The facts are as follows: On March 11, 1994 the State Department of Public Works (hereinafter DPW) awarded to ECAP Construction Company (hereinafter ECAP) the prime contract to do specified concrete work on the University of Connecticut School of Law library in Hartford. After the work was completed in April 1996, ECAP notified DPW of its claim for additional monies due it because of delays in work caused by DPW and its general contractor, changes in work orders and schedules, and an unpaid balance of the contract price. The parties initiated informal discussions to settle the claims. A December 1995 meeting proved fruitless, but in a January 1996 meeting, at which were present P. J. Delahanty, deputy commissioner of DPW, Richard Piotrowski, bureau chief of facilities design and construction and others for the State, and Lawrence Pace, president of ECAP, and Stephen Coutras, ECAP's project manager, the sum of $425,000 was mentioned as a settlement amount.
The testimony of the participants to that discussion differ. Pace testified Piotrowski made a firm and final settlement offer CT Page 8348 of $425,000. Pace asked Piotrowski when payment would be made and Piotrowski said within eight weeks. Pace said he would have to discuss the offer with his brother, a principal of ECAP and he would get back to Piotrowski. The following Monday Pace called Piotrowski and accepted the offer. His testimony is corroborated by Coutras.
Piotrowski testified he made a tentative offer of $425,000, but it was subject to the approval of the commissioner of DPW and of the Attorney General's office, as required by C.G.S. §
ECAP then proceeded, pursuant to §
The State stipulated at the start of the trial that this demand for arbitration conformed to all the requirements of §
In October, 1997 ECAP submitted an amended demand for arbitration, identifying an additional issue in dispute as "failure to pay settlement, as agreed." More specifically its amended demand stated, "DPW offered ECAP $425,000 as full payment of ECAP's claim. ECAP accepted the offer. DPW refused to pay ECAP as agreed. Said refusal to pay ECAP as agreed was a breach of agreement to settle ECAP's claim and accord without satisfaction."
ECAP further claimed DPW acted in bad faith and with reckless indifference and wanton and intentional violation of ECAP's rights, for which it seeks punitive damages and attorney's fees.
It is as to this additional demand that the State seeks an CT Page 8349 injunction prohibiting arbitration of it.
The court is guided by the policy favoring arbitration and "only unusual circumstances justify judicial action to present arbitration from proceeding. . . ." McCoskey Co. v. AmericanArbitration Association,
However, a countervailing principle is that the doctrine of sovereign immunity precludes the State being sued without its consent. The apposite statute authorizing a person in the position of ECAP to bring an action against the State is C.G.S. §
Section
Any person, firm or corporation which has entered into a contract with the State, acting through any of its departments, commissions or other agencies, for the . . . construction . . . of any . . . building . . . of the State may, in the event of any disputed claims under such contract . . . bring an action against the State to the judicial district of Hartford for the purpose of having such claims determined, provided notice of such claim under such contract and the factual basis for such claim made have been given in writing to the agency head of the department administering the contract . . .
Section
It is well recognized in our law that statutes, such as §
1. The State argues that the evidence in the cases establishes that no agreement to settle was ever reached between the State and ECAP and therefor there was no contract on the basis of which to evoke §
Section
ECAP asserts an agreement to settle its claims and it is disputed by the State. That is the disputed claim submitted to arbitration. The issue of whether or not such an agreement was reached and whether it has been breached is one not to be decided by this court but to be decided through arbitration.
2. The State argues that the agreement to settle is not a contract for the construction of a building and so does not come within the provisions of §
3. The State argues if the purported agreement to settle is a disputed claim, it is not one "under" the construction contract. But if the State concedes that all of ECAP's construction claims for damage, amounting to $1,870,169, are arbitratable under the statute, how can it seriously assert that an agreement to settle those claims, or any of them, is not similarly arbitratable. The State tries to make a distinction between "under" the construction contract and "related to", "derived from" or "based upon" the contract. That is semantic sophistry. Section
4. The State argues that ECAP's arbitration demand, to the extent that it claim's the State's bad faith and wanton and intentional violation of ECAP's rights, is a tort claim not authorized by §
Morever, when the statute permits arbitration in such broad language, the issue of what disputes are arbitratable should be left to the arbitration panel. Turner Construction Co. v.Eppoliti, Inc.,
5. Finally the State argues ECAP has failed to allege in its demand for arbitration the factual basis for its claims of breach of settlement agreement, that notice was given to the agency head and given within two years of completion of the work, as required by §
Since the State has failed to prove a violation of §
Thus, this court concludes the State has tailed to establish its right to an injunction in this case, and judgement may accordingly enter for the defendents.
SATTER, J.T.R.
