(1) To have construction documents reviewed the applicant must submit to the department of health:
- (a) A completed and signed application, on a form provided by the department of health, for each structure (individual building);
- (b) The required plan review fee, according to WAC 246-359-990;
(c) Two sets of construction documents, on substantial paper, including:
- (i) Plans and diagrams drawn to scale;
- (ii) Specifications;
- (iii) Computations; and
- (iv) Other documents needed to determine if the provisions of this chapter and related state rules are being met, for example solid waste disposal management plan or soil testing;
- (d) When applicable, manufacturer's installation instructions as required for factory assembled structures, WAC 246-359-710, and manufactured homes, WAC 246-359-720;
- (e) Proof of an adequate approved potable water supply to meet the intended use of the TWH and which meets the requirements of chapters 246-290 and 246-291 WAC (water rules) and WAC 296-307-16130;
- (f) Copy of the on-site sewage system permit from the jurisdiction having authority;
- (g) Proof of a water right permit from the department of ecology, when required;
- (h) Proof of current approval from the department of labor and industries, when required, for factory assembled structures; and
- (i) Proof the project meets zoning requirements as established for height, setback and road access under the authority having jurisdiction.
- (2) The plans and specifications must clearly identify in detail the location, nature and extent of the work proposed.
(3) The department of health will only begin plan review when:
- (a) All the documents required in this section are submitted; and
- (b) The plan review fee is received.
- (4) The department of health can refund up to eighty percent of the plan review fee if the applicant submits a written request to stop the project before the plan review process is complete. Refunds are based on the plan review fee paid as required by Table I in WAC 246-359-990 and the amount of plan review completed as determined by the department.
(5) The department of health will charge an additional plan review fee according to Table I in WAC 246-359-990, when:
- (a) Site inspections determine the project has not been built according to the approved construction documents and an additional plan review is required; or
- (b) Revised construction documents are submitted after approval of the initial construction documents.
[Statutory Authority: Chapter 70.114A RCW and RCW 43.70.334 through 43.70.340. WSR 15-13-091, § 246-359-070, filed 6/15/15, effective 1/1/16. Statutory Authority: RCW 70.114A.081. WSR 99-03-065, § 246-359-070, filed 1/18/99, effective 2/18/99.]