The narrow issue is whether the trial court erred in deciding that a forfeiture clause in an earnest money agreement was not a valid liquidated damages provision. We hold that there was no error in that respect. The broader question addressed in this opinion is how the validity of such clauses is to be tested.
UNDISPUTED FACTS
Defendants owned a 373 acre ranch, which they listed for sale in July, 1978. Plaintiff viewed the property in August and on September 8 entered into an earnest money agreement to purchase the ranch for $490,000. That writing provided for an earnest money deposit of $50,000, of which $30,000 was paid at that time, and an additional $20,000 was to be paid on October 10. Plaintiff paid the additional earnest money.
The initial writing provided that closing was to occur an November 10, at which time another $124,000 was to be paid, and the defendants were to carry the balance on a contract. In mid October an addendum was added to the initial writing, extending the closing date to December 12. idaintiff was unable to perform on that date.
The basic part of the earnest money agreement was m a printed form copyrighted by the Oregon Association of Realtors and, in this instance, supplied by the listing broker md salesman. A part of the printed portion was entitled ‘FORFEITURE PROVISIONS” and, in pertinent part, was is follows:
“* * * If the said sale is approved by the seller and title to said premises is marketable, and the purchaser neglects or refuses to comply with any conditions of sale within ten (10) days from the furnishing of a preliminary title report, or make payments promptly as set forth on the reverse side hereof, then the earnest money and additional earnest money receipted for on the reverse side hereof shall be forfeited, the cost of title insurance, escrow and attorney fees paid, and the remainder divided as provided on the reverse side hereof under Sellers [sic] closing instructions and fee agreement between the seller and the REALTOR to the extent of the agreed upon fee, and the residue, if any, paid to the seller as liquidated damages and this contract shall thereupon be of no farther binding effect, or at his option, seller may seek damages or specific performance of this contract.”
When plaintiff was unable to perform on December 12, defendants advised him that they would not return the earnest money. The entire $50,000 earnest money, which had been deposited with a local title company, was released to defendants on December 13.
While the foregoing events were taking place, two other prospective purchasers had made offers to buy the ranch, but both offers had been withdrawn prior to plaintiffs failure to perform on December 12. One of those purchasers made a new offer in a writing dated December 13, and that offer was accepted by defendants on December 30. That sale closed January 25,
Plaintiff demanded return of the $50,000. Defendants refused to comply with the demand. Plaintiff then commencec this cause to recover that sum.
PROCEEDINGS IN THE TRIAL COURT
The key issue was whether the above-quoted FOR FEITURE PROVISION was valid as being a clause foi liquidated damages or invalid as being a penalty for nonper formance. The parties waived a jury, and the trial cour decided that the clause was unenforceable. The trial cour decided that defendants had suffered actual damages as i result of plaintiffs breach in the amount of $6,500, an< awarded plaintiff judgment for $43,500. 1 As a predicate fo judgment for plaintiff, the trial court made findings from the bench at the close of the trial:* 2
“THE COURT: Well, I’m going to, as I indicate, decide this case from the bench. It’s been requested I make findings. I’m going to try because of the amount of money involved. I think this case has every likelihood of appeal. I’m going to try to specifically show what I find as a finding and what I’m using as a conclusion.
* * * *
“I find that there’s no question that the Plaintiff knew that there was a forfeiture clause. I find that the failure of the sale was entirely due to the buyer. Any changes because of this contract were minor or non-existent and were not — the reason that the contract, that the sale didn’t go through, it was totally due to the buyer not having the money and not being able to come up with it. The question then comes as to whether this is a forfeiture or whether it’s liquidated damages. It’s my feeling it’s a penalty. This is a point upon where we get to the question of law which is as I say, can be corrected on appeal if necessary.
“It is difficult perhaps to anticipate or to make an effort to find what the reasonable relationship of the stipulated amount bears to the actual damages. This means difficulty due to anticipating, not mechanical difficulty. Much has been made of the fact that it costs $50,000 a year to operate the ranch. That was not considered at that time. We heard the $50,000 a year to operate the ranch actually for the first time in the trial. That $50,000 a year was not broken down and the testimony was also that it included mortgage payments. We know that mortgage payments, part of them are capital. There was attempt to break down the actual operating costs. There was discussion of this. The evidence seems pretty clear that it was just a 10 percent rule of thumb because this is the way the state did it and this was custom. I don’t think the question of backup buyers or not backup buyers are important, per se, except as to whether this could be reasonably anticipated if .they were seriously considering actual damages.”
