was not as to “the survey or measurement of lands,” and the statute did not apply; that this was a mere mathematical calculation of the cubic contents of a certain rock excavation, and any person was competent to prove it, whether he were á surveyor or not.
It was not necessary to call a surveyor to prove the fact of the number of 3rards excavated. It was necessary to show a surveyor’s estimate under the agreement; but the parties had evidently got beyond that issue, and were trying the question as to the actual amount of excavating done, and the plaintiff was not bound to call a surveyor for that purpose. If any person capable of making a measurement and calculation could have been called, and his evidence would be proper, although he had no compared standard to go b3r in his measurement, there could be no objection to such witness, because he was a surveyor and had measured by a tape line which had not been verified by the standards.
The judgment and order denying motion for new trial should be affirmed, with costs.
Charles P. Daly, Ch. J., and Van Hoesen, J., concurred
The judgment here was affirmed by the Court of Appeals, April 8th, 1879.