- (1) Lowest responsible bidder. The award of a contract for a procurement shall be made to the lowest responsible bidder, taking into account qualified bids from sheltered workshops, small businesses, and minority businesses.
- (2) Rejection of bids. Any, and all, bids may be rejected. The reason for rejection shall be documented and made a part of the bid file.
- (3) Discounts for early payment. Discounts for early payment may be taken into account in making awards only when all other conditions are equal.
- (4) Tied bids. In the case of tie bids, an award shall be made to Wisconsin suppliers, in preference to out-of-state suppliers, as provided in s. 16.75 (1) (a), Stats. If the tie is between 2 Wisconsin bidders or 2 non-Wisconsin bidders, the successful bidder shall be selected by chance as determined by a witnessed and documented drawing of names or its equivalent.
History
History: Cr. Register, September, 1986, No. 369, eff. 10-1-86.