The defendant appeals from a judgment rendered in favor of the plaintiff in an action brought to recover the agreed purchase price of $2,396 for twelve galvanized iron tanks, each of the capacity of 8,189 gallons.
The contract was evidenced by certain letters passing between the parties. Of such letters those which are considered of material consequence in determining this controversy specified that the tanks be guaranteed against leaks before leaving plaintiff's factory, and that the tanks be placed on platforms not exceeding twelve inches in height. The construction of the tanks was commenced at the plaintiff's factory, but was completed on the property of the defendant. The platforms on which the tanks were to rest were furnished and constructed by the defendant, and while used for the purpose for which they were intended, the trial court found that they were not "accepted by the plaintiff," and "that the plaintiff assumed no obligations in regard to the foundations furnished by the defendant." The court further found: "That said tanks did comply with plaintiff's written guarantee and did comply with the express warranty found in Civil Code section
If it be determined with reference to the tanks which leaked that all the warranties, express as well as implied, were fulfilled by the plaintiff, or that such tanks leaked because of the fault of the defendant, the plaintiff was entitled to judgment; on the other hand, if the leaks were caused by the fault of the plaintiff, the judgment should be reversed. That part of the contract which provided that the tanks should be guaranteed against leaks before leaving the factory of theplaintiff, was modified by implied consent of the parties in that the tanks were only partially constructed at the factory of the plaintiff and the tanks were completed at the plant of the defendant. It must therefore have been within the contemplation of the parties as a part of such modification that, whether constructed at the plaintiff's factory or at the defendant's plant (without reference to the foundation on which the tanks rested), the tanks would be free from leaks on their completion. The warranty contained in section
With reference to the effect upon the tanks produced by the manner of construction of the platforms and their surroundings, the same witness stated: "The tanks were leaking *Page 462 because the seams had cracked in one or two places causing leaks. . . . I concluded these cracks were caused by the settling of the foundation. I found some planks had settled more than others and that the planks were not even on a level. In some places planks had settled so much that they no longer touched or supported the tank. I found a leak at one such place where one plank was high and the planks on either side had settled so they were three-fourths of an inch below the bottom of the tank. Such an unevenness of the foundation would cause the bottom of the tank to bulge and put an unnecessary strain on the seams. This would tend to crack open the solder and cause a leak. A full tank of oil would weigh approximately 56,000 pounds; that would make a weight of about 580 pounds per square foot all over the surface of the bottom of the tank. That weight would be sufficient to draw and open the seams at the bottom of the tank if it was resting upon an uneven surface. I called the attention of defendant's men to the fact that the foundation was not level, in several instances, when they were laying the planks; then, later, when I went down to the plant to repair leaks I called to Mr. Peacock's attention the fact that the foundation was not level in places. He said he would fix it, but he did not do so. . . . If the foundations of the tanks were not level that would cause strains on the sides of the tanks. That strain might appear anywhere on the body of the tanks and it would cause the tank to draw at the joints. . . . Where I put the stove bolts in the bottom, the tanks were leaking where the solder had cracked on the seam. I believe it was the strain caused by the unevenness of the foundation that made the solder crack." Another witness stated: "I suggested that to remedy the faulty foundation the planks should be brought up together, that the ends be matched up, not left staggered, and that they be braced underneath. The foundation consisted of loose planks laid on the ground. These planks were not of uniform thickness and the ends of the planks were so arranged that some joints were beneath the tank. In some places the ground had settled so that the tanks were not resting on the planks as they should have been. The bottoms of the tanks were in places suspended between the planks." A third witness testified that: "The foundations were not even, that is, the surface of the planks was not even. Some of the planks had settled away from the bottom *Page 463 of the tank. I should say that in one place there was approximately three-fourths of an inch between the plank and the tank. . . . From what I have observed I can tell the effect on galvanized tanks of the character of those I saw in this case. If they were filled with oil and the foundations on which they were setting was unlevel I know the unlevelness at the joints would cause a drawing and stretching of the metal which would pull a seam apart on a joint where it was soldered."
The contract, as far as the warranty against leaks was concerned, originally contemplated that the tanks would not leak before leaving the factory. Consequently any question of the tanks being placed either on the bare ground, or on a plank foundation, or on a cement foundation, was not considered by the parties as having anything to do with the subject of whether on their completion the tanks would leak or not. If immediately upon completion of their manufacture, and assuming that they might have been tested while resting temporarily on the bare ground or elsewhere, it had been found that the tanks were free from leaks, they would have met the condition of the contract that they were guaranteed against leaks before leaving the factory. Where or in what position the tanks were ordered to be placed by the defendant (other than that plaintiff should not be compelled to install them on foundations over twelve inches in height) was of no concern of the plaintiff and had nothing to do with the requirement that they be free from leaks on the completion of their manufacture. The location of the tanks and the conditions which were to surround them rested entirely within the control of the defendant. As the findings of the lower court show were the actual conditions, "the foundation upon which said tanks were placed, and which foundation was furnished by the defendant corporation, was not substantial and presented an uneven and yielding surface, and that the leakages were caused by the defective platform furnished by the defendant."
The statement made by respondent's superintendent that in his judgment the planks would "serve the purpose all right" for the foundation if the ground were properly leveled, even though coupled with the use by plaintiff of such foundations, cannot be taken as a modification of the guaranty of the tanks against leaks before leaving the factory, especially in view of the testimony that attention was repeatedly *Page 464
called to the fact that the foundation was not level and that defendant's superintendent said "he would fix it," but that he did not do so. The evidence shows that after the tanks were completed, and during the time that the parties were considering the leaky condition of the four tanks, the cause of the leaks was entirely attributed to the faulty foundations upon which the tanks rested. The judge of the trial court made a personal examination of the tanks and presumably based his conclusions as to their fitness partly upon his observations and partly upon the testimony of witnesses. It very satisfactorily appears from the evidence that the defendant assumed the responsibility of constructing the foundations for the tanks, and that the leaks were entirely due to the faulty construction of such foundations. Plaintiff did not undertake to build and deliver unleakable tanks on the platforms furnished by the defendant. Its engagement was that the tanks would not leak at the time they were ready for delivery at its factory, which place was later changed as of the defendant's plant. The fact that after the tanks were completed and were resting upon the foundations constructed by the defendant, the plaintiff attempted to make them tight and assured defendant that they would be made tight, does not affect the original contract, but rather goes to a matter of business policy or expediency. Even at considerable cost and annoyance the plaintiff may have wished to entirely please defendant, not only for the purpose of influencing possible future business with the defendant, but for the sake of sustaining the business reputation of the plaintiff in the community in which it was transacting business. The whole question here involved depends primarily on the facts. [1] According to the findings by the lower court, those facts are all against defendant's contentions. At any rate, the court found that the platforms "were not accepted by the plaintiff; that the plaintiff assumed no obligations in regard to the foundations furnished by the defendant; that said tanks did comply with plaintiff's written guaranty and did comply with the express warranty found in Civil Code, section
The judgment is affirmed.
Conrey, P. J., and Curtis, J., concurred.
A petition by appellant to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on July 17, 1924.
All the Justices concurred.