Wash. Admin. Code § 344-12-098
The properties, use, and testing of drilling fluids and the conduct of related drilling procedures shall be such as are necessary to prevent the blowout of any well. Sufficient drilling fluid materials to insure well control shall be maintained in the field area readily accessible for use at all times.
(2) Drilling fluid testing. Mud testing and treatment consistent with good operating practice shall be performed daily or more frequently as conditions warrant. The following drilling fluid system monitoring or recording devices shall be installed and operated continuously during drilling operations, with mud, occurring below the shoe of the conductor casing:
[Statutory Authority: RCW 78.52.050. WSR 85-03-018 (Order 6, Resolution No. 10), § 344-12-098, filed 1/8/85. Statutory Authority: RCW 78.52.050 and chapter 78.52 RCW. WSR 82-12-052 (Order 3, Resolution No. 7), § 344-12-098, filed 6/1/82.]