Order, Supreme Court, New York County (Herman Cahn, J.), entered on or about August 5, 2004, which granted defendant’s motion to dismiss the complaint only to the extent of dismissing, without prejudice, plaintiffs claims related to extra work and the unpaid contract price, and denied plaintiffs cross motion for summary judgment, unanimously affirmed, without costs.
Pursuant to the Form of Proposal for “Single-Part Base Bid Contracts with Alternates & Unit Prices Listed,” each bidder was required to submit a base bid for “all labor, materials, tools, supplies and insurance.” Under section X (A) of the contract specifications, “Base bid shall include all costs for dewatering of the excavation including the cost of equipment, mobilizing and demobilizing costs, fencing and permits.” It is this provision on which defendant primarily relies. As indicated, plaintiffs base bid was $697,000.
However, pursuant to the Form of Proposal, each bidder was also required to submit unit prices for a list of 24 items, including “Dewatering of clean or contaminated ground water. And associated work in accordance with sub-section X. Price shall include oil/water separation if required.” Section X (B) of the contract specifications states: “Include in the Unit Price the cost of providing and installing a temporary oil/water separator, a well point system, pumps, piping, wiring, etc. as indicated in contract drawings, to treat groundwater should it be contaminated with fuel oil . . . Should an oil/water separator not be required, provide credit as per the price specified in the Form of Proposal to the Construction Manager.” Plaintiffs quoted unit price for the dewatering was $4.50 per gallon, and plaintiff alleges that it removed and excavated 1,418,300 gallons.
Defendant argues that, contrary to the motion court’s finding, requiring unit prices for dewatering is not irreconcilable with requiring that the base bid include all costs for dewatering, because the contract does not provide that the unit price for dewatering will actually be paid. Rather, defendant explains, including unit prices in a base bid contract such as this provides a method for calculating additions or deletions to the contract,
Defendant asserts that it had no occasion to consider the unit price quoted by plaintiff for dewatering, because the contract did not specify any quantity of water to be extracted. It required plaintiff to “dewater tank area ... as necessary to control petroleum contaminated groundwater for specifications.” Certainly, defendant argues, there is nothing in the record to suggest that defendant ever determined that it would be in its best interests “to inflate a $600,000 contract to a $6 million contract based upon the unit price quoted in the Form of Proposal.”
Conversely, plaintiff argues that it defies logic that defendant, unless required by the contract, would ever choose to pay more for dewatering, based on unit pricing, than it was obligated to pay under the base bid. Indeed, defendant’s explanation, while supported by the unambiguous language quoted above from the list of unit prices and the Supplementary Terms and Conditions, would seem to render the provisions concerning unit prices meaningless (see American Express Bank v Uniroyal, Inc., 164 AD2d 275, 277 [1990], lv denied 77 NY2d 807 [1991]).
Thus, we find that neither party has established its entitlement to summary judgment on the issue of plaintiffs compensation for its dewatering operation. Concur—Mazzarelli, J.P., Marlow, Ellerin, Gonzalez and Catterson, JJ.
