Every authority shall submit the following information in an application for a certificate of public convenience and necessity that is required before the authority may issue bonds:
- (1) A description of the project for which bonds are being issued, including a map showing proposed and existing facilities, and the location of floodplain areas.
- (2) Information concerning applicable environmental factors for affected lands, such as land use zoning, forest lands, rivers, streams and wetlands.
- (3) The purpose and necessity of the project, with supporting data including project start and end dates.
- (4) The effect of the project on quality and reliability of service.
- (5) A brief description and analysis of the alternatives to the project.
- (6) The cost of the project by major plant categories or functions.
- (7) The proposed method of financing the project including all terms and conditions.
- (8) The estimated annual operating costs of the project, by major expense categories and functions.
- (9) A description of and the original cost of any property being replaced, by major plant categories or functions.
History
History: Cr. Register, August, 1999, No. 524, eff. 9-1-99.