The following list of deficiencies may be considered cause for a determination that an unsatisfactory record of performance exists:
- (1) Failure to complete project on time; or
- (2) Continued workmanship below the level of standard; or
- (3) Failure to adhere to the plans and specifications; or
- (4) Disregard for the welfare or safety of traveling public; or
- (5) Inadequate supervision and control of subcontractors; or
- (6) Insufficient supervision available on project site; or
- (7) Inadequate coordination and planning with owner; or
- (8) Inadequate procurement and delivery of supplies and materials; or
- (9) Inadequate control and utilization of equipment; or
- (10) An overall performance rating in the performance report of less than standard as defined in WAC 468-16-030 and 468-16-150.
[Statutory Authority: RCW 47.28.070. WSR 25-23-007, s 468-16-040, filed 11/6/25, effective 12/7/25. Statutory Authority: RCW 47.01.101, 47.28.030 and 47.28.070. WSR 93-03-020 (Order 134), § 468-16-040, filed 1/12/93, effective 2/12/93; WSR 91-04-014 (Order 128), § 468-16-040, filed 1/28/91, effective 2/28/91.]