Reporter of Judicial Decisions
The dispositive issue in the present case grows out of the proper interpretation of the terms of §
The facts necessary for a resolution of these issues will be set forth as each issue is discussed.
The letters in question each contain a legend at the bottom which indicates that copies were sent to ten different parties, including the contractor. The plaintiff, however, produced return receipts for certified mailing (green cards) for only four of the ten to whom copies were mailed, not including the contractor. Nevertheless, Jorge Barreira, the plaintiff's principal, testified that he had received signed return receipts from the contractor but mislaid them and has been unable to locate them. The court credits Barreira's testimony not only because it finds it credible, but also because of four additional reasons. First, he produced the other return receipts, which correspond with the names of the persons shown on the "cc" legend on the letter. Second, the contractor's name was listed on the top of the list of ten. Third, he produced each of the two *Page 102 return receipts from one of the ten, Fletcher Thompson Architects. Fourth, and finally, each of the receipts was dated either March 13 or 14, 1997.
Federal precedents make compliance with the statutory notice requirement of §
Section
Once again, relying on federal precedent construing the federal Miller Act, our Supreme Court has adopted a "substantial performance rather than [a] strict compliance [test] when construing statutory notice requirements dealing with the service of notice and with the *Page 104
contents of notice." Okee Industries, Inc. v. National Grain Mutual Ins.Co., supra,
The next issue is whether the failure of the surety to act upon the plaintiffs notice of claim within the prescribed ninety period is mandatory or directory. The court begins by noting that there is no corresponding provision in the federal Miller Act and so, there is no federal case law to draw upon as an aid in construing the provision. Neither is there any Connecticut precedent to guide the court. Thus, analysis of the provision must be undertaken on the basis of well established principles of statutory construction.
"The process of statutory interpretation involves a reasoned search for the intention of the legislature. . . . In other words, we seek to determine, in a reasoned manner, the meaning of the statutory language as applied to the facts of [the] case, including the question of whether the language actually does apply. In seeking to determine that meaning, we look to the words of the statute itself, to the legislative history and circumstances surrounding its enactment, to the legislative policy it was designed to implement, and to its relationship to existing legislation and common law principles governing the same general subject matter." (Citation omitted; internal quotation marks omitted.) Willoughby v. NewHaven,
In the present case, the plaintiff argues that the word "shall" in the statute governing the time limit set for the surety to make payment or deny a subcontractor's claim is mandatory. The plaintiff further argues that the surety's failure either to pay or deny either claim within that ninety day period gives the plaintiff an automatic right to the amount claimed, whether disputed or undisputed. In response, the surety argues that the legislature did not intend such a draconian result and, therefore, the word "shall" should be interpreted as directory rather than mandatory.
The legislative history reveals that when the statute was amended in 1987, the legislature added, inter alia, a section that allows either party to recover attorney's fees if the court, in its discretion, finds that "either the original claim, the surety's denial of liability, or the defense interposed to the claim is without substantial basis in law or fact." Public Acts 1987, No.
