- (1) Commission basis reports are due within four months of the end of a utility's fiscal year.
(2) The intent of the commission basis report is to depict the gas operations of a gas utility under normal temperature and power supply conditions during the reporting period. The commission basis report must include:
- (a) Booked results of gas operations and rate base, and all the necessary adjustments as accepted by the commission in the utility's most recent general rate case or subsequent orders;
- (b) Results of operations adjusted for any material out-of-period, nonoperating, nonrecurring, and extraordinary items or any other item that materially distorts reporting period earnings and rate base; and
- (c) Booked revenues and power supply expenses adjusted to reflect operations under normal temperature and power supply conditions before the achieved return on rate base is calculated.
- (3) Commission basis reports should not include adjustments that annualize price, wage, or other cost changes during a reporting period, nor new theories or approaches that have not been previously addressed and resolved by the commission.
- (4) Each utility must submit the basis of any cost allocations and the allocation factors necessary to develop the commission basis results of gas operations for the state of Washington.
[Statutory Authority: RCW 80.01.040, 80.04.160, 81.04.160 and 34.05.353. WSR 05-06-051 (Docket No. A-021178 and TO-030288, General Order No. R-518), § 480-90-257, filed 2/28/05, effective 3/31/05.]