Wash. Admin. Code § 463-68-060
If construction does not both start within five years of the effective date of the site certification agreement and thereupon continue in a reasonably uninterrupted fashion toward project completion, then at least 90 days prior to the end of the five-year period, the certificate holder shall report to the council its intention to proceed or not to proceed with the project. If the certificate holder intends to proceed with the project, the certificate holder shall submit a report to the council describing:
(1) The nature and degree of any changes to the following since the effective date of the site certification agreement:
[Statutory Authority: RCW 80.50.040(1). WSR 25-12-020, s 463-68-060, filed 5/22/25, effective 6/22/25. Statutory Authority: RCW 80.50.040 (1) and (12). WSR 04-21-013, § 463-68-060, filed 10/11/04, effective 11/11/04.]