On appeal the defendants contended that the trial court had erred in holding that, “as a matter of law,” the liquidated damages provision was a “penalty” and not an enforceable provision. They further contended that there was no evidence 3 to support the trial court’s findings of fact:
(1) That the clause was a “penalty.”
(2) That the figure of $50,000 as the yearly cost of operating the ranch was not considered at the time of making the contract.
(3) That the dollar figure chosen ($50,000) was just a 10% (of the purchase price) rule of thumb for earnest money and was the figure used by the state in its land dealings and that 10% was “custom.”
The Court of Appeals first stated what it would take as the governing rules of law as they appear from two of our fairly recent decisions and one of that court’s own decisions:
“A contract provision for liquidated damages is valid if it is designed to provide just compensation for the injured party in the event of a breach; if it goes beyond just compensation, however, it is unenforceable as a penalty. Wright v. Schutt Construction,262 Or 619 , 623,500 P2d 1045 (1972). The test is whether:
“ ‘(a) the amount so fixed is a reasonable forecast of just compensation for the harm that is caused by the breach, and
“ ‘(b) the harm that is caused by the breach is one that is incapable or very difficult of accurate estimation.’262 Or at 623 , quoting Restatement of Contracts § 339(1) (1932).
“To satisfy the first requirement, there must be a genuine preestimate of the injury; that is, the parties must make an honest and good faith effort to arrive at an accurate estimate. Dean Vincent, Inc. v. McDonough,281 Or 239 , 246,574 P2d 1096 (1978). A showing that the liquidated damages are ‘grossly disproportionate’ to actual damages is evidence that the estimate was not reasonable.281 Or at 246 . The burden of proof, however, is on the party who seeks to avoid the clause.281 Or at 249 . The question is for the trier of fact, unless reasonable minds could not disagree as to the facts and the conclusions to be drawn from them. Foster v. Peterson,42 Or App 249 , 258,600 P2d 490 (1979).”
The Court of Appeals then found there was substantial evidence to support the trial court’s findings of fact resulting in the trial court’s ruling that the clause was for a penalty:
“Here, the trial court specifically found that there was not a genuine pre-estimate of the damage that defendants would suffer should plaintiff fail to perform; rather, the amount of damages was selected on the basis of a rule of thumb that an earnest money deposit should represent 10 percent of the purchase price. There was substantial evidence in the record to support this determination, including defendants’ inability, at deposition before trial, to state the amount of their monthly expenses in operating the ranch and the fact that their actual damages were, as the evidence showed, grossly disproportionate to the proposed liquidated damages. The trial court did not err in refusing to enforcethe liquidated damages clause.” (Footnotes omitted.)
REVIEW OF DECISIONS OF THIS COURT
We allowed the defendants’ petition for review because of apparent ambiguity, if not confusion, in our pronouncements of the law applicable to this kind of case.
“Because of clashing precedent, it has become difficult to predict the result in any close case on the validity of a stipulated damages provision. The outcome often depends upon which set of conflicting rules the court chooses to follow; and in many cases the reasons for that choice have remained unarticulated.”
Layton Manufacturing v. Dulien Steel,
In the ensuing discussion we shall use the word “clause” or the word “provision” to refer to the words of a contract that set the amount of damages to be recovered by one party from another in case of the latter’s failure to perform as agreed. When we use the word “proponent” we refer to the party who desires to enforce the clause or provision as a valid liquidated damages agreement. When we use the word “opponent” we refer to the party who contends that the clause or provision is unenforceable as being for a penalty.
Although confusion in our decisions existed prior to
Medak v. Hekimian,
This court agreed that the decision of penalty or liquidated damages was “one of law for the court.”
“At the time of the making of the contract would the sum provided seem to bear any reasonable relationship to the anticipated damages and would the actual damages be difficult or impossible of ascertainment? If both answers are ‘yes,’ the sum provided would normally be considered liquidated damages. Restatement of the Law of Contracts, § 339; * *
“There would appear to be nothing reprehensible or unreasonable in the parties agreeing to a sum which would compensate plaintiffs for such actual anticipated loss in case of breach. It would certainly be actual damage of the most highly speculative type. These imponderables at the time of making a contract would seem to justify the use of a sum as liquidated damages as long as it was not disproportionate to actual anticipated damages.”
We note that although the decision cites Restatement of the Law of Contracts, § 339 (hereinafter § 339(1)), for the court’s statement of the two relevant criteria, there is a difference between the court’s formulation of the two criteria and the text of § 339(1). That text is:
“(1) An agreement, made in advance of breach, fixing the damages therefor, is not enforceable as a contract and does not affect the damages recoverable for the breach, unless
“(a) The amount so fixed is a reasonable forecast of just compensation for the harm that is caused by the breach, and
“(b) The harm that is caused by the breach is one that is incapable or very difficult of accurate estimation.”
