The board and executive director will consider the following when reviewing increase requests:
- (1) Whether the granting of the request will obligate funding beyond an acceptable level or will adversely affect authorized funds previously approved by the board.
- (2) Whether the request would fund expansion of the scope of work beyond that approved at design phase.
- (3) Whether the local agency should have anticipated an increase would be necessary at the outset of the project.
- (4) Requests for increases at construction approval phase will take priority over other phase requests.
- (5) Local agency funding partner ability to contribute to the increased costs.
- (6) Other criteria on a case-by-case basis.
[Statutory Authority: Chapter 47.26 RCW. WSR 23-08-032, § 479-05-203, filed 3/28/23, effective 4/28/23; WSR 07-18-050, § 479-05-203, filed 8/30/07, effective 9/30/07.]