Wash. Admin. Code § 222-24-030
(1) Right of way timber shall be removed or decked in suitable locations where the decks will not be covered by fill material or act as support for the fill or embankment.
(3) Compact fills. During road construction, fills or embankments shall be built up by layering. Each layer shall be compacted by operating the tractor or other construction equipment over the entire surface of the layer. Chemical compacting agents may be used in accordance with WAC 222-38-020.
(b) Uncompleted road construction to be left over the winter season or other extended periods of time shall be drained by outsloping or drainage structures. Water bars and/or dispersion ditches may also be used to minimize eroding of the construction area and stream siltation. Water movement within wetlands must be maintained.
*(7) Moisture conditions. Construction shall be accomplished when moisture and soil conditions are not likely to result in excessive erosion and/or soil movement, so as to avoid damage to public resources.
*(8) End haul/sidecasts. End haul or overhaul construction is required where significant amounts of sidecast material would rest below the 100-year flood level of any typed water, within the boundary of a Type A or Type B Wetland or wetland management zones or where the department determines there is a potential for mass soil failure from overloading on unstable slopes or from erosion of side cast material causing damage to the public resources.
*(9) Waste disposal. When spoil, waste and/or other debris is generated during construction, this material shall be deposited or wasted in suitable areas or locations and be governed by the following:
(10) Disturbance avoidance for northern spotted owls. Road construction, operation of heavy equipment and blasting within a SOSEA boundary shall not be allowed within 0.25 mile of a northern spotted owl site center between March 1 and August 31, provided that, this restriction shall not apply if:
(11) Disturbance avoidance for marbled murrelets.
*(4) Stabilize soils. Erodible soil disturbed during road construction and located where it could reasonably be expected to enter the stream network must be seeded with noninvasive plant species. The use of local area native species, adapted for rapid revegetation is preferred. Treatment with other erosion control measures may be approved by the department.
*(5) Channel clearance. Within 50 feet upstream from a culvert inlet clear stream channel of all debris and slash generated by the operations that reasonably may be expected to plug the culvert prior to the removal of equipment from the vicinity, or the winter season, whichever is first. (See the board manual, section 4 for debris removal guidelines.)
*(6) Drainage.
*(2) In permanent road construction, do not bury:
[Statutory Authority: Chapter 34.05 RCW, RCW 76.09.040, [76.09.]050, [76.09.]370, 76.13.120(9). WSR 01-12-042, § 222-24-030, filed 5/30/01, effective 7/1/01. Statutory Authority: RCW 76.09.040 and chapter 34.05 RCW. WSR 97-24-091, § 222-24-030, filed 12/3/97, effective 1/3/98; WSR 97-15-105, § 222-24-030, filed 7/21/97, effective 8/21/97. Statutory Authority: Chapters 76.09 and 34.05 RCW. WSR 96-12-038, § 222-24-030, filed 5/31/96, effective 7/1/96. Statutory Authority: RCW 76.09.060, 76.09.040 and chapter 34.05 RCW. WSR 92-23-056, § 222-24-030, filed 11/17/92, effective 12/18/92. Statutory Authority: RCW 76.09.040, 76.09.050 and chapter 34.05 RCW. WSR 92-15-011, § 222-24-030, filed 7/2/92, effective 8/2/92. Statutory Authority: RCW 76.09.040. WSR 87-23-036 (Order 535), § 222-24-030, filed 11/16/87, effective 1/1/88. Statutory Authority: RCW 76.09.040 and 76.09.050. WSR 82-16-077 (Resolution No. 82-1), § 222-24-030, filed 8/3/82, effective 10/1/82; Order 263, § 222-24-030, filed 6/16/76.]