With respect to the second criterion, the text of Medak and of § 339(1) are similar. Medak requires that the actual damages be “difficult or impossible” of ascertainment; § 339(1) requires that the harm caused by breach be “incapable or very difficult” of accurate estimation. 4 With respect to the first criterion appears the difference in concept. Medak speaks to the necessity of a “reasonable relationship” between the fixed sum and “the anticipated damages”; § 339(1) requires that the fixed sum be a “reasonable forecast” of actual harm. Medak is saying that, tested at the time of agreement on the fixed sum, the sum must bear a reasonable relationship to damages to be anticipated as of that time. The Restatement’s requirement of a reasonable forecast of “the harm that is caused by the breach” is not the same. Medak is concerned with testing validity of the provision by reference to damages to be anticipated by the parties at the time of making the contract. The Restatement is concerned with whether the parties made a reasonable forecast of the harm that actually flows from the breach:
“If the parties honestly but mistakenly suppose that a breach will cause harm that will be incapable or very difficult of accurate estimation, when in fact the breach causes no harm at all or none that is incapable of accurate estimation without difficulty, their advance agreement fixing the amount to be paid as damages for the breach is within the rule stated in Subsection (1) and is not enforceable. * * *” (Emphasis added.)
Comment e to § 339(1).
Since the time of citation to § 339(1) in Medak this court has sometimes used the “reasonable forecast” requirement of § 339(1) and sometimes the “reasonable relationship” test from the language of the decision in Medak. Often the decisions display no recognition of the difference. Chronologically, we shall briefly note what has occurred.
In
Weber v.
Anspach,
In
Harty v. Bye,
In
Wright v. Schutt Construction,
“There is general agreement * * * with the proposition that a contract provision for liquidated damages will not be declared to be a penalty because the stipulated amount to be paid as damages is more than the amount of the actual damages unless the stipulated amount is ‘grossly disproportionate,’ or has no ‘reasonable relation’ to the probable loss, as anticipated at the time of the contract.”
In
Babler Bros., Inc. v. Hebener,
In
Schlecht v. Bliss,
In
Shaw v. Northwest Truck Repair,
The next case that we discuss,
Chaffin v. Ramsey,
“It is agreed that if either seller or buyer fails to perform his part of this agreement, he shall forthwith pay to the other party hereto a sum equal to 10 per cent of the agreed price of sale as consideration for the execution of this agreement by such other party.”
“That the amount provided for as liquidated damages in the contract was not a reasonable forecast of just compensation for the possible harm which would be caused by a default of either party.
“The clause appeared on a form contract and was not bargained for by the parties.
“That the harm caused by the breach was, at the time of the contract, and now is, capable of accurate estimation.”
The case was tried without a jury and the trial judge rendered a written opinion, in which it was stated that it was undisputed that defendant had failed to comply with the contract and that the parties did not discuss the “liquidated damages” clause. The trial court then made a “finding” that the clause was “unenforceable as not bargained for and not a reasonable forecast of just compensation when actual damages could have been ascertained.” The trial court then found the amount of actual damages and gave judgment therefor on the second cause of complaint.
On direct appeal to this court by the proponents, who had recovered judgment for less than the fixed $13,000, the majority held that the test was that set forth in Medak, namely, the “reasonable relationship to anticipated damages” rule. Proceeding to reversal of the trial court, the majority first acknowledged the statement from Medak that the question of penalty or liquidated damages is one of law for the court. From that point of departure the majority moved to a statement that there must be “evidence bearing upon” the two elements necessary under the Medak “reasonable relationship” rule. The opinion goes on to indicate that the question was “open” in Oregon as to whether the proponent or opponent of the clause has the burden of proof. The opinion ends by stating that even if the proponents have that burden, they met it in this case.
We have reviewed Chaffin in some detail because it demonstrates that by 1976, only 11 years after Medak, the court was almost evenly divided as to whether the proper test was that of “reasonable relationship to anticipated damages” or “reasonable forecast of just compensation for the harm that is caused by the breach,” with the latter being modified by requirement of a “genuine pre-estimate.” Chaffin also demonstrates the almost even division of the court concerning burden of persuasion.
