On May 26, 1998, the plaintiff filed a motion for summary judgment arguing that it had complied with the notice requirements of General Statutes §
"General Statutes (Rev. to 1983) §§
General Statutes §
General Statutes §
The plaintiff has failed to supply evidence to the court indicating whether it was to be paid as a subcontractor who CT Page 9544 furnished labor or materials included in a requisition submitted by the contractor or as a subcontractor performing work not included on a requisition or estimate. Pursuant to §
Even assuming the plaintiff was to be paid as a subcontractor furnishing labor or materials included in a requisition submitted by the contractor, the computation of the one year limitation period in §
NADEAU, JUDGE