The defendant admitted that the plaintiff shipped the brass coils to this country, but denied that any money was due to the plaintiff. The defendant also asserted four special defenses. The first defense asserts that the plaintiff negligently, and in breach of its contract with the defendant, mishandled the loading of defendant's 200 metric tons of brass coils in such a fashion as to damage these coils. It is further alleged that this damage necessitated repairs to the coils and additional shipping costs. In the second its contract with the defendant, mishandled the loading of defendant's 200 metric tons of brass coils in such a fashion as to damage these coils. It is further alleged that this damage necessitated repairs to the coils and additional shipping costs. In the second special defense, the defendant alleges that its contract required the plaintiff to load and ship defendant's brass coils so that they could be unloaded from a cargo ship by a CT Page 1472 forklift, but that this became impossible and that the defendant spent approximately $43,450 to offload the coils. In the third special defense, the defendant contends that this dispute should be resolved through arbitration pursuant to the "Dutch Forwarding Conditions." In the fourth special defense, the defendant argues that the claim by the plaintiff is "time-barred" by the Dutch Forwarding Conditions.
The defendant also filed a counterclaim with three counts. In the first count, the defendant alleges that the plaintiff breached the express contract with the defendant because the coils could not be offloaded by forklift as agreed but rather required an extra $43,453 to unload. In the second count of its counterclaim, the defendant contends that the plaintiff breached an implied contract that the coils could be offloaded with a forklift, which proved impossible and resulted in an additional cost of $43,453 to offload these items. The third count claims that the plaintiff's breach of an express and implied contract also constitutes negligence.
The plaintiff filed two special defenses to the counterclaim. These defenses allege that it is not responsible to the defendant for any alleged damages, and that the counterclaim by the defendant is time-barred by virtue of the Dutch Forwarding Conditions "which govern the transaction."
The case was referred to Attorney Frank W. LiVolsi, Jr., an attorney trial referee, in accordance with General Statutes §
The attorney trial referee concluded, on the basis of the above findings of fact, that: (1) the defendant incurred extra costs to unload the brass coils; (2) the Dutch Forwarding Conditions did not apply to this transaction as the plaintiff submitted itself to the jurisdiction of this court by bringing suit against the defendant in this court; (3) judgment should enter in favor of the plaintiff for $16,795, the amount of the contract with the defendant; (4) judgment should enter in favor of the defendant on its counterclaim in the amount of $36,190.45; and (5) the judgments should not include interest or attorney's fees.
As authorized by Practice Book §
In response to the motion to correct filed by the defendant, the attorney trial referee declined to change his recommendations. The referee did, however, comment on each item of the defendant's motion to correct and his responses can be summarized as follows: (1) the referee agreed that the defendant had been damaged by improper loading of the scrap brass coils by the plaintiff, and no further clarification on this point was needed; (2) the referee agreed that the improper loading had caused some delay in shipping the goods to the consignee; and (3) the referee could not recommend an award for carrying costs as the defendant's witness on this subject was unable to specify any such loss with a reasonable degree of probability.
In accordance with Practice Book
This court's scope of review of an attorney trial referee's report was reiterated by the Supreme Court in Elgar v. Elgar,
Thus, according to Elgar v. Elgar, supra,
With respect to determining whether there is support in the record for the factual findings of the referee, the plaintiff did not file a motion to correct or exceptions. Thus, the plaintiff, in effect, is agreeing that the material facts in the referee's report were based on sufficient evidence. The defendant's exception relates solely to the recommendation by the referee that judgment enter in favor of both parties, and did not include a reference to carrying costs of $5,826. CT Page 1475
Neither the plaintiff nor the defendant filed objections to the referee's report as authorized by Practice Book §
Since the referee's findings of fact must remain uncorrected, the only remaining issue concerns whether the referee's conclusions follow legally and logically from the underlying facts. This determination is required because a reviewing court is obliged to consider whether "the conclusions reached were in accordance with the applicable law." Thermoglaze. Inc. v.Morningside Gardens, Co.,
The referee determined that the plaintiff was entitled to recover the shipping charges in its contract but that the defendant had been damaged by the plaintiff's improper loading of the scrap brass coils. The referee's ultimate conclusions that both parties should recover on the complaint and on the counterclaim follow legally and logically from these underlying facts. Romano v. Derby,
Based on the standard of review outlined in Elgar v. Elgar, supra,
So Ordered.
Dated at Stamford, Connecticut, this 8th day of February, 1999.
___________________________ William B. Lewis, Judge