We then reached Layton Manufacturing v. Dulien Steel, supra. Plaintiff was proponent of the provision. Defendant raised an affirmative defense that the provision was unenforceable as being for a penalty. The trial court ultimately held for the defendant on this issue. We first stated that the question was one of law and was to be decided under the “reasonable relationship” test, for which we cited both Medak and § 339(1) as authority. We then discussed the many variables that would have been necessary to take into consideration in attempting to pre-estimate damages at the time of making the contract. We then said:
“Because it would be speculation to decide the reasonableness of the damage estimate, the party bearing the burden of proof on this question must suffer the risk of nonpersuasion; and that party here is the defendant.”
The next case to present this problem on direct appeal was
Dean Vincent, Inc. v. McDonough,
On appeal plaintiff assigned error only for denial of its motion for directed verdict. This court examined the record and found evidence from which the jury could have found that there was no reasonable forecast of just compensation for loss because of want of a genuine pre-estimate of injury. We then noted that there was evidence from which the jury could have found that $17,500 was grossly disproportionate or without reasonable relationship to the actual damage found by the jury to have occurred. On that state of the evidentiary record, we ruled that there was ample evidence to support the verdict even if the burden of pleading and proof should have been assigned to defendant.
We then discussed what the law should be with respect to allocation of the burden of pleading and proof. In that setting the discussion was dictum, but we said:
“Although this court is not unanimous in its views upon this subject, 6 it is now the opinion of the majority of its members that this court should adopt what was referred to in Chaffin (at 436) as the ‘modern view’ to the effect that parties who negotiate the terms of a contract may properly include a provision for liquidated damages and that, in the absence of proof of oppression or ‘adhesive’ circumstances, the defendant should have the burden to both plead and prove that such.a contract provision is invalid for failure to satisfy the two requirements of the rule as stated in Restatement of Contracts § 339, supra, and as previously adopted by this court.” 7 discard the concept that the question ‘whether a contractual provision is designed to operate as a penalty is a question “of law” for decision of the court.’ We do not necessarily disagree with these contentions. Because, however, no such contentions were made in this case we do not believe that this is an appropriate case to decide these questions.”
In
Dean Vincent, Inc. v. Krimm,
“[I]n the absence of ‘adhesive’ circumstances the defendant [opponent] should have the burden both to plead and prove that a provision for liquidated damages is invalid either because it did not represent a reasonable attempt to forecast just compensation for a breach or because the harm was capable of and not difficult of accurate estimation.”
RULES FOR FUTURE CASES
In the cases from
Medak
in 1965 to
Krimm
in 1979 ;his court has necessarily
During this 14 year period of decision making, some over strong dissent as in Chaffin, it appears that no case was so presented as to draw to this court’s attention the fact that the legislature had addressed the issue with respect to the sale of goods in 1961. 7 In that year the legislature passed Oregon’s version of the Uniform Commercial Code. Or Laws 1961, ch 726. The subsection on liquidated damages in contracts for the sale of goods was drawn directly from the UCC. ORS 72.7180(1) provides:
“Damages for breach by either party may be liquidated in the agreement but only at an amount which is reasonable in the light of the anticipated or actual harm caused by the breach, the difficulties of proof of loss, and the inconvenience or nonfeasibility of otherwise obtaining an adequate remedy. A term fixing unreasonably large liquidated damages is void as a penalty.”
Insofar as policy choice is concerned, enactment of the statute makes the choice, or choices, by the constitutional department of state government that is responsible to the people for that kind of choice.
It is true that the legislature’s choice, by its terms, applies only to contracts for the sale of goods, but we are unable to perceive any good reason for not using that same rule as the initial point of departure for analyzing the validity of provisions for liquidated damages in contracts in general. It may be that reasons for variance will surface in the context of litigating the validity of such provisions, but until then the courts of this state shall follow that legislative formulation in cases of this kind. Citations to cases earlier than this one that state or suggest conflicting rules are to be disregarded unless a decision cited is of assistance in interpreting the text of ORS 72.7180(1). 8
There will inevitably arise situations that require judicial interpretation of the text chosen by the legislature. We believe that guidance to necessary interpretation may be found by resort to Restatement (Second) of Contracts, § 356(1):
“Damages for breach by either party may be liquidated in the agreement but only at an amount that is reasonable inthe light of the anticipated or actual loss caused by the breach and the difficulties of proof of loss. A term fixing unreasonably large liquidated damages is unenforceable on grounds of public policy as a penalty.”
