- (1) The prime contractor shall submit a monthly inclusion report to WSDOT, documenting each MWBE on the contract, the MWBE's original and current contract value, invoice to date, and total payments to date.
- (2) The prime contractor shall provide an inclusion manager responsible for developing, overseeing, and managing a contract inclusion program and the inclusion plan, which describes and defines the process for attaining the MWBE goals.
- (3) The inclusion plan shall be submitted to WSDOT within 30 days of initiating contract work, and be updated annually, thereafter, until project physical completion.
[Statutory Authority: RCW 39.04.155, 43.19.727, 47.01.101, 47.28.030, and chapter 39.19 RCW. WSR 24-05-030, § 468-19-060, filed 2/12/24, effective 3/14/24.]