Wash. Admin. Code § 194-37-170
(1) Each utility must document its calculation of the levelized annual incremental cost of eligible renewable resources. Utilities are encouraged, but not obligated, to use the following methodology:
Step 1: Calculate the net present value of the cost of the utility's eligible renewable resource and substitute resource over an equivalent contract length or facility life.
Step 2: Calculate equal nominal values over the appropriate contract length or facility life that have a net present value equal to those calculated in Step 1, using the same discount rate.
Step 3: Calculate the annual difference between the levelized delivered cost for the eligible renewable resource and the substitute resource to determine the levelized incremental cost of the eligible renewable resource.
A utility that uses the annual update methodology must document the basis for any change to the levelization methodology used in a prior June 1 report to levelize the costs of an eligible renewable resource and its associated substitute resource.
[Statutory Authority: RCW 19.285.080(2). WSR 08-07-079, § 194-37-170, filed 3/18/08, effective 4/18/08.]