Appeal by the State from a judgment of the Court of Claims in the amount of $13,102.77 for damages for breach of a contract between the claimant and the State of New York. After the appeal was heard, a reargument upon the question of damage was had pursuant to our direction. (4 A D 2d 981.) On October 10, 1951, the claimant and the State entered into a contract for the improvement of the grounds at the Potsdam State Teachers College. The work consisted of excavation, a small amount of sewer work, grading and seeding, the placing of sidewalks and roadways and the planting of shrubbery. The contract provided for completion of the work within 120 days from the date of execution, which would be February 7, 1952. However, the specifications provided that grass seed was to be sown from March 15 to May 1, or from August 15 to October 1 and that the shrubs were to be planted in good planting weather between September 1 and May 15. The contract provided that the State reserved the right to let other contracts in connection with the work and required the contractor to co-ordinate his work with that of other contractors. It further provided that, if the contractor was delayed in his work by any act or neglect of the State, the “time of completion shall be extended” but that “No charges or claim for damages shall be made by the Contractor for any delays
