In this section, “meter” or “meters” may refer to metering system(s).
(1) Polyphase meters used with instrument transformers, together with associated equipment such as demand equipment, pulsing devices, phase-shifting transformers, control devices, etc., shall be tested on the customer’s premises, a central testing facility or in a mobile test facility, except for pars. (a) and (d), for accuracy at unity and 50% power factor under the following circumstances.
- (a) Before being placed in service. For new meters given a prior test by the manufacturer, the manufacturer’s certified test results may be substituted for this requirement.
- (b) When they are suspected of being inaccurate or damaged.
- (c) When the accuracy is questioned by a customer. (See s. PSC 113.0922.)
- (d) When they are removed from service.
- (e) Within a period of 4 months before or 4 months after 2 years of service for non-magnetic-bearing electromechanical meters, 4 years of service for electromechanical magnetic-bearing surge-proof meters and 6 years of service for completely solid state electronic meters with electronic registers capable of down-loading voltage and current monitoring readings from the instrument transformers to digital meter reading devices at meter reading intervals. Exception: Electronic (solid state) meters may be tested instead in accordance with the plan outlined in s. PSC 113.0921.
- (2) A stator balance test shall be performed on all new meters before being placed in service.
- (3) Meters with electronic programmable registers may be shop tested on a periodic basis.
History
History: Cr. Register, July, 2000, No. 535, eff. 8-1-00; CR 02-027: am. (1) (intro.) and (a), Register December 2002 No. 564, eff. 1-1-03.