(b) District certification. — The Secretary of the Department of Commerce may identify and certify microgrid districts in this state upon a finding that the following requirements are met:
(8) The requirements of subsections (d), (e), (g), (h), and (j) of this section enacted during the regular session of the Legislature, 2025, shall not apply to any microgrid district certified on or before January 1, 2024, or any special contract entered into and approved by the Public Service Commission on or before January 1, 2025. No amendments to this section enacted during the regular session of the Legislature, 2025, shall be interpreted to remove an existing microgrid district certification.
The Secretary of the Department of Commerce may not certify more than two microgrid districts: Provided, That this limit on certifying microgrid districts shall not apply to any microgrid district wherein greater than 70% of the electricity generated within the microgrid district is consumed by one or more high impact data centers, as defined in §11-6N-2 of this code, or will be consumed by one or more high impact data centers, when such data centers are completed and fully operational. A designation made pursuant to this section by the secretary as to the certification of a microgrid district is final.
(c) Providing electric service within a certified microgrid district. — Within a microgrid district, any person, firm, corporation, or entity or their lessees and tenants seeking to provide electric service through the generation or distribution of electricity within the microgrid district to businesses locating within the microgrid district may:
(d) Microgrid customers; eligibility. — In order to take advantage of the provisions of this section, a plant or facility choosing to locate and operate within a microgrid district must constitute new electric load. Any owner, lessee, or tenant of a plant or facility that has not previously received electric service from a regulated public electric utility located within this state, or who is making a capital investment in a new facility within the microgrid district shall be considered eligible new electric load. Electric service to any such plant or facility shall be considered new electric load so long as any customer making a new capital investment within the microgrid district does not decrease the load of an existing facility outside the microgrid district in this state in conjunction with the new capital investment within the microgrid district, and regardless of whether or not a person or entity previously received service from a public electric utility at or near the same location prior to the certification of the microgrid district.
An eligible plant or facility choosing to locate and operate within a microgrid district is not required to connect with and use any public electric utility: Provided, That any connection with and use of a public electric utility for purposes of the initial construction and development within the microgrid district shall not impact a plant or facility's status as new electric load in order to take advantage of the provisions of this section.
(e) Microgrid customers; special contracts and rates. — After certification of a microgrid district, the Public Service Commission may approve special contracts for a a microgrid customer within the microgrid district. For purposes of this section, a “special contract” is:
(2) electric utility service terms and conditions, including rates, ordered by the Public Service Commission that vary from the electric utility’s tariff to be in effect between a utility and an eligible retail electric microgrid customer when the electric utility and the eligible retail electric microgrid customer are unable to negotiate a written agreement.
A microgrid customer seeking a special contract shall first enter into negotiations with the utility within whose service territory the microgrid district is located regarding the terms and conditions of a mutually agreeable special contract. If the negotiations result in an agreement between the microgrid customer and the utility within 120 days, the microgrid customer and the utility shall jointly file with the Public Service Commission the special contract. If the negotiations are unsuccessful in the 120-day period, the microgrid customer may file a petition with the Public Service Commission to consider establishing a special contract. The Public Service Commission shall consider all relevant factors in establishing a special contract. Upon the filing of a petition pursuant to this section, the Public Service Commission shall establish a special contract for the provision of requested service, including backup and supplemental service to a microgrid customer within the microgrid district. Microgrid customers’ load within the microgrid district not covered by a contract for back up and supplemental service shall be considered non-firm and interruptible. The Public Service Commission shall establish a special contract upon the filing of a petition pursuant to this section and shall do so within 90 days of filing.
(g)