The executive director may approve scope changes except the following which require the board's approval:
- (1) A change in the project limits with a request for an increase in funding beyond the executive director's administrative authority in WAC 479-01-060;
- (2) Adding or decreasing through lanes;
- (3) Adding or eliminating grade separations;
- (4) Reducing limits greater than one hundred lineal feet;
- (5) Inclusion or exclusion of major project element that may be considered a scope change by the executive director; or
- (6) Changes to project components that were used to rate the project.
[Statutory Authority: Chapter 47.26 RCW. WSR 07-18-050, § 479-05-052, filed 8/30/07, effective 9/30/07.]