The commentary is also enlightening. The Reporter’s Note to the section makes it abundantly clear that the American Law Institute believed § 356(1) to be in harmony with subsection 2-718(1) of the Uniform Commercial Code, codified in Oregon as ORS 72.7180(1). 9
THE CASE AT BAR
The case at bar was pleaded and tried in the manner which our previous decisions recognized as being the modern rule. Plaintiff, as opponent of the validity of the clause, pleaded both that the amount fixed was not a reasonable forecast of just compensation for the defendants’ harm resulting from his failure- to perform and that the loss was not incapable or very difficult of accurate estimation. Defendants, as proponents, did plead that the loss was incapable or difficult of accurate estimation and that the amount fixed in the clause was a reasonable forecast of “anticipated” damages, but the cause was tried as if plaintiff had the burden of proof to establish the allegations in his complaint. 10 We are presently of the belief that the same result would obtain if the text of ORS 72.7180(1) were the point of departure, but it is not necessary that we here interpret or construe that text, and we do not do so.
This was an action in which the parties had a right to trial by jury. They stipulated to try the case without a jury. The findings of the trial court “have the same force and effect” and are “equally conclusive, as the verdict of a jury.” ORCP 62F. Upon appeal and on review in this court, defendants have directed our attention to evidence from which the trier of fact might have found in their favor. That could be of no concern to either the Court of Appeals or this court, however, for in these circumstances an appellate court cannot reject the findings of fact of the trial court unless the appellate court can say affirmatively that there is no evidence to support the fact found by the trial court. Defendants have argued that such is the case here, but we agree with the Court of Appeals that there was evidence, as summarized by that court,
The judgment of the Court of Appeals is affirmed.
Notes
The trial court judgment provided for interest at six percent per annum from th date of plaintiffs demand for return of the earnest money. The trial court expressl refused to award either plaintiff or defendants attorney fees, although the earnes money agreement provided:
“If suit or action is filed on this contract, the party not prevailing agrees to pay th prevailing parties reasonable attorney fees which shall be fixed by the Court < Courts in which the suit or action, including any appeal therein is tried, heard c decided.”
Plaintiff cross-appealed, assigning as error the refusal of the trial court to award to hii reasonable attorney fees and the failure of the trial court to set interest on the award
i
nine percent per annum from July 25,1979, the effective date of legislation setting th¡ figure as the legal rate of interest on a judgment of this kind. In
Illingworth v. Bushon
Certain findings adverse to contentions of the plaintiff are not included because they are not pertinent to disposition of this case or our discussion of this kind of case.
This case was tried in December, 1980. In April, 1981, we decided
Falk v Amsberry,
If the actual damages or harm is either impossible of ascertainment or incapable if accurate estimation, a fortiori, such damages or harm is “difficult” or “very iifficult” of ascertainment or estimation. We see no reason to continue to speak to impossibility or incapability; they are subsumed in the concept of difficulty.
“[EJxpected possible damages” is an interesting concept. Any event whose probability is more than zero is “possible”; however, expected “probable” damages would not meet the test that damages be difficult to estimate.
Neither the majority nor the dissent takes note that the opponent of the provision pleaded unenforceability as an affirmative defense.
See Layton Manufacturing v. Dulien Steel,
“6.
See
dissenting opinion in
Chaffin v. Ramsey,
“7. The concurring opinion contends that defendant should also have the burden of proof on the issue of ‘oppression or “adhesive” circumstances’ and that this court should
The existence of the subsection 2-718(1) of the Uniform Commercial Code codified in Oregon as ORS 72.7180(1), was recognized in the concurring opinion in
Layton Manufacturing v. Dulien Steel,
We regard it as being just as much a function of this court to keep its own law “in order” as to resolve inconsistencies of Court of Appeals decisions, whether intramural or, vis-a-vis this court, extramural.
“A fair measure of agreement has come to exist among jurists that the principal function of the top court in a three-tier judicial system is to keep the law in proper order.” (Footnote omitted. Emphasis added.)
R. Leflar, Internal Operating Procedures of Appellate Courts, page 4. See also American Bar Association Standards of Judicial Administration Relating to Appellate Courts, page 4-5, approved by the House of Delegates in February, 1977:
“In [court] systems having an intermediate appellate court, * * * the supreme court exercises a function of selective review, the purposes of which are to maintain uniformity of decision among subordinate courts and to reformulate decisional law in response to changing conditions and social imperatives.”
For analysis of subsection 2-718(1) of the Uniform Commercial Code text, we lave found helpful insight in Dean Hawkland’s A Transactional Guide to the Uniform Commercial Code, Vol. 1,170-172, and in Wallach, The Law of Sales, 1046-1053. See ilso Nordstrom, Sales, 472-474.
In their respective briefs in the Court of Appeals the parties agreed that plaintif had the burden of proof.
