- (1) Upon receipt of loan funds, the recipient shall carry out the alteration or relocation work for which the loan was approved to completion in a timely and expeditious manner in accordance with a schedule approved by the department.
- (2) The recipient may not suspend or delay work without approval of the department.
- (3) The department may not unreasonably withhold approval for suspension or delay of the recipient’s work if there is just cause for the delay or suspension.
History
History: Cr. Register, January, 1991, No. 421, eff. 2-1-91.