- (1) Before construction a detailed plan must be submitted to the department that shows how adequate and competent construction inspection will be provided.
(2) The construction quality assurance plan shall include a:
- (a) Construction schedule with a summary of planned construction activities, their sequence, interrelationships, durations, and terminations.
- (b) Description of the construction management organization, management procedures, lines of communication, and responsibility.
- (c) Description of anticipated quality control testing that includes type of test, frequency, and who will perform the tests.
- (d) Description of the change order process that includes who will initiate change orders, as well as who will review, negotiate, and approve change orders.
- (e) Description of the technical records handling methodology that includes where plans and specifications, as-built drawings, field orders, and change orders will be kept.
- (f) Description of the construction inspection program that includes inspection responsibility, anticipated inspection frequency, deficiency resolution, and inspector qualifications.
[Statutory Authority: RCW 90.48.110. WSR 00-15-021 (Order 00-09), § 173-240-075, filed 7/11/00, effective 8/11/00. Statutory Authority: Chapters 43.21A and 90.48 RCW. WSR 83-23-063 (Order DE 83-30), § 173-240-075, filed 11/16/83.]