Wash. Admin. Code § 173-900-335
(1) The authority or authorized party must update or revise the plan in the following situations:
(2) Five-year renewal: The authority or authorized party must:
(3) Failure to provide service:
(a) Failure to provide service means implementation of the plan fails to do any of the following:
(b) If the authority or authorized party of a plan, through implementation of the plan fails to provide services, the authority or authorized party must submit an updated plan to ecology within sixty days of failing to provide service.
(4) Revisions or updates to the plan: The authority or authorized party must submit a plan revision, including nonsignificant and significant plan revisions, to ecology within sixty days of any changes to the plan or receiving notice from ecology that an update is required.
(c) Significant revisions submitted and ecology approval is required: Significant revisions to CEP recycling plans are identified in Table 335 below. Ecology must approve the significant revisions prior to implementation.
Table 335
CEP Recycling Plan Revisions
| Plan Content | Nonsignificant Revisions | SignificantRevisions |
| Submitted but no approval required to implement | Submitted and approval is required toimplement | |
| Binding agreement | Changes to manufacturers participating in the plan or changes to contact information for manufacturers already included in the plan. | No revisions requiring approval. |
| Standard plan participant assessment of charges or apportionment of costs | No nonsignificant revisions. | Any changes to the assessment of charges or apportionment of costs. |
| Letter of certification | Changes to the contact information included for manufacturers already participating in the plan. | Addition or withdrawal of manufacturers participating in an independent plan. |
| Use of Washington businesses | Any changes to the use of Washington state businesses. | No changes requiring approval. |
| Collection services | Addition of collection site(s) or services without eliminating or changing existing services. | Changes to the level of services provided by the plan other than additional services. |
| Collectors | Any addition or change to registered collectors used by the plan. | No changes requiring approval. |
| Transporters | Adding, changing or removing registered transporters used by the plan. | No revisions requiring approval. |
| Direct processors | Any additions or changes to direct processors already used by an approved plan. | Use of a direct processor not already registered under this chapter. |
| Direct processor compliance audit report | Submission of copies of audit reports for any direct processor the plan uses after the plan was last approved or the plan's annual report was last submitted. | No revisions requiring approval. |
| Design for recycling | Any changes to the description of design for recycling included in the plan. | No revisions requiring approval. |
| Direct processor contract face sheet | Submission of copies of the contract face sheet as required in WAC 173-900-320(12) for any direct processor the plan uses after the plan was last approved or the plan's annual report was last submitted. | No revisions requiring approval. |
| Recordkeeping | Any changes to recordkeeping. | No revisions requiring approval. |
| Implementation timeline | No nonsignificant revisions. | Any changes to the implementation timeline. |
| Public outreach and marketing requirements | Additional public outreach and marketing efforts. | Any changes to the public outreach plan, other than additional public outreach and marketing. |
| Fair compensation | Any changes to fair compensation. | No changes requiring approval. |
(5) Approval process: Within sixty days after receipt of a plan revision or update requiring approval, ecology will determine whether the plan complies with this chapter. Ecology will determine if the revision or update is:
(b) Disapproved. If disapproved, ecology will send a letter of disapproval to the authority or authorized party via certified mail. The disapproval letter will provide ecology's reasons for not approving the plan.
(6) Approval criteria: Ecology will consider the following when reviewing a plan revision or update for approval:
[Statutory Authority: Chapters 70.95N, 70.105, and 70.105D RCW. WSR 07-21-013 (Order 07-05), § 173-900-335, filed 10/5/07, effective 11/5/07.]