- (1) Before construction, a detailed plan must be submitted to the department showing how adequate and competent construction inspection will be provided.
(2) The construction quality assurance plan shall include:
- (a) Construction schedule with a summary of planned construction activities, their sequence, interrelationships, durations, and terminations.
- (b) Description of the construction management organization, management procedures, lines of communication, and responsibility.
- (c) Description of anticipated quality control testing including type of test, frequency, and who will perform the tests.
- (d) Description of the change order process that includes who will initiate change orders, as well as who will review, negotiate, and approve change orders.
- (e) Description of the technical records handling methodology that includes where plans and specifications, as-built drawings, field orders, and change orders will be kept.
- (f) Description of construction inspection program that includes inspection responsibility, anticipated inspection frequency, deficiency resolution, and inspector qualifications. (See also, WAC 173-240-075.)
[Statutory Authority: RCW 90.48.110. WSR 00-15-019 (Order 00-07), § 173-245-055, filed 7/11/00, effective 8/11/00. Statutory Authority: RCW 90.48.035. WSR 87-04-020 (Order DE 86-34), § 173-245-055, filed 1/27/87.]