Wis. Admin. Code § ATCP 33.10
(1) Filing required. At least 21 days before an operator constructs or substantially alters a structure at a storage facility, the operator shall file all of the following with the department:
(c) The approximate date on which the operator plans to start the construction or alteration. The operator may not start the construction or alteration before that date unless the operator gives the department prior notice of the new start date. The department may request additional schedule information, as necessary, in order to schedule an inspection under sub. (3).
Note: Subsection (1) does not apply to the routine repair or maintenance of an existing structure. See s. ATCP 33.01 (34). This chapter does not require an operator to take soil samples before the operator constructs or substantially alters a structure. However, an operator may wish to do so in order to maintain cost reimbursement eligibility under s. ATCP 35.04.
History: CR 05-108: cr. Register October 2006 No. 610, eff. 11-1-06.