The defendant is the owner of a tract of land which it describes as Rosedale Terrace. It has mapped the tract and divided it into streets, and is selling the lots to seekers after suburban homes. By a contract made in October, 1906, the plaintiff agreed to buy eight lots for $3,955. He was to pay $300 at once, and the residue in installments of $20 a month. He was also to pay interest on the unpaid balances, and taxes and assessments. It would take fifteen years to complete the payments. The plaintiff was not given any right of possession in the interval. When full payment had been made, but not before, he was to receive a warranty deed. The defendant also agreed "to grade all streets and plant shade trees thereon, and put down cement sidewalks."
The plaintiff made his payments every month until June, 1911. He then stopped them without warning. A year later he began this action to recover what he had paid, and to impress a lien upon the land. He says that there has been undue delay in grading the streets, in planting the shade trees and in laying the cement sidewalks. For this delay he says that he is entitled to rescind the contract. The tract comprises about 115 acres. Seventy-five blocks of cement sidewalk, or 27,000 feet, have already been laid; sixty-four blocks, or less than half, have yet to be laid. In some blocks there is a cement sidewalk on one side only. In the plaintiff's block there is a cement sidewalk on both sides. The streets have been graded to some extent, though imperfectly and *Page 249 roughly. Many shade trees have been planted. Many lots have been improved with dwellings. All this work was done without any protest by the plaintiff that it was going forward too slowly. He made no complaint when he stopped his payments. He made none, even after stopping payment, till this action was begun. About that time he seems to have insisted that a sidewalk must be laid in front of his lot; and this was promptly done. There is no evidence that at any time he asked for anything else. It is true there is an admission in the pleadings that a letter of demand was sent to the defendant, but there is no statement of the date of the demand or even of its nature. The defendant's performance had been something more than colorable, even though it may have been deficient. Going forward with the work at a rate of progress which had evoked no protest, it was suddenly informed by the plaintiff that the contract was at an end.
We think this summary rescission of the contract was beyond the plaintiff's power. We may assume that the defendant was bound to complete the improvements within a reasonable time, and that the rate of progress was too slow. That is not enough to justify the plaintiff's conduct. Where a contract involving successive or continued acts is to be performed in a reasonable time, delay, though it will give rise to a cause of action for damages, will not always permit rescission. The conduct of the parties, while the delay continues, may be such as to indicate a purpose to keep the contract alive; and such a purpose, once manifested, may not be suddenly abandoned (McTague v. Sea Isle City Lot Bldg.Assn.,
The judgment of the Appellate Division should be reversed, and that of the Special Term affirmed, with costs in the Appellate Division and in this court.
WILLARD BARTLETT, Ch. J., HISCOCK, COLLIN, HOGAN, SEABURY and POUND, JJ., concur.
Judgment accordingly. *Page 251
