Time frames for compliance with Part D or ASME A17.3 (or combination thereof) as applicable.
- (1) These time frames do not apply to maintenance and periodic testing as required by ASME A17.1/CSA B44, Section 8.6.
(2) Where a single unit is required to comply with multiple requirements or a group of units is required to comply with multiple requirements on one or more conveyances, the owner shall:
- (a) Have twenty-four months/two years in which to come into compliance; or
- (b) Submit a written plan within twenty-four months indicating the projected time frame in which to comply.
- (3) Where conveyances are targeted for alterations upon complying with subsection (2)(b) of this section, the owner may delay implementation of the requirements of Part D or ASME A17.3 (or combination thereof) until such time when the alteration is permitted by the department.
(4) The owner shall have a maximum of 60 months/5 years in which to come into compliance with the following:
- (a) ASME A17.3 requirement 3.10.12 System to Monitor and Prevent Automatic Operation of the Elevator with Faulty Door Contact Circuits.
- (b) Where Firefighters' Emergency Operation is required by ASME A17.3, requirement 3.11.3 (note: ASME A17.3, requirement 3.11.3 only pertains to elevators where Firefighters' Emergency Operation does not comply with the 1987 or later editions of ASME A17.1 or ASME A17.1/CSA B44. There is no requirement to add Firefighter's Emergency Operation (FEO) under ASME A17.3 if the elevator was not provided with FEO during the initial installation).