The defendant denied the material allegations of the complaint and asserted three special defenses based on the plaintiff's alleged violations of the Connecticut State Building Code. The defendant also asserted a fourth special defense alleging that the plaintiff had waived any right to further money because it signed a release at the time of the last payment it received.
The case was referred to Attorney Kenneth B. Povodator, an attorney trial referee, in accordance with General Statutes §
The attorney referee concluded, on the basis of the above findings of fact, that: (1) the defendant had breached its contract with the plaintiff by failing to pay for change order #45; (2) judgment should enter in favor of the plaintiff for the face amount of change order #45, $51,661,1 plus interest at 18% per year as set forth in change order #45, which amounts to $18,597 as of November 22, 1997, plus per diem interest of $25.83 to the date of judgment.2
The defendant, pursuant to Practice Book §
In response to the motion to correct filed by the defendant, the attorney referee declined to change his recommendation that judgment enter on the complaint for the plaintiff in the amount of $51,661, plus interest. The referee did, however, comment on each item of the defendant's motion to correct and his responses can be summarized as follows: (1) the referee agreed that the contract of November 9, 1993 that was admitted in evidence, was CT Page 8458 an "abridged" contract in the sense that it did not contain, for example, the specifications and drawings, but that this was immaterial to the resolution of this case, which involved change order #45, (2) the signatures on the change order, which were challenged by the defendant, had been authenticated by the plaintiff, and that the person who signed change order #45, Ramon Larracuente, the executive director of the defendant, had signed other change orders on behalf of the defendant, all of which had been paid by the defendant; (3) the referee reiterated that the defendant's architect and representative had both signed off on change order #45: (4) the plaintiff had proved its case, and the defendant had not proved its special defenses; (5) the plaintiff's right to obtain 18% interest, including damages for delay, was contained in the change order itself; (6) the contract and change order refer to the defendant being entitled to liquidated damages in the event completion of the contract was due to the plaintiff's delay; (7) the plaintiff did not make a claim for liquidated damages; and (8) the claim for delay damages was reasonable based on testimony from the plaintiff and the approval of such damages in a delay in paying a previous change order.
In accordance with Practice Book §
This court's scope of review of an attorney referee's report was reiterated by the Supreme Court in Elgar v. Elgar,
Thus, according to Elgar v. Elgar, supra,
Regarding the first task of determining whether there is support in the record for the factual findings of the referee, the transcript indicates that the witness for the plaintiff, its president, testified that: (1) his company had performed the work required by change order #45 but the defendant had not paid for this work; (2) he recognized the signature of Larracuente because he had signed most of the previous 44 contract change orders; and (3) Larracuente had acknowledged that the sums of money due for that last change order "were due."
The defendant did not file objections to the referee's report as authorized by Practice Book §
Since the referee's findings of fact are supported by the record, such findings must stand uncorrected. It was also noted that the defendant did not present any evidence in its own behalf.
The only remaining issue concerns whether the referee's conclusions follow legally and logically from the underlying facts. This determination is required because a reviewing court is obliged to consider whether "the conclusions reached were in CT Page 8460 accordance with the applicable law." Thermoglaze, Inc. v.Morningside Gardens, Co.,
The referee determined that: (1) the plaintiff had proved that it had completed change order #45; (2) the defendant did not prove its special defenses regarding the State Building Code or the execution of a release; and (3) the payment of interest was agreed upon by the parties in a duly executed change order signed by an authorized representative of the defendant and the defendant's architect. The referee's ultimate conclusion that the plaintiff should collect on change order #45 follows legally and logically from these underlying facts. Romano v. Derby, supra,
Based on the standard of review outlined in Elgar v. Elgar, supra,
Accordingly, as to the plaintiff's complaint, judgment is entered in favor of the plaintiff to recover from the defendant the sum of $51,661, plus interest in the amount of $24,563.73 to the date of judgment, for a total recovery of $76,224.73. Costs shall be taxed by the office of the chief clerk in accordance with General Statutes §
So Ordered.
Dated at Stamford, Connecticut, this 13th day of July, 1998.
William B. Lewis, Judge
