- (1) The test of any unit of metering equipment shall consist of a comparison of its accuracy with a standard of known accuracy by a qualified person. Units not properly connected or not meeting the accuracy or other requirements of ss. PSC 113.0811, 113.0812 and 113.0813 at the time of test shall be reconnected and/or rebuilt to meet such requirements and adjusted to within the required accuracy and as close to 100% accurate as practicable or their use discontinued.
- (2) Each unit of metering equipment shall be inspected for mechanical and electrical faults whenever the accuracy of the device is checked.
- (3) Each meter tested shall have the register and the internal connections checked before the meter is first placed in service and whenever the meter is repaired.
- (4) Each meter shall have the connections to the customer’s circuits, the disc rotation and any multiplier checked when the meter is installed or removed or an instrument transformer is changed.
- (5) Polyphase meters shall be tested for accuracy at 50% power factor before first being used for measuring customer’s service either by a test of each meter or by a sample test plan approved under s. PSC 113.0911 (1) (a).
- (6) The connections, phase sequence and multiplier of polyphase transformer-rated metering installations shall be checked for error by qualified personnel within 60 days after the meter is installed.
- (7) Special control devices, switches, etc., for time-of-use service shall be checked for proper operation whenever the associated meter is tested.
History
History: Cr. Register, July, 2000, No. 535, eff. 8-1-00.