(1) Complete streets program projects will have five phases. Each phase will require specific documentation as described below and each phase must be approved before the applicant agency is eligible to receive the related funding:
(3) An electronic signature shall have the same force and effect as a manual signature on all agreements, forms, and other documents submitted in support of a project under this chapter. For purposes of this section, an "electronic signature" has the same meaning as in RCW 1.80.010(10).
TIB will provide documents for the city or county to sign and return.
All necessary project cost documentation must be received prior to final payment.