"In order to determine whether a statute's provisions are mandatory [the court] has traditionally looked beyond the use of the word shall and examined the statute's essential purpose. . . . The test to be applied in determining whether a statute is mandatory or directory is whether the prescribed mode of action is the essence of the thing to be accomplished, or in other words, whether it relates to a matter of substance or matter of convenience. . . . If it is a matter of substance, the statutory provision is mandatory. If, however, the legislative provision is designed to secure order, system and dispatch in the proceedings, it is generally held to be directory, especially where the requirement is stated in affirmative terms unaccompanied by negative words. . . . Furthermore, if there is no language that expressly invalidates any action taken after noncompliance with the statutory provisions, the statute should be construed as directory." (Citations omitted; internal quotation marks omitted.) United Illuminating Co. v. New Haven,
The legislative history reveals that, in 1987, the legislature further amended the statute by adding the provision requiring the surety either to pay or deny within ninety days. According to Representative Martin M. Looney, the new procedure "addresses the problem of collecting under a payment bond. . . . This bill authorizes the subcontractor or a sub-sub contractor who has not been paid within 90 days to collect directly from the company that provided the Contractor's payment bond, going to court only if the bond company fails to satisfy *Page 107 his claim." 30 H.R. Proc, supra, pp. 7069-70. Further, Senator James H. Maloney commented that "[t]he amendment revises the procedures for claims under materialmen's bonds. What it does . . . in effect [is] require that non-disputed claims be paid, and only the contested portion of the claim would go to litigation. This will simplify the . . . well, first of all, eliminate a number of cases that otherwise might be brought. And will generally improve the orderliness of the materialmen's bonds procedure." 30 S. Proc, Pt. 4, 1987 Sess., p. 1468. The amendment did not provide, nor does the statute in its present configuration provide, an explicit consequence for a surety's failure to admit or deny a claim within the ninety day period. As stated previously, according to principles of statutory construction, if a requirement is stated in affirmative terms, unaccompanied by negative words, and has no words expressly invalidating any action taken after noncompliance, the requirement is usually interpreted as being directory.
On the other hand, "`[t]he use of the word "shall" in conjunction with the word "may" [in other sentences of the same statutory section] confirms that the legislature "acted with complete awareness of their different meanings" . . . and that it intended the terms to have different meanings.'" (Citation omitted.) Office of Consumer Counsel v.Dept. of Public Utility Control,
In Zoning Board of Appeals v. Freedom of Information Commission,
Similarly, this court finds that the history of both the federal and the Connecticut Miller Acts makes it clear that the abiding purpose of the legislation is to facilitate the speedy disposition of subcontractor claims when engaged in municipal construction projects. *Page 109
Further support for the argument that the ninety day limit is mandatory is found in the decisions in which our courts have ruled that the amendment containing this provision should not be applied retroactively. See Blakeslee Arpaia Chapman, Inc. v. EI Constructors Co., supra,
The general rule regarding retroactivity is found in General Statutes §
Connecticut courts have refused to apply amendments to §
In a slight variation of the issues, other decisions of this court have found that a surety's failure to respond to a claim within ninety days can be the basis for a claimant's cause of action for a violation of the Connecticut Unfair Trade Practices Act, General Statutes §
Having held the ninety day pay or deny provision to be mandatory and not directory, the court must now determine whether the surety's failure to adhere to the requirement results in automatic approval of payment to the plaintiff.
The result that has uniformly emanated from our case law when a mandatory statutory time limit has been violated in the context of administrative law, has been to invalidate the action of the particular agency that *Page 111
committed the violation. Hartford Principals' Supervisors' Assn. v.Shedd, supra,
Except for the defense of the statute of limitations, the court's disposition of the plaintiff's claims has preclusive effect on the defendant surety's special defenses and counterclaim and obviates the need for any further adjudication, save for the plaintiff's request for attorney's fees and the statutory mandate for interest under §
Attorney's fees are awardable under the statute only if the denial of liability or the defenses interposed were "without substantial basis in fact or law." In view of the novelty of the issues involved and the good faith nature of the defenses, the court cannot say that the plaintiff has met the statutory threshold of "without substantial basis." The request for attorney's fees, therefore, is denied. *Page 112
Section
Interest is calculated in this manner:
$14,467.54 — North Street contract
$ 5,761.99 — Old Greenwich contract
$20,229.53 x .10 + 365 = $5,619 per day = $2,022.95 per year
From March 17, 1997 to March 17, 2000 — $2,022.95 x 3 = $6,068.85
From March 17, 2000 to December 1, 2000 — 259 days x $5,619 =
$1,455.32
+$6,068.45
=$7,524.17 Total Interest
+$20,229.53 Total Principal
=$27,753.70 Total Judgment
Interest of $5,619 per day is to be awarded until the date of payment.
