Wash. Admin. Code § 480-100-645
(2) Approval process. The utility's CEIP and biennial CEIP update filing will be set for an open public meeting. On the commission's own motion or at the request of any person who has a substantial interest in the subject matter of the filing, the commission will initiate an adjudication, or if appropriate a brief adjudicative proceeding, to consider the filing. The commission will enter an order approving, rejecting, or approving with conditions the utility's CEIP or CEIP update at the conclusion of its review. The commission may, in its order, recommend or require more stringent targets than those the utility proposes.
[Statutory Authority: RCW 80.01.040, 80.04.160, and chapters 80.28, 19.280, and 19.405 RCW. WSR 21-02-022 (Dockets UE-191023 and UE-190698, General Order 601), § 480-100-645, filed 12/28/20, effective 12/31/20.]